Emergency Watershed Protection (EWP) Site Showing Notes – July 29, 2010 Town of Concord / State Route 240 South of Ross Road
AG-2C31-S-10-0006
NRCS Representatives in attendance: Lauri Eipp, Contracting Officer; Mike Shinnick, Engineer; and Dan Bennett, Engineer; John Whitney, District Conservationist; Jim Bielli, Student Intern; Mike Shaw, Soil Conservationist/Inspector
Lauri review contract requirements:
· Federal Contract (different than state and local) – but sponsored by Erie County
· OSHA + additionally NRCS Safety requirements apply
· Must submit safety plan and someone certified in first aid on site at all times.
· Davis Bacon wage rates – must submit certified payrolls.
· Encouraged all interested to download entire contract package including Plans and specs on Federal Business Opportunities website
· Cost estimated at less than $25K - No bid bond required – also reserved for Emerging Small Business under the Small Business Competitive Demonstration Program. Emerging Small business = average annual gross receipts over last 3 years cannot be more than 50% of the small business size standard with is $33.5M ($16.75M)
· Payment bond (50 % of bid price) required after award by successful low bidder
· August 5 bid opening at 11:15 a.m.
· Successful contractor must register in the Central Contractor Registration (CCR) database
· 3 day performance time from point notice to proceed issued
· Have 3 days to mobilize
· No Sunday work
· Taxable job – contractor is not exempt from paying local/state sales tax on materials
· Only bid on those projects you want and are capable to perform - if you bid on them all you will be expected to perform on them all within the stated performance time.
· Be sure to sign Bid Form – SF 1442
Mike Shaw covered technical requirements:
· Moving Toe out
· 210 LF sloped rock – 6 ft
· Rock gradation – 300 to 2000 lbs
· Culvert needs work
· Concrete can be buried in slope
· Trees must be taken off site
· Existing rock can be used as bedding or chink
· Gravel may need to be moved off site – when designed it was not needed, but since some additional gravel may have deposited.
· No additional pay item for traffic control – need to include cost in mob/demob
· Erosion and sediment control plan need to be submitted to NRCS prior to work start
· 80 cy of excavation
· Pay item per LF @ toe
· Sanitary facility required.
· Seeding and plant materials included – must be purchased and installed by contractor
· If using chain saw need chaps and face guard – review NRCS safety requirements.
· Need to seed, mulch, plants before final inspection and payment. Don’t need to see a certain plant survival rate but need to see that green healthy plants are obtained.
Questions:
Q – Traffic Control?
A - County maintained state road. No additional permit is necessary.
Q – Geotextile?
A – No. NRCS does not generally use.
Q – Staging Area – can more area be in the landowners yard?
A – Yes, so long as you remain within the construction limits and shown on the drawings.
Q – Must pay taxes?
A – Yes – not tax exempt
Q – Can we get CAD drawings?
A – Yes – if necessary upon contract award.
Q – on Sheet 3, Note 2 – amount of gravel bedding?
A – need 12 inches of gravel bedding.
Q – on wage rates A – Davis Bacon Wage rates apply – may be different from county / state rates. Refer to solicitation package – wage rates posted at www.fbo.gov with each. Must submit certified payrolls with each job and before final payment can be made.
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .