J3 Wage Determination.doc

DOC document 27 KB Posted

Attached to
Leicester Hollow Trail Decommissioning on the Green Mountain NF
Solicitation number
AG-24H8-S-10-0097
Issued by

About this file

J3 Davis Bacon Wage Determination

View the file

Other files

File Type Posted
Amendment 1.rtf RTF text file
SF18 Contractor to complete and return.rtf RTF text file
J1 Specifications.doc DOC document
J2 - Drawings and Maps.pdf PDF
AG-24H8-S-10-0097.rtf RTF text file
J4 - Technical Evaluation Forms.rtf RTF text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Davis Bacon Wage Determination

General Decision Number: VT100025 03/12/2010 VT25

Superseded General Decision Number: VT20080025

State: Vermont

Construction Type: Heavy

Counties: Addison, Caledonia, Essex, Lamoille, Orange, Orleans and Washington Counties in Vermont.

HEAVY CONSTRUCTION PROJECTS (does not include sewer & water lines, or treatment plants)

Modification Number Publication Date

0 03/12/2010

* SUVT1996-002 11/19/1996

Rates Fringes

ELECTRICIAN

$ 14.00 2.48

LABORER

$ 8.52 1.22

Power equipment operators:

Backhoes $ 10.50

Bulldozer

$ 13.69 6.40

Excavator $ 15.00 1.17

TRUCK DRIVER

Tandem Dump $ 11.55 1.53

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a)(1)(ii)).

In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION