Construction Specifications WRP Easement #: 6645321000Z3F
Date: 06/17/2016
Issue: FOR BID AND CONSTRUCTION
Construction and Material Specifications
Project:
KILKENNY
Wetland Reserve Project
Issue:
FOR BID AND CONSTRUCTION
Page i
Table of Contents
List of Construction Specifications ........................................................................................................................... v List of Material Specifications ................................................................................................................................... v Construction Specification 2—Clearing and Grubbing ..................................................................................... 2-1
1. Scope ............................................................................................................................................................ 2-1
2. Protection of Existing Vegetation ............................................................................................................. 2-1
3. Marking ....................................................................................................................................................... 2-1
4. Clearing and Grubbing .............................................................................................................................. 2-1
5. Disposal ....................................................................................................................................................... 2-1
6. Measurement and payment ...................................................................................................................... 2-1
7. Items of work and construction details ................................................................................................... 2-3
Construction Specification 5—Pollution Control ............................................................................................... 5-1
1. Scope ............................................................................................................................................................ 5-1
2. Material ........................................................................................................................................................ 5-1
3. Erosion and sediment control measures and works ............................................................................. 5-1
4. Chemical pollution ..................................................................................................................................... 5-2
5. Air pollution ............................................................................................................................................... 5-2
6. Maintenance, removal, and restoration .................................................................................................. 5-2
7. Measurement and payment ...................................................................................................................... 5-2
8. Items of work and construction details ................................................................................................... 5-3
Construction Specification 6—Seeding, Sprigging, and Mulching .................................................................. 6-1
1. Scope ............................................................................................................................................................ 6-1
2. Material ........................................................................................................................................................ 6-1
3. Seeding mixtures, sod, sprigs, and dates of planting ............................................................................ 6-2
4. Seedbed preparation and treatment ........................................................................................................ 6-2
5. Seeding, sprigging, fertilizing, mulching, and stabilizing .................................................................... 6-2
6. Measurement and payment ...................................................................................................................... 6-2
7. Items of work and construction details ................................................................................................... 6-3
Construction Specification 7—Construction Surveys ........................................................................................ 7-1
1. Scope ............................................................................................................................................................ 7-1
2. Equipment and material ............................................................................................................................ 7-1
3. Quality of work .......................................................................................................................................... 7-1
4. Primary control ........................................................................................................................................... 7-2
5. Construction surveys ................................................................................................................................. 7-2
6. Staking ......................................................................................................................................................... 7-3
7. Records ........................................................................................................................................................ 7-3
8. Payment ....................................................................................................................................................... 7-3
9. Items of work and construction details ................................................................................................... 7-4
Construction Specification 8—Mobilization and Demobilization ................................................................... 8-1
1. Scope ............................................................................................................................................................ 8-1
2. Equipment and material ............................................................................................................................ 8-1
3. Payment ....................................................................................................................................................... 8-1
4. Items of work and construction details ................................................................................................... 8-1
Construction Specification 10—Water for Construction ................................................................................. 10-1
1. Scope .......................................................................................................................................................... 10-1
2. Facilities and equipment ......................................................................................................................... 10-1
Page ii
3. Dust abatement and haul road maintenance........................................................................................ 10-1
4. Earthfill, drainfill, and rockfill ................................................................................................................ 10-1
5. Concrete, mortar, and grout ................................................................................................................... 10-1
6. Other construction requiring water ....................................................................................................... 10-1
7. Measurement and payment .................................................................................................................... 10-1
8. Items of work and construction details ................................................................................................. 10-2
Construction Specification 11—Removal of Water .......................................................................................... 11-1
1. Scope .......................................................................................................................................................... 11-1
2. Diverting surface water ........................................................................................................................... 11-1
3. Dewatering the construction site ........................................................................................................... 11-1
4. Dewatering borrow areas ........................................................................................................................ 11-1
5. Erosion and pollution control ................................................................................................................. 11-2
6. Removal of temporary works ................................................................................................................. 11-2
7. Measurement and payment .................................................................................................................... 11-2
8. Items of work and construction details ................................................................................................. 11-3
Construction Specification 21—Excavation ...................................................................................................... 21-1
1. Scope .......................................................................................................................................................... 21-1
2. Classification ............................................................................................................................................. 21-1
3. Blasting ...................................................................................................................................................... 21-1
4. Use of excavated material ....................................................................................................................... 21-2
5. Disposal of waste materials .................................................................................................................... 21-2
6. Excavation limits ...................................................................................................................................... 21-2
7. Borrow excavation ................................................................................................................................... 21-2
8. Overexcavation ......................................................................................................................................... 21-2
9. Measurement and payment .................................................................................................................... 21-3
10. Items of work and construction details ................................................................................................. 21-4
Construction Specification 23—Earthfill ........................................................................................................... 23-1
1. Scope .......................................................................................................................................................... 23-1
2. Material ...................................................................................................................................................... 23-1
3. Foundation preparation .......................................................................................................................... 23-1
4. Placement .................................................................................................................................................. 23-2
5. Control of moisture content .................................................................................................................... 23-2
6. Compaction ............................................................................................................................................... 23-3
7. Reworking or removal and replacement of defective earthfill .......................................................... 23-4
8. Testing ....................................................................................................................................................... 23-4
9. Measurement and payment .................................................................................................................... 23-5
10. Items of work and construction details ................................................................................................. 23-6
Construction Specification 44—Corrugated Polyethylene Pipe ..................................................................... 44-1
1. Scope .......................................................................................................................................................... 44-1
2. Material ...................................................................................................................................................... 44-1
3. Handling and Storage .............................................................................................................................. 44-1
4. Excavation ................................................................................................................................................. 44-1
5. Preparing the Pipe Bed and Blinding the Pipe ..................................................................................... 44-2
6. Placement and Joint Connections .......................................................................................................... 44-2
7. Backfilling .................................................................................................................................................. 44-2
8. Measurement and payment .....................................................................................................................44-2
9. Items of work and construction details ................................................................................................. 44-3
Page iii
Construction Specification 45 - Plastic Pipe ..................................................................................................... 45-1
1. Scope .............................................................................................................................................................45-1
2. Material ........................................................................................................................................................45-1
3. Handling and Storage ................................................................................................................................45-1
4. Excavation ....................................................................................................................................................45-1
5. Laying the pipe ............................................................................................................................................45-1
6. Pipe Embedment .........................................................................................................................................45-2
7. Backfill ..........................................................................................................................................................45-2
8. Pipe Encasement in Concrete ....................................................................................................................45-3
9. Joints .............................................................................................................................................................45-3
10. Fittings ..........................................................................................................................................................45-4
11. Thrust Blocks and Anchors ........................................................................................................................45-4
12. Pressure Testing ..........................................................................................................................................45-4
13. Measurement and Payment .......................................................................................................................45-5
14. Items of work and Construction details ...................................................................................................45-6
Construction Specification 61—Rock Riprap .................................................................................................... 61-1
1. Scope .......................................................................................................................................................... 61-1
2. Material ...................................................................................................................................................... 61-1
3. Subgrade preparation .............................................................................................................................. 61-2
4. Equipment placed rock riprap ............................................................................................................... 61-2
5. Hand placed rock riprap ......................................................................................................................... 61-2
6. Filter or bedding ........................................................................................................................................61-2
7. Measurement and payment .................................................................................................................... 61-2
8. Items of work and construction details ................................................................................................. 61-3
Construction Specification 95—Geotextile ........................................................................................................ 95-1
1. Scope .......................................................................................................................................................... 95-1
2. Quality ....................................................................................................................................................... 95-1
3. Storage ....................................................................................................................................................... 95-1
4. Surface preparation .................................................................................................................................. 95-1
5. Placement .................................................................................................................................................. 95-1
6. Measurement and payment .................................................................................................................... 95-2
7. Items of work and construction details ................................................................................................. 95-3
Construction Specification 97 - Geomembrane Liner ...................................................................................... 97-1
1. Scope ...........................................................................................................................................................97-1
2. Material .......................................................................................................................................................97-1
3. Shipping and storage ................................................................................................................................97-1
4. Subgrade preparation ...............................................................................................................................97-1
5. Anchor trench ............................................................................................................................................97-1
6. Liner placement .........................................................................................................................................97-1
7. Seaming methods ......................................................................................................................................97-2
8. Seaming procedures..................................................................................................................................97-2
9. Seam testing ...............................................................................................................................................97-3
10. Repairs ........................................................................................................................................................97-4
11. Appurtenances ..........................................................................................................................................97-4
12. Gas vents and drainage ............................................................................................................................97-5
13. Cover soil ....................................................................................................................................................97-5
14. Placement of concrete ...............................................................................................................................97-5
Page iv
15. Measurement and payment .....................................................................................................................97-5
16. Items of work and construction details ..................................................................................................97-6
Construction Specification 401—Precast Concrete Structures ..................................................................... 401-1
1. Scope ........................................................................................................................................................ 401-1
2. Materials .................................................................................................................................................. 401-1
3. Construction Methods ........................................................................................................................... 401-4
4. Plan Requirements ................................................................................................................................. 401-4
5. Items of Work and construction details. ............................................................................................. 401-5
Construction Specification 403 — Wetland Plugs ........................................................................................... 403-1
1. Scope ....................................................................................................................................................... 403-1
2. Materials ................................................................................................................................................. 403-1
3. Construction Methods .......................................................................................................................... 403-1
4. Measurement ......................................................................................................................................... 403-2
5. Items of Work and construction details ............................................................................................. 403-3
Material Specification 522—Aggregates for Portland Cement Concrete ..................................................... 522-1
1. Scope ......................................................................................................................................................... 522-1
2. Quality ...................................................................................................................................................... 522-1
3. Reactivity with Alkalies ......................................................................................................................... 522-1
4. Storing and Handling ............................................................................................................................. 522-1
Material Specification 523—Rock Riprap ......................................................................................................... 523-1
1. Scope ......................................................................................................................................................... 523-1
2. Quality ...................................................................................................................................................... 523-1
3. Methods of Soundness Testing.............................................................................................................. 523-2
4. Field Durability Testing ......................................................................................................................... 523-3
5. Grading ..................................................................................................................................................... 523-3
Material Specification 531—Portland Cement ................................................................................................. 531-1
1. Scope ........................................................................................................................................................ 531-1
2. Quality ...................................................................................................................................................... 531-1
3. Storage at the Construction Site ............................................................................................................ 531-1
Material Specification 532—Supplementary Cementitous Materials ........................................................... 532-1
1. Scope ......................................................................................................................................................... 532-1
2. Quality ...................................................................................................................................................... 532-1
Material Specification 547 - Plastic Pipe ........................................................................................................... 547-1
1. Scope ......................................................................................................................................................... 547-1
2. Material ..................................................................................................................................................... 547-1
3. Perforations .............................................................................................................................................. 547-1
Material Specification 548—Corrugated Polyethylene Pipe .......................................................................... 548-1
1. Scope ......................................................................................................................................................... 548-1
2. Pipe ............................................................................................................................................................ 548-1
3. Fittings ...................................................................................................................................................... 548-1
Material Specification 592—Geotextile ............................................................................................................. 592-1
1. Scope ......................................................................................................................................................... 592-1
2. General Requirements ............................................................................................................................ 592-1
3. Classification ............................................................................................................................................ 592-1
4. Sampling and Testing ............................................................................................................................. 592-1
5. Shipping and Storage.............................................................................................................................. 592-2
Material Specification 593 - Lime ...................................................................................................................... 593-1
Page v
1. Scope ......................................................................................................................................................... 593-1
2. Quality ...................................................................................................................................................... 593-1
Material Specification 594 - Geomembrane Liner ........................................................................................... 594-1
1. Scope ......................................................................................................................................................... 594-1
2. Material ..................................................................................................................................................... 594-1
3. Liner properties ....................................................................................................................................... 594-1
Page v
List of Construction Specifications
• 002 Clearing and Grubbing
• 005 Pollution Control
• 006 Seeding, Sprigging, and Mulching
• 007 Construction Surveys
• 008 Mobilization and Demobilization
• 010 Water for Construction
• 011 Removal of Water
• 021 Excavation
• 023 Earthfill
• 044 Corrugated Polyethylene Pipe
• 045 Plastic Pipe
• 061 Rock Rip Rap
• 095 Geotextile
• 097 Flexible Liner
• 401 Precast Concrete Structure
• 403 Wetland Plug Plantings
List of Material Specifications
• 522 Aggregates for Portland Cement Concrete
• 523 Rock Riprap
• 531 Portland Cement
• 532 Supplementary Cementious Materials
• 547 Plastic Pipe
• 548 Corrugated Polyethylene Pipe
• 592 Geotextile
• 593 Lime
• 594 Geomembrane
Page 2-1 of 2-3
Construction Specification 2—Clearing and Grubbing
1. Scope The work consists of clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from the designated areas.
2. Protection of Existing Vegetation Trees and other vegetation designated to remain undisturbed shall be protected from damage throughout the duration of the construction period. Any damages resulting from the contractor's operations or neglect shall be repaired by the contractor.
Earthfill, stockpiling of materials, vehicular parking, and excessive foot or vehicular traffic shall not be allowed within the drip line of vegetation designated to remain in place. Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.
Any cuts, skins, scrape, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.
Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk. All roots 1-inch or larger in diameter that are cut, broken, or otherwise severed during construction operations shall have the end smoothly cut perpendicular to the root. Roots exposed during excavation or other operations shall be covered with moist earth or backfilled as soon as possible to prevent the roots from drying out.
3. Marking The limits of the area(s) to be cleared and grubbed will be marked by stakes, flags, tree markings, or other suitable methods. Trees to be left standing and uninjured will be designated by special markings placed on the trunk about 6 feet above the ground surface.
4. Clearing and Grubbing All trees not marked for preservation and all snags, logs, brush, stumps, shrubs, rubbish, and similar materials shall be cleared from within the limits of the designated areas. Unless otherwise specified, all stumps, roots, and root clusters that have a diameter of 1 inch or larger shall be grubbed out to a depth of at least 2 feet below subgrade for concrete structures and 1 foot below the ground surface at embankment sites and other designated areas.
5. Disposal All materials cleared and grubbed from the designated areas shall be disposed of at locations shown on the drawings or in a manner specified in section 7. The contractor is responsible for complying with all local rules and regulations and the payment of any and all fees that may result from disposal at locations away from the project site.
6. Measurement and payment Method 1—For items of work for which specific units prices are established in the contract, the cleared and grubbed area is measured to the nearest 0.1 acre. Payment for clearing and grubbing is made for the total area within the designated limits at the contract unit price. Such payment will constitute full
Page 2-2 of 2-3 compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 2—For items of work for which specific unit prices are established in the contract, the length of the cleared and grubbed area is measured to the nearest full station (100 feet) along the line designated on the drawing or identified in the specifications. Payment for clearing and grubbing is made for the total length within the designated limits at the contract unit price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 3—For items of work for which specific unit prices are established in the contract, each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet are measured before removal. The size of each tree and snag is determined by measuring its trunk at breast height above the natural ground surface. The size of each log is determined by measuring the butt and by measuring its length from butt to tip. The size of each stump is measured at the top. Diameter is determined by dividing the measured circumference by 3.14.
Payment for clearing and grubbing of each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet or larger is made at the contract unit price for its size designation as determined by the following schedule:
Measured diameter Size designation
(in) (in) 4 to 86
8 to 12 10
12 to 24 18
24 to 36 30
36 to 60 48
Over 60 60
The sum of such payments shall constitute full compensation for clearing and grubbing (including the clearing and grubbing of smaller trees, stumps, snags, logs, brush, shrubs, and roots), applicable permits and associated fees, and rubbish removal. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 4—For items of work for which specific lump sum prices are established in the contract, payment for clearing and grubbing is made at the contract lump sum price. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 7.
Page 2-3 of 2-3
7. Items of work and construction details
A. Subsidiary to Bid Items #3 through #12, Clearing and Grubbing.
1) This item shall consist of all work associated with clearing and grubbing areas as identified on the construction drawings.
2) Areas shall be flagged by contractor in accordance with Section 3 of this specification and Construction Specification 7.
3) Grubbing shall be as follows:
Construction Specification #2 Table #1: Grubbing Requirements
Bid Items Grubbing Requirement 3 & 4; Dike 1 & 2 (respectively) 8 & 9; Ditch Plug 1 &2 (respectively)
One (1) foot below dike footprint and one (1) foot below dike core (side slopes and bottom).
10 through 12; Water Control Structure, Flow Over Weir; Pipe
Grub Two (2) foot below subgrade
5 through 7; Sloughes 1 through 3 (respectively) No grubbing required
4) Clearing shall be performed as outlined in Section 4.
5) All material removed from clearing and grubbing activities shall be disposed of in designated areas as shown on the construction drawings.
6) Contractor shall avoid trees which have been marked on construction plans; contractor shall mark trees as indicated in Section 3 of this specification.
7) All payment requests, with each invoice, shall be accompanied by complete documentation and supporting data in accordance with Construction Specification 7.
8) No Separate payment shall be made for Clearing and Grubbing. Compensation for this item shall be included in the payment for Bid Items #3 through #12.
Page 5-1 of 5-6 Date: 07/01/2016
Construction Specification 5—Pollution Control
The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.
2. Material All material furnished shall meet the requirements of the material specifications listed in section 8 of this specification.
3. Erosion and sediment control measures and works The measures and works shall include, but are not limited to, the following:
Staging of earthwork activities—The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.
Seeding—Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.
Mulching—Mulching to provide temporary protection of the soil surface from erosion.
Diversions—Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.
Stream crossings—Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.
Sediment basins—Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s). These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Sediment filters—Straw bale filters or geotextile sediment fences trap sediment from areas of limited runoff. Sediment filters shall be properly anchored to prevent erosion under or around them. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Waterways—Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Other—Additional protection measures as specified in section 8 of this specification or required by Federal, State, or local government.
Page 5-2 of 5-6
4. Chemical pollution The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to collect and temporarily contain chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer wash-water, or asphalt, produced as a by-product of the construction activities. Pollutants shall be disposed of in accordance with appropriate State and Federal regulations. At the completion of the construction work, tanks, barrels, and sumps shall be removed and the area restored to its original condition as specified in section 8 of this specification. Sump removal shall be conducted without causing pollution.
Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities shall be disposed of without causing pollution as specified in section 8 of this specification.
5. Air pollution The burning of brush or slash and the disposal of other materials shall adhere to state and local regulations.
Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.
All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations. A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.
6. Maintenance, removal, and restoration All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed and the site restored to near original condition.
7. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in section 8 of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessive to need. Such payment will constitute full compensation for the completion of the work.
Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance
Page 5-3 of 5-6 remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.
Method 3—For items of work for which lump sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating shall be the number estimated to complete the work as outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in section 8 of this specification.
8. Items of work and construction details
A. Subsidiary to Bid Line Items #1 through #16.
1) This item shall consist of the installation of all measures to control pollution and “sediment and erosion control” including disposal of chemical pollutants, air pollutions, etc. which shall be disposed of by the contractor in accordance with local, state, and federal guidelines.
2) Contractor shall provide water tight containers for disposing of chemical pollutants, and shall notify proper agency and the Contract Officers Technical Representative immediately after discovering a spill. Contractor shall be responsible for cleanup and any remediation required, at their own expense.
3) Seeding of disturbed areas shall be performed as specified in Construction Specification #6, within this specification package.
4) Contractor shall be responsible for any permit requirements as well as furnishing, installing, and maintaining any measures required by any permit agency.
5) No separate payment shall be made for Pollution Control. Compensation for this item shall be included in the payment for Bid Line Items #1 through #16.
B. Bid Line Item #13, Furnish, Install, Maintain, and Remove Silt Fence.
1) This item shall consist of the furnishing, installation, maintain, and removing temporary silt fencing (from here on known as “Silt Fence”). The silt fence shall be installed prior to any land disturbing activities. Maintain the silt fence until the project is accepted or until the fence is removed. Remove and replace deteriorated or ineffective filter fabric. Remove and dispose of silt accumulations (>0.25 feet measured from average ground to apex of accumulation) in appropriate disposal areas as shown on construction drawings when necessary or as directed. Leave silt fence in place until site stabilization and remove at project completion. Removed silt fence becomes the property of the Contractor. Dress, seed, Page 5-4 of 5-6 and mulch all areas where silt fence is removed in accordance with Construction Specification 6.
2) Materials
a. Posts
i. Steel Post meeting the following requirements: Minimum 5 feet long, minimum 1 3/8 inches wide measured parallel to the fence, minimum weight of 1.25 lbs/ft of length, equipped with an anchor plate with a minimum area of 14.0 square inches, and having a means of retaining fabric in the desired position without displacement.
b. Filter Fabric
i. The fabric shall consist of strong rot-proof synthetic fibers formed into a woven fabric or a non-woven needle-punched fabric meeting all applicable requirements of this section.
The fabric shall be free from any treatment or coating that might significantly alter its physical properties before or after installation. The fabric fibers shall contain stabilizers and/or inhibitors to make the filaments resistant to deterioration resulting from ultraviolet or heat exposure. The fabric shall be a pervious sheet of synthetic fibers oriented into a stable network so that the fibers retain their relative position with respect to each other. Finish the edge of the fabric to prevent the outer fibers from pulling away from the fabric.
The fabric shall be free of defects or flaws which significantly affect its physical and/or filtering properties. Sheets of fabric may be bonded together or sewn with a fungus resistant material. Do not use nylon thread for sewn seams. No deviation from any physical requirements will be permitted due to the presence of the seam.
During all periods of shipment and storage, wrap the fabric in a heavy duty protective covering to protect the fabric from direct sunlight, mud, dust, dirt, and debris. Do not expose the fabric to temperatures greater than 140°F.
ii. Physical Properties:
Grab Tensile Strength: 50 lbs Elongation: 30 % max Puncture Strength: 30 lbs.
Apparent Opening Size: #30 sieve Ultraviolet Exposure Strength Retention (at 500 hrs): 70 % Permittivity: 0.15 sec-1 Exhibit no fungal growth as tested by ASTM G21 All minimum strength requirements are minimum average roll values in the weakest principal direction.
c. Attachment Device:
i. Provide wire, zip tie, or other approved attachment device with a minimum tensile strength of 50 pounds (lbs.).
Page 5-5 of 5-6
3) Install in accordance with construction drawings.
4) Maintenance
a. Inspect silt fences at least once a week and after each rainfall. Make any required repairs immediately and report to Inspector and/or COTR.
b. Should the silt fence collapse, tear, decompose, or become ineffective replace it immediately.
c. Remove sediment deposits upon accumulating greater than or equal to 0.25 feet as measured from average ground to the apex of accumulation, or at the direction of Inspector/COTR. Take care to avoid undermining the fence during the cleanout.
d. Remove all fencing material and unstable sediment deposits and bring the area to grade and stabilize upon request and approval of the site being deemed stable by the COTR/Engineer.
5) Measurement and payment…