CvrPg_AG-32KW-S-14-0091_Amend_1.pdf
PDF 84 KB Posted
- Solicitation number
- AG-32KW-S-14-0091
About this file
Responses to Offerors Questions
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CvrPg_AG-32KW-S-14-0091_Amend_2.pdf | ||
| Attach_3_DavisBaconPresidioTX.pdf | ||
| Attach_1_Statement_of_Work.pdf | ||
| CvrPg_AG-32KW-S-14-0091.pdf | ||
| Attach_2_Clauses.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
AG-32KW-S-14-0091
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
APHIS-MRPBS-ASD-ESB
EDINBURG TX 78541
BLDG 6407
22675 N. MOOREFIELD RD.
APHIS MRPBS CONSTRUCTION CONTRACTIN
06/17/2014000001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/17/2014
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Tax ID Number: Not Available
DUNS Number: Not Available
1. The purpose of this amendment 000001 to the above referenced solicitation is to respond to pre-proposal questions.
Is there a preference as to whether the scale is mechanical in nature or if a digital weight readout is requested?
There is no preference; however, we do want its operation to be efficient while producing an accurate readout.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
MARTHA GARZA
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
AG-32KW-S-14-0091/000001
If so, will there be 110VAC power supplied?
There is currently no power source at specific location, a power pole with the electric meter supplying the personnel trailer is the closest source about 100 feet away.
I assume this is government property, so is "permitting" necessary and if so we would need to provide?
No permitting necessary
Would a capacity of 20,000 lbs. be sufficient?
Yes
What security clearances, if any will be required for our technicians and / or sub-contractors?
None provided or necessary
Requests state that the new scale would be located next to an existing livestock pen with a pass through is there an existing concrete slab/pad for the pass through or existing pen and if so do we know the profile?
The pass through does not have an existing concrete slab/pad. This is where we need the expertise of the contractors in whether to build slopes leading to the slab/pad for the cattle to safely travel or maybe landings instead.
If not, is there a suggested profile for the scale concrete pad, due to it being on a "flood plain"?
We need the contractors' expertise to provide best way to deal with it being on a flood plain.
2. All offerors are required to acknowledge receipt of this amendment 000001.
3. The closing date REMAINS as July 21, 2014.