Site Showing Notes 07292010.docx
DOCX document 14 KB Posted
- Solicitation number
- AG-2C31-S-10-0008
About this file
Notes from Site Showing held 7/29/2010
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract of Offers.pdf | ||
| Duengfelder_Approved Drawings.pdf | ||
| Duengfelder_Construction Specifications.pdf | ||
| Solicitation Package.pdf | ||
| Wage Rates - Erie County.pdf | ||
| SF1442.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Emergency Watershed Protection (EWP) Site Showing Notes – July 29, 2010 Town of Concord / Duengfelder
AG-2C31-S-10-0008
NRCS Representatives in attendance: Lauri Eipp, Contracting Officer; Mike Shinnick, Engineer; and Dan Bennett, Engineer; John Whitney, District Conservationist; Jim Bielli, Student Intern.
Lauri review contract requirements:
· Federal Contract (different that state and local) – but sponsored by Erie County
· OSHA + additionally NRCS Safety requirements apply
· Must submit safety plan and someone certified in first aid on site at all times.
· Davis Bacon wage rates – must submit certified payrolls
· Encouraged all interested to download entire contract package including Plans and specs on Federal Business Opportunities website
· Cost estimated at less than $100K - No bid bond required
· Payment bond required after award by successful low bidder (50% of bid price)
· August 5 bid opening at 11:45 a.m.
· Successful contractor must register in the Central Contractor Registration (CCR) database
· 8 day performance time from point notice to proceed issued
· Have 3 days to mobilize
· No Sunday work
· Taxable job – contractor is not exempt from paying local/state sales tax on materials
· Only bid on those projects you want and are capable to perform - if you bid on them all you will be expected to perform on them all within the stated performance time.
· Be sure to sign Bid Form – SF 1442
Dan covered technical requirements:
· Debris must be removed from site.
· Rock chute detail
· Gravel bars supply fill
· Bedding is what is is
· Same fill
· 4’ x 3’ x 3’ to instead of normal 3x3x3
· 2 rock items
· NRCS will layout and will check grades for our convenience and share
· Contract is responsible for route grade control
· Staging and access
Questions:
Q –On when performance time begins?
A - Anticipate contract award day after opening. Contractor will then have 7 days to submit payment bond, register in the CCR database (in not already), submit Erosion and Sediment Control Plan, and have a preconstruction meeting with the COTR and/or Inspector. Would then issue Notice to proceed on day 8 which gives contractor 3 days to begin work. Once being performance time starts. Will be flexible on issuing notice to proceed so that the three days would not have contractor starting on a Friday or Saturday.
File details come from the government source that posted it. Updated .