Atch_3_Drawings.pdf

PDF 2 MB Posted

Attached to
Removal & Replacement of Wooden Walkway at Green Ridge Lookout
Solicitation number
AG-04GG-S-17-0003
Issued by

About this file

Drawings Atch 3

View the file

Other files

File Type Posted
Atch_1-2__Specs.pdf PDF
Atch_5__Fire_Clauses_r6-fs-6300-52.pdf PDF
AG-04GG-S-17-0003.pdf PDF
Atch_4__Wage_Decision_OR160049.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GREEN RIDGE LOOKOUT WALKWAY REPLACEMENT

CONSTRUCTION PROJECT

DESCHUTES NATIONAL FOREST SISTERS RANGER DISTRICT

SHT. SHEET INDEX

1. COVER SHEET

2. VICINITY MAP

3. SITE PLAN

4. STRUCTURAL NOTES

5. STRUCTURAL NOTES CONT.

6. WALKWAY PLAN & ELEVATION

7. WALKWAY DECK

8. SUPPORT & APPROACH

9. BEARING SHOE

10. FOUNDATION

11. COLUMN & BASE

OREGON

N

BEND

PROJECT LOCATION

26 97

97 395

APPROVALS

REVIEWED BY:

/s/ PROJECT ENGINEER - Lisa Anheluk DATE

TECHNICALLY APPROVED BY:

/s/ FOREST ENGINEER - Peggy Fisher DATE

RECOMMENDED BY:

/s/ RECREATION STAFF - Amy Racki DATE

RECOMMENDED BY:

/s/ DISTRICT RANGER - Kristie Miller DATE

APPROVED BY:

/s/ FOREST SUPERVISOR - John Allen DATE

STRUCTURAL ONLY

SITE PLAN - GREEN RIDGE LOOKOUT

N

WALKWAY

TOILET

BUILDING

GREEN RIDGE

LOOKOUT

PARKING

BURIED

PROPANE LINE EXISTING WALKWAY

LENGTH: 24'

WITDH 3'

1. SIMPLY SUPPORTED ON GROUND AND TOWER CROSS BRACING AT

LOOKOUT WITH MID-SPAN SUPPORT.

2. THE HEIGHT OF WALKWAY IS APPROX. 10' AT THE FAR

SUPPORT. THE GROUND SLOPE IS APPROX. 40%.

3. A 12" PROPANE LINE IS RUN UNDER THE WALKWAY. LEAVE IN

PLACE (SUPPORT AS NECESSARY) AND REATTACH WITH EXISTING

HARDWARE WHEN NEW WALKWAY IS IN PLACE.FENCE