Q A.docx
DOCX document 13 KB Posted
- Solicitation number
- AG-32SC-S-14-0012
About this file
Questions and Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site_Visit_Participants.pdf | ||
| SOW.pdf | ||
| SF24.pdf | ||
| ARS372.pdf | ||
| SF25a.pdf | ||
| Wage_Determination.pdf | ||
| AG-32SC-S-14-0012.pdf | ||
| SF1413.pdf | ||
| SFLLL.pdf | ||
| Past_Performance.pdf | ||
| ARS371.pdf | ||
| SF25.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question #1:
Does the Combined Synopsis/Solicitation under solicitation number AG32SCS140012 contain requirements similar to a current contract? If possible, please provide the current contract number. Or, is this a new requirement for the government?
Answer:
This is a new requirement.
Question #2:
If a new station is installed, who will remove and replace the sheetrock end wall of the pump room?
Answer:
Arboretum staff will remove and replace the wall.
Question #3:
Does the work include servicing the Y strainer?
Answer:
Yes, service or replace the Y strainer assembly.
Question #4:
Timing of work and how long can water be off?
Answer:
Contractor should provide a timeline of projected water outage. The time of year and the duration of the outage will dictate scheduling of work, if a complete water outage is required.
Question #5:
Will a temporary water bypass be required?
Answer:
Depends on the answer to question #3.