Attachment 4 plan sheet 3.pdf
PDF 9 KB Posted
- Solicitation number
- AG-0489-S-10-0202
About this file
Attachment 4 - Plan sheet 3
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 30 -0202 amendment 3.pdf | ||
| SF 30 -0202Amend2.pdf | ||
| Mailing list 0202.xls | XLS spreadsheet | |
| FS ARRA SIGN DETAILS 2apr09.pdf | ||
| SF 30.pdf | ||
| Attachment 7 R-6 Fire Plan Template.pdf | ||
| Attachment 2 plan sheet 1a.pdf | ||
| Attachment 1 plan sheet 1.pdf | ||
| Attachment 3 plan sheet 2.pdf | ||
| Solicitation 0489-0202 RD60.pdf | ||
| Attachment 5 plan sheet 4.pdf | ||
| Attachment 6 Fire Protection.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mile Post Work Item sheet 3 of 4 of plans
10.90
Junction of 60 and 65 road. Begin rocking segment #1. Begin scarification -continue through entire length of project. Begin blade and shape of road bed and ditch (where existing ditch is present or designated by Forest
Service) - ditch depth to be 12" and maximum slope of 3:1 (or as agreed).
Remove 35 boulders from subgrade (existing travelway) between MP 10.9 and 12.2 - to be marked by FS. Begin placement of aggregate - depth 3" unless otherwise noted. Width to match existing aggregate width unless otherwise marked by FS. Boulders and rocks dislodged through work process are to be placed below shoulder on fill side of road.
13.00 End rocking segment #1
13.0-15.3
Continue item 30322 (Road reconditioning, compaction method B) through this section after completion of all haul and placement of aggregate.
15.30
Junction of 6000240 road left. Begin rocking segment #2. Begin scarification - continue through entire length of project. Begin blade and shape of road bed and ditch (where existing ditch is present or designated by Forest Service) - ditch depth to be 12" and maximum slope of 3:1 (or as agreed). Begin placement of aggregate - depth 3" unless otherwise noted. Width to match existing aggregate width unless otherwise marked by FS. Boulders and rocks dislodged through work process are to be placed below shoulder on fill side of road. MP 16.57 at inside of curve add an additional 3" depth by 12' wide by 60 ft length.
21.50 End rocking segment #2 at junction of road 6020
NOTES -
Quarry development is incidental to Item 32203.
Include crusher mobilization in item 15101 (mobilization)
Provide a minimum of two AASHTO T-11 and T-27 tests daily.
Measurement of aggregate quantity is in place, compacted on road.
Preform all maintenance prior to, and during haul necessary to keep road in a condition suitable for all traffic use on the haul and project roads.
ARRA signage requirements are listed in Section C of the contract
Water sources require approval from the Forest Service prior to use