AG04T0S120044-Specifications.pdf
PDF 188 KB Posted
- Attached to
- Road and Parking Lot Striping IDIQ
- Solicitation number
- AG-04T0-S-12-0044
About this file
Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AG04T0S120044-Solicitation.pdf | ||
| AG04T0S120044-ContractPacketToReturn.pdf | ||
| AG04T0S120044-HeboVicinityMap.jpg | JPG image | |
| AG04T0S120044-CentralCoastVicinityMap.jpg | JPG image | |
| AG04T0S120044-SampleTaskOrder.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 1
FP-03 SPECIFICATION LIST FOR 2012 Siuslaw Striping All specifications not included in the specifications listing, but referenced by listed specifications, are applicable. The supplemental specifications shown on the specification list are physically attached. Section 100 through 149 of the Standard Specifications and all other Standard or supplemental specifications shown in the specification listing are applicable to this contract.
Title Revised
Siuslaw Striping
Preface 3/15/2004 X 101 Terms, Format, and Definitions FP03 X
101.01 Meaning of Terms 1/22/2009 X
101.03 Abbreviations 6/16/2006 X
101.04 Definitions 3/29/2007 X
102 Bid, Award, and execution of Contract FP03 X
102.00 Bid, Award, and execution of Contract 2/16/2005 X
103 Scope of Work FP03 X
103.00 Deletions 2/16/2005 X
104 Control of work FP03 X
104.00 Deletions 6/16/2006 X
104.06 Use of Roads by Contractor 2/17/2005 X
105 Control of Material FP03 X
105.02 Material Sources 1/18/2007 X
105.02 Material Sources 1/22/2007 X
105.05 Use of Material Found in the Work 5/12/2004 X
106 Acceptance of Work FP03 X
106.01 Conformity with Contract Requirements 7/31/2007 X
106.07 Delete 5/11/2004 X
107 Legal Regulations and Responsibility to the Public FP03 X
107.05 Responsibility for Damage Claims 5/11/2004 X
107.06 Contractor's Responsibility for Work 6/16/2006 X
107.09 Legal Relationship of the Parties 6/16/2006 X
107.10 Environmental Protection 6/16/2006 X
108 Prosecution and Progress FP03 X
108.00 108 Delete 2/16/2005 X 109 Measurement and Payment FP03 X
109.00 Deletions 2/17/2005 X
109.02 Measurement Terms and Definitions 6/16/2006 X
151 Mobilization FP03 X 156 Public Traffic FP03 X
156.03 Accommodating Traffic During Work 2/24/2005 X
156.08 Traffic and Safety Supervisor 2/24/2005
171 Weed and Disease Prevention 3/26/2007 X 634 Permanent Pavement Marking FP03 X
634.03 General 3/3/2005 X
607 Cleaning, Reconditioning, and Repairing Existing Drainage Structures FP03 X 635 Temporary Traffic Control FP03 X
635.03 General 5/13/2004 X
718 Traffic Signing and Marking Material FP03 X
718.02 Reserved 3/2/2005 X
718.05 Aluminum Panels 2/25/2008 X
718.14 Waterborne Traffic Paint - Daylight reflectance 3/2/2005 X
AG-04T0-S-12-0044
IDIQ-Road and Parking Lot Striping
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
AG-04T0-S-12-0044
109 Deletions
109.02 Measurement Terms and Definitions
155 - Schedules for Construction Contracts
155 Delete
634 - Permanent Pavement Marking
634.03 General
718 - Traffic Signing and Marking Material
718.02 Reserved
718.02 Protective Overlay Film and Edge Film
718.05 Aluminum Panels
718.08 (b)(2)(c)Signpost - Square tubular steel posts
718.14 (g)Waterborne Traffic Paint - Daylight reflectance
718.15 (g)Epoxy Marking - Drying Time
718.15 (a)Epoxy Markings Pigments
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
AG-04T0-S-12-0044
IDIQ-Road and Parking Lot Striping http://www.nist.gov/
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
AG-04T0-S-12-0044
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
AG-04T0-S-12-0044
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.01_nat_us_07_31_2007
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to
106.05 inclusive. The primary method of acceptance is specified in each Section of work.
However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program.
Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.
If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
AG-04T0-S-12-0044
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
AG-04T0-S-12-0044
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
634 - Permanent Pavement Marking
634.03_nat_us_03_03_2005
634.03 General.
Add the following:
On single lane roads apply pavement markings according to the manufacturer’s recommendations and in a direction consistent with safe application.
718 - Traffic Signing and Marking Material
718.02_nat_us_03_02_2005
718.02 Reserved.
Replace this section with the following:
718.02 Protective Overlay Film and Edge Film.
Protective overlay film will be a high performance flouropolymer film such as 3M Scotchlite Premium Protective Overlay Film Series 1160 or approved equal.
Edge film will be a pressure-sensitive, premium-quality, clear, ultraviolet-resistant, 3 inches wide vinyl film.
718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.
718.08_nat_us_03_27_2007
718.08 (b)(2)(c)Signpost - Square tubular steel posts
Delete the existing subsection and substitute the following:
(c) Galvanizing after punching ASTM A 653M, (inside and outside of post) coating Z275 designation
718.14_nat_us_03_02_2005
718.14 (g)Waterborne Traffic Paint - Daylight reflectance
Delete the existing subsection and substitute the following:
(g) Daylight reflectance. (Without glass beads)
(1) White, ASTM E 1347 84% relative to magnesium oxide standard
AG-04T0-S-12-0044
(2) Yellow, ASTM E 1347 55% relative to magnesium oxide standard
718.15_nat_us_03_27_2007
718.15 (g)Epoxy Marking - Drying Time
(g) Drying time. 15 mil film thickness with beads.
(1) Laboratory at 72o F, ASTM D 711 30 minutes maximum to no-pick-up condition
(2) Field at 77 oF, viewed from 50 feet 10 minutes maximum to no-pick-up condition 718.15_nat_us_03_27_2007
718.15 (a)Epoxy Markings Pigments
(2) Yellow.
(a) Chrome yellow (PbCrO4), 23% min.
ASTM D 126, type III.
(b) Epoxy resin 70 to 77%
| Table of Contents |
| Preface |
| 101 - Terms, Format, and Definitions |
| 101.01 Meaning of Terms |
| 101.03 Abbreviations. |
| 101.04 Definitions. |
| 102 - Bid, Award, and Execution of Contract |
| 102 Bid, Award, and Execution of Contract |
| Deletions |
| Deletions |
| 104.06 Use of Roads by Contractor |
| 105.02 Material Sources. |
| 105.02(a) Government-provided sources. |
| 105.05 Use of Material Found in the Work. |
| 106 - Acceptance of Work |
| 106.01 Conformity with Contract Requirements. |
| 106.07 Delete |
| 107 - Legal Relations and Responsibility to the Public |
| 107.05 Responsibility for Damage Claims. |
| 107.06 Contractor’s Responsibility for Work. |
| 107.09 Legal Relationship of the Parties. |
| 107.10 Environmental Protection. |
| 108 Delete. |
| 109 Deletions |
| 109.02 Measurement Terms and Definitions. |
| 155 Delete. |
| 634.03 General. |
| 718 - Traffic Signing and Marking Material |
| 718.02 Reserved. |
| 718.02 Protective Overlay Film and Edge Film. |
| 718.05 Aluminum Panels |
| 718.08 (b)(2)(c)Signpost - Square tubular steel posts |
| 718.14 (g)Waterborne Traffic Paint - Daylight reflectance |
| 718.15 (g)Epoxy Marking - Drying Time |
| 718.15 (a)Epoxy Markings Pigments |
File details come from the government source that posted it. Updated .