AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 2

03 06/10/16 801438

USDA Forest Service Mt. Baker-Snoqualmie National Forest 2930 Wetmore Ave., Suite 3A Everett, WA 98201

Same as Block 6

✘ AG-05M6-S-16-0030

05/24/16

N/A

1. The purpose of Amendment 03 is to publicize vendor questions asked and Forest Service answers given. If you have any questions please contact the undersigned at (425) 783-6056 or via e-mail at bajohnson03@fs.fed.us. Amendment 03 is continued on Page 2.

BRIAN A. JOHNSON

CONTRACTING OFFICER

06/10/16

Heather Meadows Visitor Center Re-Roof and Chimney Re-build, Mt. Baker- Snoqualmie NF, Mt. Baker Ranger District

AG-05M6-S-16-0030

Amendment 03

Heather Meadows Visitor Center Re-Roof and Chimney Re-build, Mt. Baker- Snoqualmie NF, Mt. Baker Ranger District

2. The following are questions asked by interested vendors and the associated answers provided by the Forest Service. As future questions are asked and answers given they will be added to this document and labeled with the appropriate Amendment number for acknowledgement purposes.

QUESTIONS & ANSWERS

Vendor Question #1: Regarding the chimney rock/brick removal to roof line; at this point are you intending to have the chimney flue liner/tile removed to the roof line as well, or, if it is in good condition, can the flue tile remain? (Assuming there is flue tile)

Forest Service Answer #1: Assume no chimney liners, but if chimney liners are discovered do not disturb the liners.

Vender Question #2: Are you intending to continue using the existing chimney cap/spark arrestor?

Forest Service Answer #2: Yes

Vendor Question #3: As masonry chimneys are generally finished with a mortar or concrete crown, will one be required? If so, please provide a specification on it.

Forest Service Answer #3: No. Reconstruction of the chimney shall match existing conditions.

Vendor Question #4: C.13 states that flashing materials, other than valleys, shall be stainless steel or galvanized iron. For flashings such as drip edge, is color clad steel or color clad aluminum acceptable?

Forest Service Answer #4: The acceptability of materials is based on the manufacturer’s recommendation.

End of Amendment 03