A. Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| b.Section_J_Attachments.pdf | ||
| c.ReturnThisCopy.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ Construction Gulliford Aspen Fence Construction Solicitation No. AG-04M3-S-16-0052 North Fork John Day Ranger District
REQUEST FOR QUOTATION
PAGE OF PAGES
| (THIS IS NOT AN ORDER) |
| THIS RFQ |
| X |
| IS |
| IS NOT A 100% SMALL BUSINESS SET- ASIDE |
| 1 |
| 71 |
| 1. REQUEST NO. |
| 2. DATE ISSUED |
| 3. REQUISITION/PURCHASE REQUEST NO. |
| 4. CERT. FOR NAT.DEF. |
| RATING |
| AG-04M3-S-16-0052 |
| 5/11/2016 |
| 798510 |
| UNDER BDSA REG. 2 |
AND/OR DMS REG. 1
| 5a. ISSUED BY |
| 6. DELIVER BY (Date) |
Contracting East Acquisition Area Wallowa-Whitman National Forest 1550 Dewey Ave Suite A Baker City OR 97814
See Section F
| 5b. FOR INFORMATION CALL (NO COLLECT CALLS) |
| 7. DELIVERY |
FOB DESTINATION
| NAME |
| TELEPHONE NUMBER |
OTHER (See Schedule)
| AREA CODE |
| NUMBER |
| 9. DESTINATION |
| SUE DOMINA, CO |
| 541 |
| 523-1263 |
| a. NAME OF CONSIGNEE |
| 8. TO: |
| Umatilla National Forest |
| a. NAME |
| b. COMPANY |
| b. STREET ADDRESS |
North Fork John Day Ranger District
| c. STREET ADDRESS |
| c. CITY |
Ukiah
| d. CITY |
| e. STATE |
| f. ZIP CODE |
| d. STATE |
| e. ZIP CODE |
OR
| 10. PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5A ON OR BEFORE CLOSE OF BUSINESS |
| IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5A. This request does not commit the Government to pay any costs incurred in the preparation of the |
| June 10, 2016 @ 2:30pm (PT) |
| submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter. |
11. SCHEDULE (Include applicable Federal, State and local taxes)
| ITEM NO. |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| (a) |
| (b) |
| (c) |
| (d) |
| (e) |
| (f) |
Gulliford Aspen Fence Construction North Fork John Day Ranger District, Umatilla National Forest
| X |
| X |
| X |
| X |
DUNS: __________________________
This project is 100% set-aside for small business.
| a. 10 CALENDAR DAYS (%) |
| b. 20 CALENDAR DAYS |
| c. 30 CALENDAR DAYS |
| d. CALENDAR DAYS |
12. DISCOUNT FOR PROMPT PAYMENT
| NUMBER |
| PERCENTAGE |
| NOTE: Additional provisions and representations |
| X |
| are |
are not attached.
| 13. NAME AND ADDRESS OF QUOTER |
| 14. SIGNATURE OF PERSON AUTHORIZED TO |
| 15. DATE OF |
| a. NAME OF QUOTER |
| SIGN QUOTATION |
| QUOTATION |
| b. STREET ADDRESS |
| 16. SIGNER |
| a. NAME (Type or print) |
| b. TELEPHONE |
c. COUNTY
AREA CODE
| d. CITY |
| e. STATE |
| f. ZIP CODE |
| c. TITLE (Type or Print) |
| NUMBER |
NSN 7540-01-152-8084
Previous edition not usable 18-121
CONTRACTOR’S COPY
STANDARD FORM 18 (Rev. 6-95) Prescribed by GSA-FAR (48 CFR) 53.215-1(a)
TABLE OF CONTENTS
| B - SECTION B - Supplies or Services and Prices/Costs Schedule of Items | 4 |
| Clauses | 4 |
| C - SECTION C - Description/Specifications/Statement of Work | 4 |
| Clauses | 4 |
| D - SECTION D - Packaging and Marking | 5 |
| Clauses | 5 |
| E - SECTION E - Inspection and Acceptance | 5 |
| Clauses | 5 |
| F - SECTION F - Deliveries or Performance | 5 |
| Clauses | 5 |
| G - SECTION G - Contract Administration Data | 6 |
| Clauses | 6 |
| H - SECTION H - Special Contract Requirements | 6 |
| Clauses | 6 |
| I - SECTION I - Contract Clauses | 6 |
| Clauses | 6 |
| J - SECTION J - List of Documents, Exhibits, and Other Attachments | 55 |
| List of Documents, Exhibits, and Other Attachments | 55 |
| Clauses | 55 |
| K - SECTION K - Representations, Certifications, and Other Statements of Offerors | 55 |
| Clauses | 55 |
| L - SECTION L - Instructions, Conditions, and Notices to Offerors or Respondents | 64 |
| Clauses | 64 |
| M - SECTION M - Evaluation Factors for Award | 68 |
| Clauses | 68 |
SECTION B - Supplies or Services and Prices/Costs Schedule of Items
SECTION B – Schedule of Items
| ITEM NO. |
| SUPPLIES/SERVICES |
| QUANTITY |
PAY
UNIT
UNIT
PRICE
AMOUNT
| 1 |
| Mobilization / Bonding |
| 1 |
| LS |
| xx |
| $ |
| 2 |
| Buck and Pole Fence Construction |
| 2.1 |
| Fence 1 (Repair) |
| 75 |
| *Section |
| $ |
| $ |
| 2.2 |
| Fence 3 (Construct New) |
| 54 |
| *Section |
| $ |
| $ |
| 2.3 |
| Fence 4 (Replace) |
| 75 |
| *Section |
| $ |
| $ |
| 2.4 |
| Fence 5 (Replace) |
| 85 |
| *Section |
| $ |
| $ |
| 2.5 |
| Fence 6 (Replace portions of fence) |
| 35 |
| *Section |
| $ |
| $ |
| 2.6 |
| Fence 8B (Replace) |
| 65 |
| *Section |
| $ |
| $ |
| 2.7 |
| Fence 9 (Repair) |
| 21 |
| *Section |
| $ |
| $ |
Sub-Total
| 2.8 |
| Option Item: Fence 7 (Replace) |
| 152 |
| *Section |
| $ |
| $ |
| 2.9 |
| Option Item: Fence 2B (Replace) |
| 119 |
| *Section |
| $ |
| $ |
Sub-Total
*Based on 11-foot sections with no more than 6-inches of rail overhang beyond each buck, on either side.
| 3 |
| Woven Wire Fence Construction |
| 3.1 |
| Fence 2A |
| 1665 |
| LF |
| $ |
| $ |
| 3.2 |
| Fence 8A |
| 720 |
| LF |
| $ |
| $ |
Sub-Total
| 4 |
| Cage Construction |
| 12 |
| Each |
| $ |
| $ |
TOTAL ALL ITEMS
SECTION C - Description/Specifications/Statement of Work Description of Work This project consists of constructing buck and pole fences, woven wire fences, and cages around stands of aspen as flagged on the ground. Some materials needed to construct the fences will be supplied by the Government, including post and pole materials, the pattern to build A-frames on buck and pole fences, woven wire field fence, t-posts, pressure-treated wooden posts, and bracing hardware for cage construction. All other materials required for fence and cage construction , tools, all-terrain-vehicles, and trailers to distribute poles and completed A-frames, fence posts, and woven wire materials shall be supplied by the Contractor. The contractor shall transport the fence material from the North Fork John Day Ranger Station to the job site.
The Contractor shall brush out a 12-foot wide fence right-of-way and distribute fence materials around the fence perimeter. Brushing may consist of sawing stumps nearly level with the ground, and removing brush, remnants of burn piles, and small trees, to allow unobstructed construction of the fence and passage of an All Terrain Vehicle, within the fence right-of-way. The fence may be placed around larger obstructions such as boulders, unburned slash piles and large diameter trees.
For Buck and Pole Fences: The Contractor shall construct and distribute A-frames around the fence perimeter, erect and join the A-frames to build the frame of the fence, attach the rails to each section of fence, and construct one sliding gate per fence. The location of each gate will be determined by the Contracting Officer.
The contractor shall drill nail holes into the fence posts and rails prior to attaching the fence components to prevent splitting of rails and posts.
For Woven Wire Fences: The Contractor shall install wooden and steel fence posts around the fence perimeter, stretch and attach woven wire field fence, construct H-braces and angle braces for added support, and install one 6-foot wire gate per fence. Should the ground be too rocky to install fence posts into the ground, rock jacks shall be constructed to hold the fence posts. The location of each gate will be determined by the Contracting Officer.
For Cages: The Contractor shall install cages around the root suckers of aspen trees, outside of fences, in designated locations. The cages shall be constructed from steel t-posts, woven wire field fence, barbless wire, and metal bracing hardware. Metal posts shall be installed in the ground to a depth of 12 inches. Cage dimensions are 7 feet wide by 12 feet long and 6 feet tall.
Project Location
This project is located on the North Fork John Day Ranger District, Umatilla National Forest, Ukiah, Oregon. Fences are located along the 5308-054 road, near the 5308-140 road, the 5314-040 road, and the 5311-020 road. Fences 4, 5 and 6 require hauling materials beyond the terminus of the 5308-054 using an ATV and trailer.
Price Range
This project is estimated at $25,000 and $100,000. Davis Bacon Wage Rates apply. Alternative Payment Protection is required from the awardee if over $35,000.
452.211-72 Statement of Work/Specifications. (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
452.211-73 Attachments to Statements of Work/Specifications. (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
SECTION D - Packaging and Marking All material supplied by the Government in the possession of the Contractor shall be labeled as “Property of the Umatilla National Forest”.
SECTION E - Inspection and Acceptance
52.252-2 Clauses Incorporated by Reference. (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far 52.246-12 Inspection of Construction. (AUG 1996) 52.246-13 Inspection—Dismantling, Demolition, or Removal of Improvements. (AUG 1996)
Measurement and Payment
Payment will be made per section of fence completed and accepted for buck and pole fences. A section consists of one completed A-frame and 6 attached 12-foot rails. The gate shall be considered a section. Payment will be made per linear foot completed and accepted of woven wire fences. Payment will be made per cage.
For Buck and Pole Fences: A 10% deduction in price per unacceptable A-frame that is not erected vertical to the ground surface, given a variation of 5% from perpendicular to the horizontal ground surface. An additional 10% shall be deducted for sections that contain rails that are attached crooked or that are poorly spaced. Rails that are placed more than 5% from horizontal and/or are separated by more than 11 inches shall be considered unacceptable. The Contractor shall rework all sections that do not meet the above standards. Failure to rework unacceptable sections shall result in the price deductions described above.
For Woven Wire Fences: A 10% deduction in price per unacceptable stretch of fence consisting of 5 steel t-posts, one wooden post, two support braces (one H-brace and one angle brace), and the attached woven wire fencing.
An acceptable fence shall have posts erected vertical to ground surface, given a variation of 5% from perpendicular to the horizontal ground surface; posts shall be secured firmly in the ground to the proper depth; splices shall be properly constructed; fencing nails shall be attached to wooden posts according to specifications; woven wire fence material shall be attached on the outside of the fence; woven wire fence shall be attached to steel posts according to specifications; fence shall be stretched to specifications, with no observable sagging; rock jacks, if required, are constructed to specifications; braces are placed where required and constructed according to specifications.
A 5% deduction in price shall be made for non-conforming stream crossing panels.
A 5% deduction in price shall be made for non-conforming gates.
For Cages: A 10% deduction in price shall be asssessed for t-posts that are not driven to the proper depth or are more than 5% from vertical. An additional 10% shall be deducted for woven wire that is not stretched tight. A 10% deduction shall be made for bracing hardware that is not attached correctly.
SECTION F - Deliveries or Performance
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far 52.242-14 Suspension of Work. (APR 1984) 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than November 6, 2016. The time stated for completion shall include final cleanup of the premises. Estimated start date is July 11, 2016.
SECTION G - Contract Administration Data Pre Construction Meeting
A pre-construction meeting with the successful offeror is required. It will be scheduled within 10 days of contract award. The meeting will be held at the Umatilla National Forest Headquarters, Pendleton, Oregon or other mutually agreed to location.
The Contractor shall bring the following to the meeting for discussion and/or approval:
1. Contract, Specifications, Drawings
2. Safety Plan
3. Fire Plan
4. Work Schedule
Government-Furnished Property –
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.
| Item No. |
| Property Description |
| Property Value |
| Qty |
| Location |
| Date Available |
| 1 |
| Post and Poles |
| $31.00/ Section |
| Variable |
| NFJD Ranger Station, Ukiah, OR |
Upon Award
| 2 |
| A-Frame Pattern |
| $150.00 |
| 1 |
| NFJD Ranger Stn |
| Upon Award |
| 3 |
| Woven Wire Fence |
| $150/ 330 ft roll |
| Variable |
| NFJD Ranger Stn |
| Upon Award |
| 4 |
| 12-foot Wooden posts |
| $22 each |
| 50 |
| NFJD Ranger Stn |
| Upon Award |
| 5 |
| 8-10 ft Wooden Posts |
| $13 each |
| Variable |
| NFJD Ranger Stn |
| Upon Award |
| 6 |
| Steel T-Posts |
| $10 each |
| 300 |
| NFJD Ranger Stn |
| Upon Award |
| 7 |
| Bracing Hardware for Cages |
| $52 /corner set |
| 48 |
| NFJD Ranger Stn |
| Upon Award |
SECTION H - Special Contract Requirements Additional Requirements or Restrictions The Contractor may use a standard pick-up and trailer to haul fence materials in on the designated roads listed under the Project Location. Materials shall be transported off system roads using a small trailer pulled by an ATV, a small Bobcat type loader, or carried in by hand, unless otherwise approved by the Contracting Officer’s Technical Representative. Work will commence when soils in the project area are dry enough to minimize damage to the site. Ruts deeper than 6 inches, created by vehicle or trailer tires, are considered unacceptable. Poles shall not be dragged on the ground. Any unacceptable site damage created by the work of the Contractor will be repaired and an alternate route, or method of transport, will be used.
Stream beds may be crossed at designated crossings approved by the Contracting Officer’s Technical Representative. These will be locations that are dry and care shall be taken not to cause damage to a defined channel. One method to reduce the risk of damage is to place a small, temporary ramp over the stream channel at the designated crossing location.
Self-tapping, star-head, lag screws, or similar screws approved by the Contracting Officer’s Representative are required to fasten posts, poles, and ties to the buck and pole fences. They should be of sufficient length to fast materials together such that a minimum of 3 inches is inserted in the receiving post. Typically this will require a variety of screws from 6-8 inches in length.
Product Substitution
Any modification of other items, designs, materials, products or equipment (including Government-furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.
Conformity with Drawings and Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
A. Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
B. The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
C. Government inspections and tests are for the sole benefit of the Government and do not--
1. Relieve the Contractor of responsibility for providing adequate quality control measures;
2. Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
3. Constitute or imply acceptance; or
4. Affect the continuing rights of the Government after acceptance of the completed work under paragraph (I) below.
D. The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
E. The Contractor shall promptly furnish, without additional charge, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
F. The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
G. If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor's right to proceed.
H. If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
I. Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
Contractor’s Use of Existing Roads
The Contractor is authorized to use roads in the immediate construction project area for performance of work under this contract. The authorization is limited to roads necessary for direct access between the construction area and storage sites, disposal areas, and other work areas designated in the contract.
The roads authorized for use will be subject to the following general conditions:
(1) State laws governing traffic rules and equipment requirements on State and County Highways.
(2) Federal Regulations contained in 36 CFR 261.12. These regulations prohibit use in excess of State Codes for weight and size, damaging a road while using it, and blocking a road open to use by others.
The Contractor shall be responsible for and perform road maintenance commensurate with his use of Forest Service roads in the construction area.
Road Use and Maintenance
Use of Roads
(a) The Contractor is authorized to use roads that are a part of the construction project and those Forest Service roads designated below for performance of work under this contract.
(b)
Road No.
Termini Authorizations, Restrictions & Requirements
Maintenance Required (Yes or No)
5308-140
| Closed Road |
| No |
5314-040
No
5308-054
| Beyond Barricade |
| No |
(b) If the Contractor requests use of a National Forest road or segment not designated for his use, the Forest Service may authorize such use if not in conflict with the current Road Rules document. Authorization to use such additional roads may include maintenance requirements and use limitations.
(c) The roads authorized for use will be subject to the following provisions.
1. The Road Rules in the current Umatilla, Wallowa-Whitman, and Malheur National Forest Road Rules Documents are applicable to all commercial road users. These documents are available for inspection at the office of the Forest Supervisors and shall be applicable except when modified by provisions of the contract.
2.
Umatilla NF Road Use Rules: Available on line at following address:
http://www.fs.usda.gov/Internet/FSE_DOCUMENTS/stelprdb5297956.pdf
2. State laws governing traffic rules and equipment requirements on State and County highways.
3. Federal regulations contained in 36 CFR 261.12. These regulations prohibit use of vehicles or equipment in excess of State legal highway loads or posted limits without valid State and Forest Service overload permits, damaging a road while using it, and blocking a road open to use by others, except as may be otherwise provided in the contract.
Load Limits --All vehicles and equipment shall not exceed State legal highway loads and widths or posted limits without valid State and Forest Service overload, over width permits. Forest Service overload permits for this project may be obtained from the District Ranger.
4. Federal Regulations contained in 36 CFR 261.54 as applied to the area by an order issued under 36 CFR 261.50. These regulations authorize the Forest Service, as a sovereign act, to issue additional restrictions and closures any time conditions warrant. Such closures will be in addition to those shown in the current Road Rules Document and will be posted on the road.
Safety
Contractor shall submit a project specific safety plan, addressing at a minimum the information below; including an accident prevention plan; and mitigation procedures, to the Contracting Officer for review and approval at the post award meeting.
The Contractor is responsible for providing the crew with the proper safety equipment that includes, but is not limited to, hardhats, hearing protection, eye protection, gloves, chaps, nonskid boots, etc...
Inherently hazardous conditions that could lead to serious injury or loss of life include: the potential for lacerations from saws, smashing fingers while nailing rails, lower back injuries from lifting heavy objects, injuries from falling trees due to felling operations or high wind, tripping and falling while walking over obstacles or uneven ground, log truck and other vehicle traffic when driving forest roads, working with hand tools, and bee stings. These are not all inclusive.
Long drives to project sites via Federal, State and local jurisdiction road systems with varying degrees of maintenance potentially increases Contractor and employee risk of motor vehicle accidents. Public and commercial use of these same road systems adds an additional hazard to Contractor and employee safety. Equipment operation on project sites and contractor traffic is a potentially hazardous condition for public traveling through or adjacent to the construction sites.
Safety signing, barricades, fencing, and traffic control in compliance with Manual on Uniform Traffic Control Devices (MUTCD) shall be required.
Inherent hazards of working in remote locations of National Forests include, but are not limited to:
| I. Traffic hazards |
| II. Heavy equipment operations |
· Narrow Gravel or native surface forest roads
· Long, steep grades (generally less than 20%)
· Logging & other commercial traffic
· Visitors not used to forest road driving
· Dusty conditions hindering visibility behind vehicles
· Mixed motorized traffic (ATVs) on some roads
· Backing into objects
· High db noise
· Steep side slopes or soft ground for rollovers
· Refueling hazards
· Exceeding equipment limitations
· Unsafe equipment / lack of safety equipment
· Operator fatigue
· Slope or trench wall instability
| III. Work environment |
| IV. Truck Driving & Trailer Towing |
· Inclement weather for potential hypo/hyperthermia
· High winds that can bring down trees
· Wet, snowy or ice conditions making ground unstable
· Insects, plants, animals
· Working in remote locations
· Increased stopping distance
· Load lashing/tie downs coming loose due to rough road
· Low clearances (power lines and tree branches, for example)
· Narrow turnouts & roadways
452.236-77 Emergency Response (NOV 1996)
(a) Contractor’s Responsibility for Fire Fighting. (1) The Contractor, under the provisions of FAR clause 52.236-9, Protection of existing vegetation, structures, equipment, utilities, and improvements, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work. (2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contactor or the Contractor’s agents or employees.
(b) Contractor’s Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.
(c) Contractor’s Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to fire fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the Changes clause, FAR 52.243-4.
SECTION I - Contract Clauses
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far
52.204-7 System for Award Management. (JUL 2013) 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015) 52.222-3 Convict Labor. (JUN 2003) 52.222-6 Construction Wage Rate Requirements. (MAY 2014) 52.222-9 Apprentices and Trainees. (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements. (FEB 1988) 52.222-11 Subcontracts (Labor Standards). (MAY 2014) 52.222-12 Contract Termination - Debarment. (MAY 2014) 52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014) 52.222-14 Disputes Concerning Labor Standards. (FEB 1988) 52.222-15 Certification of Eligibility. (MAY 2014) 52.222-21 Prohibition of segregated facilities. (APR 2015) 52.222-26 Equal Opportunity. (APR 2015) 52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015) 52.223-6 Drug-Free Workplace. (MAY 2001) 52.224-2 Privacy Act. (APR 1984) 52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008) 52.228-11 Pledges of Assets. (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014) 52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014) 52.232-23 Assignment of Claims. (MAY 2014) 52.232-27 Prompt payment for construction contracts. (MAY 2014) 52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL 2013) 52.233-1 Disputes. (MAY 2014) 52.233-3 Protest after Award. (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004) 52.236-5 Material and Workmanship. (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984) 52.236-10 Operations and Storage Areas. (APR 1984) 52.236-12 Cleaning Up. (APR 1984) 52.236-13 Accident Prevention. (NOV 1991) 52.245-1 Government Property. (APR 2012) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form). (APR 1984) 52.249-10 Default (Fixed-Price Construction). (APR 1984) 452.236-73 Archaeological or Historic Sites. (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution. (NOV 1996)
52.217-7 Option for Increased Quantity-Separately Priced Line Item. (Mar 1989) The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within [insert in the clause the period of time in which the Contracting Officer has to exercise the option]. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
52.219-6 Notice of Total Small Business Set-Aside. (NOV 2011)
(a) Definition. "Small business concern," as used in this clause, means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the size standards in this solicitation.
(b) Applicability. This clause applies only to--
(1) Contracts that have been totally set aside or reserved for small business concerns; and
(2) Orders set aside for small business concerns under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F).
(c) General. (1) Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.
(2) Any award resulting from this solicitation will be made to a small business concern.
(d) Agreement. A small business concern submitting an offer in its own name shall furnish, in performing the contract, only end items manufactured or produced by small business concerns in the United States or its outlying areas. If this procurement is processed under simplified acquisition procedures and the total amount of this contract does not exceed $25,000, a small business concern may furnish the product of any domestic firm. This paragraph does not apply to construction or service contracts.
52.222-8 Payrolls and Basic Records. (MAY 2014)
(a) Payrolls and basic records relating thereto shall be maintained by the Contractor during the course of the work and preserved for a period of 3 years thereafter for all laborers and mechanics working at the site of the work. Such records shall contain the name, address, and social security number of each such worker, his or her correct classification, hourly rates of wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof of the types described in 40 U.S.C. 3141(2)(B) (Construction Wage Rate Requirement statute)), daily and weekly number of hours worked, deductions made, and actual wages paid. Whenever the Secretary of Labor has found, under paragraph (d) of the clause entitled Construction Wage Rate Requirements, that the wages of any laborer or mechanic include the amount of any costs reasonably anticipated in providing benefits under a plan or program described in 40 U.S.C. 3141(2)(B), the Contractor shall maintain records which show that the commitment to provide such benefits is enforceable, that the plan or program is financially responsible, and that the plan or program has been communicated in writing to the laborers or mechanics affected, and records which show the costs anticipated or the actual cost incurred in providing such benefits. Contractors employing apprentices or trainees under approved programs shall maintain written evidence of the registration of apprenticeship programs and certification of trainee programs, the registration of the apprentices and trainees, and the ratios and wage rates prescribed in the applicable programs.
(b)(1) The Contractor shall submit weekly for each week in which any contract work is performed a copy of all payrolls to the Contracting Officer. The payrolls submitted shall set out accurately and completely all of the information required to be maintained under paragraph (a) of this clause, except that full social security numbers and home addresses shall not be included on weekly transmittals. Instead the payrolls shall only need to include an individually identifying number for each employee (e.g., the last four digits of the employee's social security number). The required weekly payroll information may be submitted in any form desired. Optional Form WH-347 is available for this purpose and may be obtained from the U.S. Department of Labor Wage and Hour Division website at http://www.dol.gov/whd/forms/wh347.pdf. The Prime Contractor is responsible for the submission of copies of payrolls by all subcontractors. Contractors and subcontractors shall maintain the full social security number and current address of each covered worker, and shall provide them upon request to the Contracting Officer, the Contractor, or the Wage and Hour Division of the Department of Labor for purposes of an investigation or audit of compliance with prevailing wage requirements. It is not a violation of this section for a Prime Contractor to require a subcontractor to provide addresses and social security numbers to the Prime Contractor for its own records, without weekly submission to the Contracting Officer.
(2) Each payroll submitted shall be accompanied by a Statement of Compliance, signed by the Contractor or subcontractor or his or her agent who pays or supervises the payment of the persons employed under the contract and shall certify -
(i) That the payroll for the payroll period contains the information required to be maintained under paragraph (a) of this clause and that such information is correct and complete;
(ii) That each laborer or mechanic (including each helper, apprentice, and trainee) employed on the contract during the payroll period has been paid the full weekly wages earned, without rebate, either directly or indirectly, and that no deductions have been made either directly or indirectly from the full wages earned, other than permissible deductions as set forth in the Regulations, 29 CFR Part 3; and
(iii) That each laborer or mechanic has been paid not less than the applicable wage rates and fringe benefits or cash equivalents for the classification of work performed, as specified in the applicable wage determination incorporated into the contract.
(3) The weekly submission of a properly executed certification set forth on the reverse side of Optional Form WH-347 shall satisfy the requirement for submission of the Statement of Compliance required by subparagraph (b)(2) of this clause.
(4) The falsification of any of the certifications in this clause may subject the Contractor or subcontractor to civil or criminal prosecution under Section 1001 of Title 18 and Section 3729 of Title 31 of the United States Code.
(c) The Contractor or subcontractor shall make the records required under paragraph (a) of this clause available for inspection, copying, or transcription by the Contracting Officer or authorized representatives of the Contracting Officer or the Department of Labor. The Contractor or subcontractor shall permit the Contracting Officer or representatives of the Contracting Officer or the Department of Labor to interview employees during working hours on the job. If the Contractor or subcontractor fails to submit required records or to make them available, the Contracting Officer may, after written notice to the Contractor, take such action as may be necessary to cause the suspension of any further payment. Furthermore, failure to submit the required records upon request or to make such records available may be grounds for debarment action pursuant to 29 CFR 5.12.
52.222-99 Establishing a Minimum Wage for Contractors (DEVIATION) This clause implements Executive Order 13658, Establishing a Minimum Wage for Contractors, dated February 12, 2014, and OMB Policy Memorandum M-14-09, Implementation of the President's Executive Order Establishing a Minimum Wage for Contractors, dated June 12, 2014.
(a) Each service employee, laborer, or mechanic employed in the United States (the 50 states and the District of Columbia) in the performance of this contract by the prime Contractor or any subcontractor, regardless of any contractual relationship which may be alleged to exist between the Contractor and service employee, laborer, or mechanic, shall be paid not less than the applicable minimum wage under Executive Order 13658. The minimum wage required to be paid to each service employee, laborer, or mechanic performing work on this contract between January 1, 2015, and December 31, 2015, shall be $10.10 per hour.
(b) The Contractor shall adjust the minimum wage paid under this contract each time the Secretary of Labor's annual determination of the applicable minimum wage under section 2(a)(ii) of Executive Order 13658 results in a higher minimum wage. Adjustments to the Executive Order minimum wage under section 2(a)(ii) of Executive Order 13658 will be effective for all service employees, laborers, or mechanics subject to the Executive Order beginning January 1 of the following year. The Secretary of Labor will publish annual determinations in the Federal Register no later than 90 days before such new wage is to take effect. The Secretary will also publish the applicable minimum wage on www.wdol.gov (or any successor website). The applicable published minimum wage is incorporated by reference into this contract.
(c) The Contracting Officer will adjust the contract price or contract unit price under this clause only for the increase in labor costs resulting from the annual inflation increases in the Executive Order 13658 minimum wage beginning on January 1, 2016. The Contracting Officer shall consider documentation as to the specific costs and workers impacted in determining the amount of the adjustment.
(d) The Contracting Officer will not adjust the contract price under this clause for any costs other than those identified in paragraph (c) of this clause, and will not provide price adjustments under this clause that result in duplicate price adjustments with the respective clause of this contract implementing the Service Contract Labor Standards statute (formerly known as the Service Contract Act) or the Wage Rate Requirements (Construction) statute (formerly known as the Davis Bacon Act).
(e) The Contractor shall include the substance of this clause, including this paragraph (e) in all subcontracts.
52.228-2 Additional Bond Security. (OCT 1997) The Contractor shall promptly furnish additional security required to protect the Government and persons supplying labor or materials under this contract if -
(a) Any surety upon any bond, or issuing financial institution for other security, furnished with this contract becomes unacceptable to the Government;
(b) Any surety fails to furnish reports on its financial condition as required by the Government;
(c) The contract price is increased so that the penal sum of any bond becomes inadequate in the opinion of the Contracting Officer; or
(d) An irrevocable letter of credit (ILC) used as security will expire before the end of the period of required security. If the Contractor does not furnish an acceptable extension or replacement ILC, or other acceptable substitute, at least 30 days before an ILC's scheduled expiration, the Contracting officer has the right to immediately draw on the ILC.
52.228-13 Alternative Payment Protections. (JUL 2000)
(a) The Contractor shall submit one of the following payment protections:
Payment Bond;
Irrevocable Letter of Credit;
Certificates of Deposit
(b) The amount of the payment protection shall be 100 percent of the contract price.
(c) The submission of the payment protection is required within 10 days of contract award.
(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.
(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.
(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.
452.228-70 Alternative Forms of Security. (NOV 1996) If furnished as security, money orders, drafts, cashiers checks, or certified checks shall be drawn payable to: USDA Forest Service
52.228-14 Irrevocable Letter of Credit. (NOV 2014)
(a) "Irrevocable letter of credit" (ILC), as used in this clause, means a written commitment by a federally insured financial institution to pay all or part of a stated amount of money, until the expiration date of the letter, upon presentation by the Government (the beneficiary) of a written demand therefor. Neither the financial institution nor the offeror/Contractor can revoke or condition the letter of credit.
(b) If the offeror intends to use an ILC in lieu of a bid bond, or to secure other types of bonds such as performance and payment bonds, the letter of credit and letter of confirmation formats in paragraphs (e) and (f) of this clause shall be used.
(c) The letter of credit shall be irrevocable, shall require presentation of no document other than a written demand and the ILC (including confirming letter, if any), shall be issued/confirmed by an acceptable federally insured financial institution as provided in paragraph (d) of this clause, and-
(1) If used as a bid guarantee, the ILC shall expire no earlier than 60 days after the close of the bid acceptance period;
(2) If used as an alternative to corporate or individual sureties as security for a performance or payment bond, the offeror/Contractor may submit an ILC with an initial expiration date estimated to cover the entire period for which financial security is required or may submit an ILC with an initial expiration date that is a minimum period of one year from the date of issuance. The ILC shall provide that, unless the issuer provides the beneficiary written notice of non-renewal at least 60 days in advance of the current expiration date, the ILC is automatically extended without amendment for one year from the expiration date, or any future expiration date, until the period of required coverage is completed and the Contracting Officer provides the financial institution with a written statement waiving the right to payment. The period of required coverage shall be:
(i) For contracts subject to 40 U.S.C. chapter 31, subchapter III, Bonds, the later of-
(A) One year following the expected date of final payment;
(B) For performance bonds only, until completion of any warranty period; or
(C) For payment bonds only, until resolution of all claims filed against the payment bond during the one-year period following final payment.
(ii) For contracts not subject to 40 U.S.C. chapter 31, subchapter III, Bonds, the later of-
(A) 90 days following final payment; or
(B) For performance bonds only, until completion of any warranty period.
(d)(1) Only federally insured financial institutions rated investment grade by a commercial rating service shall issue or confirm the ILC.
(2) Unless the financial institution issuing the ILC had letter of credit business of at least $25 million in the past year, ILCs over $5 million must be confirmed by another acceptable financial institution that had letter of credit business of at least $25 million in the past year.
(3) The Offeror/Contractor shall provide the Contracting Officer a credit rating that indicates the financial institutions have the required credit rating as of the date of issuance of the ILC.
(4) The current rating for a financial institution is available through any of the following rating services registered with the U.S. Securities and Exchange Commission (SEC) as a Nationally Recognized Statistical Rating Organization (NRSRO). NRSRO's can be located at the Web site http://www.sec.gov/answers/nrsro.htm maintained by the SEC.
(e) The following format shall be used by the issuing financial institution to create an ILC:
Issuing Financial Institution's Letterhead or Name and Address Issue Date __________ Irrevocable Letter of Credit No. __________ Account party's name ___________ Account party's address __________ For Solicitation No. ___________ (for reference only) To: (U.S. Government agency) (U.S. Government agency's address)
1. We hereby establish this irrevocable and transferable Letter of Credit in your favor for one or more drawings up to United States $______. This Letter of Credit is payable at (issuing financial institution's and, if any, confirming financial institution's) office at (issuing financial institution's address and, if any, confirming financial institution's address) and expires with our close of business on ___________, or any automatically extended expiration date.
2. We hereby undertake to honor your or the transferee's sight draft(s) drawn on the issuing or, if any, the confirming financial institution, for all or any part of this credit if presented with this Letter of Credit and confirmation, if any, at the office specified in paragraph 1 of this Letter of Credit on or before the expiration date or any automatically extended expiration date.
3. (This paragraph is omitted if used as a bid guarantee, and subsequent paragraphs are renumbered.) It is a condition of this Letter of Credit that it is deemed to be automatically extended without amendment for one year from the expiration date hereof, or any future expiration date, unless at least 60 days prior to any expiration date, we notify you or the transferee by registered mail, or other receipted means of delivery, that we elect not to consider this Letter of Credit renewed for any such additional period. At the time we notify you, we also agree to notify the account party (and confirming financial institution, if any) by the same means of delivery.
4. This Letter of Credit is transferable. Transfers and assignments of proceeds are to be effected without charge to either the beneficiary or the transferee/assignee of proceeds. Such transfer or assignment shall be only at the written direction of the Government (the beneficiary) in a form satisfactory to the issuing financial institution and the confirming financial institution, if any.
5. This Letter of Credit is subject to the Uniform Customs and Practice (UCP) for Documentary Credits, International Chamber of Commerce Publication No.___ (Insert version in effect at the time of ILC issuance, e.g., "Publication 600, 2006 edition") and to the extent not inconsistent therewith, to the laws of ___________ (State of confirming financial institution, if any, otherwise State of issuing financial institution).
6. If this credit expires during an interruption of business of this financial institution as described in Article 17 of the UCP, the financial institution specifically agrees to effect payment if this credit is drawn against within 30 days after the resumption of our business.
Sincerely, (Issuing financial institution)
(f) The following format shall be used by the financial institution to confirm an ILC:
(Confirming Financial Institution's Letterhead or Name and Address) (Date) Our Letter of Credit Advice Number _____________ Beneficiary: ___________ (U.S. Government agency) Issuing Financial Institution: __________________ Issuing Financial Institution's LC No.: ___________ Gentlemen:
1. We hereby confirm the above indicated Letter of Credit, the original of which is attached, issued by __________ (name of issuing financial institution) for drawings of up to United States dollars ___________/U.S. $_______ and expiring with our close of business on _____________ (the expiration date), or any automatically extended expiration date.
2. Draft(s) drawn under the Letter of Credit and this Confirmation are payable at our office located at ___________________.
3. We hereby undertake to honor sight draft(s) drawn under and presented with the Letter of Credit and this Confirmation at our offices as specified herein.
4. (This paragraph is omitted if used as a bid guarantee, and subsequent paragraphs are renumbered.) It is a condition of this confirmation that it be deemed automatically extended without amendment for one year from the expiration date hereof, or any automatically extended expiration date, unless:
(a) At least 60 days prior to any such expiration date, we shall notify the Contracting Officer, or the transferee and the issuing financial institution, by registered mail or other receipted means of delivery, that we elect not to consider this confirmation extended for any such additional period; or
(b) The issuing financial institution shall have exercised its right to notify you or the transferee, the account party, and ourselves, of its election not to extend the expiration date of the Letter of Credit.
5. This confirmation is subject to the Uniform Customs and Practice (UCP) for Documentary Credits, International Chamber of Commerce Publication No.___ (Insert version in effect at the time of ILC issuance, e.g., "Publication 600, 2006 edition") and to the extent not…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .