1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION / MODIFICATION OF CONTRACT
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
002 5/09/2013
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
USDA Forest Service Okanogan-Wenatchee National Forest 215 Melody Lane Wenatchee, WA 98801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) ( ) 9A. AMENDMENT OF SOLICITATION NO.
AG-05G1-S-13-9001
Mill Creek AtoZ Stewardship
X 9B. DATED (SEE ITEM 11)
04/12/2013
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, X is not ex-tended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 01 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
( ) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
This amendment is issued to make the following corrections and respond to submitted questions:
A. Changes/Additions/Deletions:
1. Exisiting solicitation has been replaced with a revised solicitation. Changes are primarily to the terms and conditions. Summary of solicitation changes are provided.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
FAR (48 CFR) 53.243
SF-30 (continued)
2. On page 11 of 61, F.5 SCHEDULES AND REPORTS – Deleted requirement to submit Standard
Form 1413 for subcontracting.
3. On page 12 of 61, G.1 Payment, last sentence : revise wording:
Delete: When payment is made to the contractor for work performed, it will be made in accordance with
FAR 52.232-1 – Payments.
Add: When payment is made to the contractor for work performed, it will be made in accordance with the
Federal Acquisition Regulations payment clauses in Section I.
4. Section I, page 34 of 61, the following clause was updated to reflect current clause date:
52.203-16 Preventing Personal Conflicts of Interest (DEC 2011)
5. Section I, page 35 of 61, the correct title was added to the following clause:
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011)
6. Section I, page 35 of 61:
Delete clause 52.245-2
Add clause 52.245-1 Government Property (Fixed-Price Contracts) (APR 2012)
7. Section I.2, page 36 of 61, the following clause was updated to reflect current clause date:
I.2 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY
MATTERS (FEB 2012)
8. I.4, page 37 of 61, 52.216-19 ORDER LIMITATIONS (OCT 1995) the minimum order amount is changed from $20,000 to $2500 as follows.
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $2,500, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.
9. Section I, page 39 of 61, Added clause:
52.217-7 at I.7 - OPTION TO EXTEND SERVICES (NOV 1999)
10. Section K, K.1, clause 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY
DEC 2012) was updated to reflect current clause in full text.
B. Questions and Answers:
Question:
1. Does the Forest Service have a preferred approach to NEPA over the life of the project? For example, will the NEPA analysis be site-specific for each of the three planning units (Onion WUI, N/S Mill, and Little
Twin WUI).
2. Also, what is the anticipated level of NEPA (for example: Programmatic EIS and then site-specific
EA’s) or some other approach?
Answer:
Please refer to Section L and M for NEPA team and experience requirements. Appendix A is written specifically to allow for any NEPA documentation that is legally sufficient. Therefore, it is at the discretion of the Prime Contractor to complete a single EIS, multiple EAs, or any combination of these, along with CEs.
File details come from the government source that posted it. Updated .