Notes from Site Showing held 7/29/2010
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract of Offers.pdf | ||
| Site Showing Notes 07292010.docx | DOCX document | |
| Amendment 2.pdf | ||
| Amendment 1.pdf | ||
| Wage Rates - Erie County.pdf | ||
| Solicitation Package.pdf | ||
| Back Creek S of Patchin_Construction Specifications.pdf | ||
| Back Creek_Approved Drawings.pdf | ||
| SF1442.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Emergency Watershed Protection (EWP) Site Showing Notes – July 29, 2010 Town of Concord / South of Patchin
AG-2C31-S-10-0007
NRCS Representatives in attendance: Lauri Eipp, Contracting Officer; Mike Shinnick, Engineer; and Dan Bennett, Engineer; John Whitney, District Conservationist; Jim Bielli, Student Intern.
Lauri review contract requirements:
· Federal Contract (different than state and local) – but sponsored by Erie County
· OSHA + additionally NRCS Safety requirements apply
· Must submit safety plan and someone certified in first aid on site at all times.
· Davis Bacon wage rates – must submit certified payrolls
· Encouraged all interested to download entire contract package including Plans and specs on Federal Business Opportunities website
· Cost estimated at less than $100K - No bid bond required
· Payment bond required after award by successful low bidder (50% of bid price)
· August 5 bid opening at 11:30 a.m.
· Successful contractor must register in the Central Contractor Registration (CCR) database
· 8 day performance time from point notice to proceed issued (will change to 12 days)
· Have 3 days to mobilize
· No Sunday work
· Taxable job – contractor is not exempt from paying local/state sales tax on materials
· Only bid on those projects you want and are capable to perform - if you bid on them all you will be expected to perform on them all within the stated performance time.
· Be sure to sign Bid Form – SF 1442
Dan covered technical requirements:
· Pins
· 3 bid items in riprap
· Rock specs discussed
· Will likely need to hand pick rocks
· Sample Erosions and Sediment Control plan provided in solicitation – can use this or provide your own.
· Pay items per LF and will be measured at the toe
· Plant materials are included in this solicitation and must be provided and installed by contractor
· NRCS will layout and check grades
· Fill will be from onsite gravel – no slag
· Guide rail only has to be replaced by contractor if removed or damaged.
Questions:
Q - Access?
A - Likely where rock was.
Q – Performance time?
A – Will amend solicitation to provide for 12 days performance time -
Q – Rebar and hole size?
A – # 8 rebar. Will amend solicitation to allow for up to a 2” hole.
Q – Liquidated damages?
A – Only if contractor is negligent.
Q – Guide rail issues?
A – Must be coordinated with sponsor – Erie County DPW.