Attachment__1_Well-Decom-Specifications.docx
DOCX document 48 KB Posted
- Solicitation number
- AG-046W-S-16-0035
About this file
Attachment 1 - Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AG-046W-S-16-0035_Well_Decommissioning.pdf | ||
| Attachment_2_Well-Decom-Maps-Descriptions.pdf | ||
| WAGE_DECISIONS.zip | ZIP file | |
| Attachment__4_Forest_Service_Fire_Protection_R6-FS-6300-52.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CRGNSA Well Decommissioning Specifications Contents
| DIVISION 100 | GENERAL REQUIREMENTS | 1 |
| Section 101. – TERMS, FORMAT, AND DEFINITIONS | 1 | |
| Section 103. — SCOPE OF WORK | 4 | |
| Section 104. — CONTROL OF WORK | 4 | |
| Section 105. — CONTROL OF MATERIAL | 5 | |
| Section 106. — ACCEPTANCE OF WORK | 5 | |
| Section 107. — LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC | 7 | |
| Section 109. — MEASUREMENT AND PAYMENT | 8 | |
| DIVISION 150 | PROJECT REQUIREMENTS | 10 |
| Section 151. — MOBILIZATION | 10 | |
| Section 156. — PUBLIC TRAFFIC | 10 | |
| DIVISION 200 | EARTHWORK | 12 |
| Section 201. — CLEARING AND GRUBBING | 12 | |
| Section 203. — REMOVAL OF STRUCTURES AND OBSTRUCTIONS | 12 | |
| Section 214. — WELL DECOMMISSIONING | 13 |
DIVISION 100 GENERAL REQUIREMENTS
Section 101. – TERMS, FORMAT, AND DEFINITIONS
101.01 Meaning of Terms. These specifications are generally written in the imperative mood. In sentences using the imperative mood, the subject, "the Contractor," is implied. Also implied in this language are "shall," "shall be," or similar words and phrases. In material specifications, the subject may also be the supplier, fabricator, or manufacturer supplying material, products, or equipment for use on the project.
Wherever "directed," "required," "prescribed," or other similar words are used, the "direction," "requirement," or "order" of the Contracting Officer is intended. Similarly, wherever "approved," "acceptable," "suitable," "satisfactory," or similar words are used, the words mean "approved by," "acceptable to," or "satisfactory to" the Contracting Officer.
The word "will" generally pertains to decisions or actions of the Contracting Officer.
101.02 Specifications Format. These specifications are divided into 10 Divisions.
Division 100 consists of general contract requirements for which no direct payment is made. The requirements contained in Division 100 are applicable to all contracts.
Division 150 consists of project contract requirements that are applicable to all contracts. Work under Division 150 is paid for directly or indirectly according to Subsection 109.05 and the Section ordering the work. When there is no pay item in the bid schedule, no direct payment is made.
Divisions 200 through 600 consist of construction contract requirements for specific items of work. Work under these Divisions is paid for directly or indirectly according to Subsection 109.05 and the Section ordering the work. When there is no pay item in the bid schedule, no direct payment is made.
Division 700 contains the material requirements for Divisions 150 through 600. No direct payment is made in Division 700. Payment for material is included as part of the work required in Divisions 150 through 600.
The first three digits of the pay item number in the Bid Schedule identify the Section under which the work is performed.
101.03 Abbreviations. Whenever these abbreviations are used in the specifications, they represent the following:
(a) Acronyms.
CFR – Code of Federal Regulations CO – Contracting Officer CQ – Contract Quantity FAR – Federal Acquisition Regulations FSM – Forest Service Manual LS – Lump Sum LSQ – Lump Sum Quantity MI – Mile USC – United States Code VECP – Value Engineering Change Proposal
101.04 Definitions. The following definitions apply to this contract:
Award — The written acceptance of a bid by the CO.
Backfill — Material used to replace or the act of replacing material removed during construction. Material placed or the act of placing material adjacent to structures.
Bid — A written offer by a bidder to perform work at a quoted price.
Bidder — Any individual or legal entity submitting a bid.
Bid Guarantee — A form of security assuring that the bidder will not withdraw a bid within the period specified for acceptance and will execute a written contract and furnish required bonds.
Bid Schedule — The prepared schedule included with the bid forms, containing the estimated quantities of pay items for which unit bid prices are invited.
Construction Limits — The limits on each side of the project that establish the area disturbed by construction operations and beyond which no disturbance is permitted. Typically the construction limits are the same as the clearing limits, except when additional clearing is required.
Contract — The written agreement between the Government and the Contractor setting forth the obligations of the parties for the performance of and payment for the prescribed work.
Contracting Officer (CO) — An official of the Government with the authority to enter into, administer, and terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the CO acting within the limits of their authority as delegated by the CO.
Contract Modification — Any written change in the terms of the contract. Contract modifications are of the following forms:
(a) Administrative change. A unilateral contract change, in writing, that does not affect the substantive rights of the parties (e.g., a change in the paying office or the appropriation data).
(b) Change order. A written order, signed by the CO, directing the Contractor to make a change that FAR Clause 52.243-4 Changes authorizes the CO to order without the Contractor's consent.
(c) Supplemental agreement. A contract modification that is accomplished by the mutual action of the parties.
Contractor — The individual or legal entity contracting with the Government for performance of prescribed work.
Contract Time — The specified time allowed for completion of all contract work.
Day — Each and every day shown on the calendar, beginning and ending at midnight.
Drawings — Design sheets or fabrication, erection, or construction details submitted to the Government by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.
Government — The Government of the United States of America.
Material — Any substances specified or necessary to satisfactorily complete the contract work.
Measurement — The process of identifying the dimensions, quantity, or capacity of an item. See Section 109 for measurement methods, terms, and definitions.
Notice to Proceed — Written notice to the Contractor to begin the contract work.
Pay Item — A specific item of work for which a unit and price is provided in the contract.
Payment Bond — The security executed by the Contractor and surety or sureties and furnished to the Government to ensure payments as required by law to all persons supplying labor or material according to the contract.
Performance Bond — The security executed by the Contractor and surety or sureties furnished to the Government to guarantee completion of the contract work.
Plans — The contract plans furnished by the Government showing the location, type, dimensions, and details of the work.
Solicitation — The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.
Special Contract Requirements — Additions and revisions to the standard specifications applicable to an individual project.
Specifications — The written requirements for performing work.
Standard Forms — Numbered forms issued by the General Services Administration for use as contract documents.
Standard Plans — Detailed plans approved for repetitive use and included as part of the plans.
Subcontract — The written agreement between the Contractor and an individual or legal entity prescribing the performance of a specific portion of the work.
Subcontractor — An individual or legal entity with which the Contractor sublets part of the work. This includes all subcontractors in any tier.
Substantial Completion — The point at which the project is complete such that it can be safely and effectively used by the public without further delays, disruption, or other impediments.
Superintendent — The Contractor's authorized representative in responsible charge of the work.
Surety — An individual or corporation legally liable for the debt, default, or failure of a Contractor to satisfy a contract obligation.
Traveled Way — The portion of the roadway designated for the movement of forest users.
Unsuitable Material — Material not capable of creating stable foundations, embankments, or trailbeds. Unsuitable material includes muck, sod, or soils with high organic contents.
Work — The furnishing of all labor, material, equipment, and other incidentals necessary to successfully complete the project according to the contract.
Section 103. — SCOPE OF WORK
103.01 Intent of Contract. The intent of the contract is to provide for the construction and completion of the work described. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.
Section 104. — CONTROL OF WORK
104.05 Load Restrictions. Comply with all legal load restrictions when hauling material and equipment on public trails and roads to and from the project. A special permit does not relieve the Contractor of liability for damage resulting from the moving of material or equipment. Unless otherwise permitted, do not operate equipment or vehicles that exceed the legal load limits over new or existing structures, or pavements within the project except those pavements intended to be removed.
Section 105. — CONTROL OF MATERIAL
105.01 Source of Supply and Quality Requirements.
Select sources and provide acceptable material.
Material may be approved at the source of supply before delivery to the project. Approval does not constitute acceptance. If an approved source does not continue to supply acceptable material during the life of the project, further use of that source may be denied.
105.03 Material Source Management. Control erosion so that sediment does not leave the work area.
Section 106. — ACCEPTANCE OF WORK
106.01 Conformity with Contract Requirements. References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids. Perform work according to the contract requirements. Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is stricter. Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.04 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
As an alternative to removal and replacement, the Contractor may submit a written request to:
1) Have the work accepted at a reduced price; or
2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
106.02 Visual Inspection. Acceptance is based on visual inspection of the work for compliance with the contract and prevailing industry standards.
106.03 Certification. For material manufactured off-site, use a manufacturer with an ISO 9000 certification or an effective testing and inspection system. Require the manufacturer to clearly mark the material or packaging with a unique product identification or specification standard to which it is produced. Other than references in or to the FAR or Federal Law, when these Standard Specifications reference certifications; certificates; or certified documents, equipment, or individuals, these references are not certifications under Section 4301 of Public Law 104-106, National Defense Authorization Act for Fiscal Year 1996. These references refer to documentation of non-regulatory, peripheral contract requirements that are required to be validated by an individual or organization having unique knowledge or qualifications to perform such validation.
Material accepted by certification may be sampled and tested at any time. If found not in conformance with the contract, the material will be rejected whether in place or not.
(a) Commercial certification. When a certification is required, but not a production certification, furnish one commercial certification for all similar material from the same manufacturer. A commercial certification is a manufacturer's or Contractor's representation that the material complies with all contract requirements. The representation may be labels, catalog data, stamped specification standards, or supplier's certifications indicating the material is produced to a commercial standard or specification. Produce certifications for pipe, geotextile, posts, and any hardware used in structure construction. If signs are not obtained from Condon Sign Shop provide commercial certification for signs and bulletin boards.
106.04 Measured or Tested Conformance. Provide all necessary production and processing of the work and control performance of the work so that all of the work complies with the contract requirements.
Results from inspection or testing shall have values within the specified tolerances or specification limits. When no tolerance values are identified in the contract, the work will be accepted based on customary manufacturing and construction tolerances.
Section 107. — LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
107.01 Laws to be Observed. Comply with all applicable laws, ordinances, safety codes, regulations, orders, and decrees. Protect and indemnify the Government and its representatives against any claim or liability arising from or based on the alleged violation of the same.
Comply with all permits and agreements obtained by the Government for performing the work that is included in the contract. Obtain all additional permits or agreements and modifications to Government-obtained permits or agreements that are required by the Contractor's methods of operation. Furnish copies of all permits and agreements.
107.02 Protection and Restoration of Property and Landscape. Preserve public and private property, and protect monuments established for the purpose of perpetuating horizontal, vertical, cadastral, or boundary control. When necessary to destroy a monument, reestablish the monument according to applicable state statute or by the direction of the agency or individual who established the monument.
Do not disturb the area beyond the construction limits. Replace trees, shrubs, or vegetated areas damaged by construction operations as directed and at no cost to the Government.
Do not excavate, remove, damage, alter, or deface any archeological or paleontological remains or specimens. Control the actions of employees and subcontractors on the project to ensure that protected sites are not disturbed or damaged. Should any of these items be encountered, suspend operations at the discovery site, immediately notify the CO, and continue operations in other areas. The CO will inform the Contractor when operations may resume at the discovery site. The Rawhide Trail runs adjacent to old cabin remnants. Do not disturb these remnants. If historic mining relics are found while excavating trail tread, stop work in the area. Relics need only be 50 years to qualify as historic. Most waste from old mines in this area qualifies as historic.
107.06 Contractor's Responsibility for Work. Assume responsibility for all work until final acceptance. This includes periods of suspended work. Protect the work against injury, loss, or damage from all causes whether arising from the execution or nonexecution of the work.
Maintain public traffic according to Section 156. Rebuild, repair, restore, and make good all losses, injuries, or damages to any portion of the work. This includes losses, injuries, or damages caused by vandalism, theft, accommodation of public traffic, and weather that occurs during the contract. The Government will only be responsible for losses, injuries, and damages to work put in place that was caused by declared enemies and terrorists of the Government and cataclysmic natural phenomenon such as tornadoes, earthquakes, major floods, and other officially declared natural disasters. The Government will only be responsible for costs attributable to repairing or replacing damaged work. The Government will not be responsible for delay costs, impact costs, or extended overhead costs.
107.07 Furnishing Right-of-Way. The Government will obtain all right-of-way.
107.08 Sanitation, Health, and Safety. Observe rules and regulations of Federal, State, and local health officials. Do not permit any worker to work in surroundings or under conditions that are unsanitary, hazardous, or dangerous.
Admit any OSHA inspector or other legally responsible official involved in safety and health administration to the project work site upon presentation of proper credentials.
Report accidents on forms furnished by the Government or, with prior approval, on forms used to report accidents to other agencies or insurance carriers. Maintain a "Log of Work Related Injuries and Illnesses," OSHA Form 300, and make it available for inspection.
107.10 Environmental Protection. Do not operate mechanized equipment or discharge or otherwise place any material within the wetted perimeter of any waters of the U.S. within the scope of the Clean Water Act (33 USC § 1251 et seq.). This includes wetlands unless authorized by a permit issued by the U.S. Army Corps of Engineers according to 33 USC § 1344. In the event of an unauthorized discharge:
(a) Immediately prevent further contamination;
(b) Immediately notify appropriate authorities; and
(c) Mitigate damages as required.
Comply with the terms and conditions of any permits that are issued for the performance of work within the wetted perimeter of the waters of the U.S. Separate work areas, including material sources, by the use of a dike or other suitable barrier that prevents sediment, petroleum products, chemicals, or other liquid or solid material from entering the waters of the U.S. Use care in constructing and removing the barriers to avoid any discharge of material into, or the siltation of, the water. Remove and properly dispose of the sediment or other material collected by the barrier.
Repair leaks on equipment immediately. Do not use equipment that is leaking. Keep a supply of acceptable absorbent materials at the job site in the event of spills. Acceptable absorbent materials are those that are manufactured specifically for the containment and clean up of hazardous materials.
Section 109. — MEASUREMENT AND PAYMENT
109.01 Measurement of Work. Take and record measurements and perform calculations to determine pay quantities for invoicing for work performed.
109.02 Measurement Terms and Definitions. Unless otherwise specified, the following terms are defined as follows:
(a) Lump sum. Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item. The quantity is designated as "All." Estimated quantities of lump sum work shown in the contract are approximate.
109.05 Scope of Payment. Payment for all contract work is provided, either directly or indirectly, under the pay items shown in the bid schedule.
(a) Direct payment. Payment is provided directly under a pay item shown in the bid schedule when one of the following applies:
(1) The work is measured in the Measurement Subsection of the Section ordering the work, and the bid schedule contains a pay item for the work from the Section ordering the work.
(2) The Measurement Subsection, of the Section ordering the work, references another Section for measuring the work and the bid schedule contains a pay item for the work from the referenced Section.
(b) Indirect payment. Work for which direct payment is not provided is a subsidiary obligation of the Contractor. Payment for such work is indirectly included under other pay items shown in the bid schedule. This includes instances when the Section ordering the work references another Section for performing the work and the work is not referenced in the Measurement Subsection of the Section ordering the work.
Compensation provided by the pay items included in the contract bid schedule is full payment for performing all contract work in a complete and acceptable manner. All risk, loss, damage, or expense arising out of the nature or prosecution of the work is included in the compensation provided by the contract pay items. Work measured and paid for under one pay item will not be paid for under any other pay item.
The quantities shown in the bid schedule are approximate unless designated as a contract quantity. Limit pay quantities to the quantities staked, ordered, or otherwise authorized before performing the work. Payment will be made for the actual quantities of work performed and accepted or material furnished according to the contract. No payment will be made for work performed in excess of that staked, ordered, or otherwise authorized.
DIVISION 150 PROJECT REQUIREMENTS
Section 151. — MOBILIZATION
Description
151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site. Mobilization includes the obtaining of permits, insurance, and bonds.
Measurement
151.02 Measure mobilization according to Subsection 109.02.
Payment
151.03 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Progress payments for mobilization lump sum will be paid as follows:
(a) Bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.
Section 156. — PUBLIC TRAFFIC
Description
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
Material
156.02 Conform to the following Section: Temporary traffic control 635 Construction Requirements
156.03 Accommodating Traffic During Work. Perform work in a manner that ensures the safety and convenience of the public and protects the residents and property adjacent to the project. Accommodate public traffic on trails adjacent to and within the project until the project is accepted according to Subsection 106.07(b).
156.05 Maintaining Roadways During Non-Work Periods. Maintain roadways for public traffic during all periods when work is not in progress. Do not leave equipment on the road if it hinders public traffic.
156.09 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.10 See Subsection 109.05.
DIVISION 200 EARTHWORK
Section 201. — CLEARING AND GRUBBING
Description
201.01 This work consists of clearing and grubbing within the clearing limits designated on the plans.
Material
201.02 Conform to the following Subsections:
Backfill material 704.03 Construction Requirements
201.03 General. Remove brush, small diameter trees, and branches only to the width required to transport well decommissioning equipment to the well head. After work has been completed and the drilling equipment has been removed from the area, place all downed trees, brush and branches back on the roadway to allows only a small pathway for foot traffic.
201.04 Clearing. Clear trees, brush, downed timber, and other vegetation as follows:
(a) Cut stumps to within 6 inches of the ground.
(b) Trim tree branches flush.
201.05 Acceptance. Clearing and grubbing will be evaluated under Subsection 106.02.
Payment
201.06 The accepted quantities will be paid at the contract price per unit of measurement for the Section 203 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05. There is no additional pay item for work described in this section.
Section 203. — REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Description
203.01 This work consists of salvaging, removing, and disposing of buildings, poles, pressure tanks, pumps, pump wiring, casings, trash, concrete, signs, utilities and other obstructions.
Material
203.02 Conform to the following Section and Subsection:
Backfill material 704.03 Construction Requirements
203.03 Salvaging Material. No structures are designated for salvage on this project.
203.04 Removing Material. Do not permit debris to enter waterways or areas designated not to be disturbed. Except in excavation areas, backfill and compact cavities left by structure removal with backfill material to the level of the finished ground.
203.05 Disposing of Material. Dispose of debris and unsuitable and excess material as follows:
0. Remove from project. Recycle or dispose of material legally off the project. Remove the following:
0. Pumps
0. Casings
0. Electrical Wiring
0. Plumbing pipes, valves, and other appurtenances
0. Casings within 30 inches of native surface
0. Buildings
0. Pressure Tanks
0. Bury. Bury debris in trenches or pits in approved areas within the right-of-way. Do not bury debris beneath drainage ditches, or in any areas subject to free-flowing water. Cover the top layer of buried debris with at least 1 foot of compacted earth. Grade and shape the area.
0. Hazardous material. Furnish a copy of all disposal permits. Dispose of material according to Federal, State, and local regulations. Treated timber is considered hazardous, do not burn or bury.
203.06 Acceptance. Removal of structures and obstructions will be evaluated under Subsection 106.02.
Measurement
203.07 Measure the Section 203 items listed in the bid schedule according to Subsection 109.02.
Payment
203.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 203 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Section 214. — WELL DECOMMISSIONING
Description
214.01 This work consists of perforating casings, filling, and sealing wells in accordance with all Oregon and Washington State Rules and Regulations.
Material
214.02 Conform to the following Section and Subsection:
Backfill material 704.03 Construction Requirements-Oregon-Only Excepts Please See the OAR Webpage for Full Text
214.03 Permanent Abandonment. OAR 690-220-0030.
a) Any water supply well that is to be permanently abandoned shall be completely filled in such a manner that vertical movement of water within the well bore, including vertical movement of water within the annular space surrounding the well casing, is effectively and permanently prevented. If a dry or non-producing water supply well is to be permanently abandoned, it shall be abandoned in accordance with these standards. Unless otherwise stated in these rules, all permanent water supply well abandonments shall be performed by a licensed Water Supply Well Constructor.
b) The abandonment procedure shall be recorded on a form provided by or previously approved in writing by the Department. The form shall include, as a minimum, all the requirements as listed in OAR 690-205-0210, plus:
a. Method of abandonment;
b. If assigned, the well identification tag number, original start card number, and owner's well number of the abandoned well.
c) When a well that has a well identification tag on it is permanently abandoned, the well identification tag shall be destroyed. The well identification tag shall not be reused.
Stat. Auth.: ORS 536.090 & 537.505 - 537.795 Stats. Implemented: ORS 536.090 & 537.505 - 537.795 Hist.: WRD 3, f. & ef. 2-18-77; WRD 9-1978, f. 12-12-78, ef. 1-1-79; WRD 13-1986, f. 10-7-86, ef. 11-1-86, Renumbered from 690-063-0010; WRD 8-1993, f. 12-14-93, cert. ef. 1-1-94; WRD 7-2001, f. & cert. ef. 11-15-01; WRD 2-2006, f. & cert. ef. 6-20-06; WRD 3-2008, f. 12-22-08, cert. ef. 1-2-09
214.04 Abandonment of Cased Wells. OAR 690-220-0040.
a) If all or a portion of the water supply well casing or the liner pipe is not removed during the abandonment of a well, the remaining casing or liner shall be thoroughly ripped or perforated. The number and size of perforations may vary, however, the perforations must be sufficient enough to allow grout to migrate outside the casing and effectively prevent the vertical movement of water. The annular space between the casing or liner and the drillhole wall shall be effectively and completely filled with cement grout applied under pressure.
b) Perforations are not required in the sealed interval provided proof of the original seal can be verified with the original well report. The verified seal interval shall be filled with cement grout, concrete or unhydrated bentonite.
c) Uncased portions of a cased well to be abandoned shall be filled in accordance with OAR 690-220-0030 through 690-220-0050.
d) The well casing to be abandoned may be severed below land surface and removed. (See Figure 220-3.)
[ED. NOTE: Figures referenced are available from the agency.] Stat. Auth.: ORS 536.090 & 537.505 - 537.795 Stats. Implemented: ORS 536.090 & 537.505 - 537.795 Hist.: WRD 3, f. & ef. 2-18-77; WRD 9-1978, f. 12-12-78, ef. 1-1-79, Renumbered from 690-063-0011; WRD 8-1993, f. 12-14-93, cert. ef. 1-1-94; WRD 7-2001, f. & cert. ef. 11-15-01; WRD 3-2008, f. 12-22-08, cert. ef. 1-2-09
214.05 Abandonment of Dug Wells. OAR 690-220-0095 (Peterson Site)
a) Abandonment of a dug water supply well shall be approved by the Department before work is started. The Department shall be notified of the proposed abandonment. The notification shall include:
a. Location;
b. Name of the owner;
c. Well diameter;
d. Well depth;
e. Depth to water;
f. Type of well casing or liner material if any; and
g. The proposed method of abandonment.
b) A method to be used in the abandonment will be approved by the Department if the method will adequately protect the ground water resource. Dug wells penetrating more than one water bearing zone shall be abandoned in a manner to eliminate the possibility of leakage from one water bearing zone to another.
c) The well shall be abandoned by a licensed Water Supply Well Constructor, a landowner with a landowner well construction permit and bond, or by a landowner in the presence of the watermaster or other Department representative.
Stat. Auth.: ORS 183, 536, 537 & 540 Stats. Implemented: ORS 183, 536, 537 & 540 Hist.: WRD 7-1988, f. & cert. ef. 6-29-88; WRD 7-2001, f. & cert. ef. 11-15-01; WRD 2-2006, f. & cert. ef. 6-20-06
214.06 Unhydrated Bentonite and Method of Placement OAR 690-220-0115
a) When abandoning a pre-existing well with unhydrated bentonite the Water Supply Well Constructor shall provide additional notification to the Regional Well Inspector or the Well Construction Program Coordinator in Salem by fax, e-mail or telephone 72 hours prior to starting abandonment work.
(a) In case of an emergency, the additional notification is not required; however, the Water Supply Well Constructor shall notify the Department prior to beginning abandonment work as required in OAR 690-205-0200.
b) Unhydrated bentonite used in the abandonment of water supply wells shall meet the following requirements:
(a) Specifically designed for use in water supply wells; and
(b) Within industry tolerance for dry western sodium bentonite; and
(c) Free of polymers that promote bacterial growth; and
(d) Manufactured to be 3/8-inch or 3/4-inch; and
(e) National Sanitation Foundation (NSF) approved or have a swell index greater than 15 milliliters (ml) per 2 grams (gm).
0. Powdered bentonite, bentonite grout or bentonite slurry shall not be used to abandon water supply wells.
0. Unhydrated bentonite shall only be used to abandon water supply wells when in contact with water having less than 800 parts per million (ppm) total dissolved solids (TDS).
2. Unhydrated bentonite may be used to abandon water supply wells exceeding 800 ppm TDS if the bentonite manufacturer provides documentation that their product can be used in water that exceeds 800 ppm TDS.
a. Prior Department approval is required before placement.
b. The bentonite manufacturer’s documentation and Department approval shall be submitted with the Water Supply Well Report as required in OAR 690-205-0210.
2. In all cases, the TDS shall be reported on the Water Supply Well Report as required in OAR 690-205-0210.
0. Water supply wells with casing that is at least four inches in diameter and less than eight inches in diameter may be abandoned with unhydrated bentonite to a maximum well depth of 700 feet, if being placed through water. Unhydrated bentonite may be used deeper with prior Department approval.
c) Water supply wells with casing that is at least four inches in diameter and less than eight inches in diameter may be abandoned with unhydrated bentonite to a maximum well depth of 1000 feet, if being placed through air. Unhydrated bentonite may be used deeper with prior Department approval.
d) Water supply wells with casing that is at least eight inches in diameter may be abandoned with unhydrated bentonite to a maximum well depth of 1200 feet, if being placed through water. Unhydrated bentonite may be used deeper with prior Department approval.
e) Water supply wells with casing that is at least eight inches in diameter may be abandoned with unhydrated bentonite to a maximum well depth of 1500 feet, if being placed through air. Unhydrated bentonite may be used deeper with prior Department approval.
f) Unhydrated bentonite shall be screened across a minimum 1/4-inch mesh screen during placement to minimize the introduction of bentonite dust into the sealing interval. The resulting seal shall be free of voids or bridges.
g) A sounding or tamping tool shall be used in the sealing interval during placement to measure the fill rate and to break up possible bridges or cake formations.
h) Unhydrated bentonite shall be poured at the manufacturers recommended rate in the water- filled portion of the drillhole and shall not be less than two minutes per 50 pound sack.
i) In a dry sealing interval, (above the water level), bentonite shall be hydrated from land surface to a minimum depth of 50 feet below land surface. Unhydrated bentonite shall be hydrated with potable water in maximum ten foot lifts to ensure activation.
j) The estimated and actual volume of sealing material used shall be calculated and reported on the Water Supply Well Report as required by OAR 690-205-0210.
Stat. Auth.: ORS 183, 536, 537 & 540 Stats. Implemented: ORS 183, 536, 537 & 540 Hist.: WRD 3-2008, f. 12-22-08, cert. ef. 1-2-09; WRD 5-2015, f. & cert. ef. 7-1-15
214.07 Cement Grout. OAR 690-220-0120
2) Cement grout for use in abandonment operations shall conform to the requirements of OAR 690-210-0310 as follows:
a) Cement grout used to seal a well shall be composed of a uniformly mixed slurry of Portland cement or High Early Strength Type III Portland cement and potable water, or High-alumina cement and potable water, mixed in the following proportions (Type of Cement -- Gallons of Water Per Sack of Dry Cement, respectively):
(a) Portland Cement -- 4-1/2 to 6;
(b) High Early Strength Type III Portland Cement -- 5-1/2 to 6-1/2;
(c) High-alumina Cement -- 4-1/2 to 6.
b) Additives to increase fluidity, reduce shrinkage, or control time of set may be used in a cement grout mixture. Expanding agents such as aluminum powder may be used at a rate not exceeding 0.075 ounce (one level teaspoonful) per sack of dry cement. The powder shall not contain polishing agents. The addition of bentonite clay to a cement grout mixture is permissible but shall not in any case exceed five percent (5%) by weight of dry cement. Calcium chloride may be added to a Portland cement grout to accelerate the set but shall not exceed two pounds per sack of dry cement. High-alumina cement and Portland cement of any type shall not be mixed together for use in a well.
c) Cement types other than those set forth herein shall not be used as a sealing material in a well except upon written approval of the Director of the Water Resources Department.
d) In no case shall sand or aggregate be added to cement grout seal mixtures.
e) The volume of sealing material required shall be calculated prior to seal installation. The calculated volume and actual volume used shall be reported on the water supply well report.
Stat. Auth.: ORS 183, ORS 536, ORS 537 & ORS 540 Stats. Implemented: ORS 183, ORS 536, ORS 537 & ORS 540 Hist.: WRD 3, f. & ef. 2-18-77; WRD 9-1978, f. 12-12-78; ef. 1-1-79, Renumbered from 690-63-031 by WRD 13-1986, f. 10-7-86, ef. 11-1-86
214.08 Concrete OAR 690-220-0130
a) Concrete for use in abandonment operations shall conform to the requirements of OAR 690-210-0315 as follows:
a. Concrete for use in the construction of a dug well, or for filling the annular space or well bore of a well, shall consist of clean, hard, and durable aggregate, and not less than five sacks of Portland cement per cubic yard of concrete. Concrete will be allowed only when the oversize drill hole is a minimum of eight inches larger in diameter than the well casing used in construction of the well. The maximum diameter of aggregate particles shall not exceed 1-1/2 inches, but, in any case, shall not exceed 1/5 or 20 percent of the minimum width of the space to be filled. The ratio of coarse aggregate to fine aggregate (Passing No. 4, U.S. Standard Sieve) shall be approximately 1-1/2 to 1 by volume, but, in any case, shall not exceed 2 to 1 nor be less than 1 to 2.
Stat. Auth.: ORS 183, ORS 536, ORS 537 & ORS 540 Stats. Implemented: ORS 183, ORS 536, ORS 537 & ORS 540 Hist.: WRD 3, f. & ef. 2-18-77; WRD 9-1978, f. 12-12-78, ef. 1-1-79,; WRD 13-1986, f. 10-7-86, ef. 11-1-86, Renumbered from 690-063-0035; WRD 7-2001, f. & cert. ef. 11-15-01
214.09 Method of Placement of Concrete or Cement Grout OAR 690-220-0140
b) Concrete or cement grout used as a sealing material in abandonment operations shall be introduced at the bottom of the well or required sealing interval and placed progressively upward to the top of the well. All such sealing materials shall be placed by the use of a grout pipe or by dump bailer in order to avoid segregation or dilution of the sealing materials.
Stat. Auth.: ORS 183, ORS 536, ORS 537 & ORS 540 Stats. Implemented: ORS 183, ORS 536, ORS 537 & ORS 540 Hist.: WRD 3, f. & ef. 2-18-77; WRD 9-1978, f. 12-12-78, ef. 1-1-79,; WRD 13-1986, f. 10-7-86, ef. 11-1-86, Renumbered from 690-063-0040 by WRD; WRD 7-2001, f. & cert. ef. 11-15-01 Construction Requirements-Washington- Only Excepts Please See the WAC Webpage for Full Text
214.010 Notification and Fees. WAC 173-160-141.
The water well operator shall notify the department of their intent to begin well decommissioning procedures at least seventy-two hours before starting work.
a) The notice of intent is submitted on forms provided by the department and must contain the following:
a. Well owner name;
b. Well location; street address; county name, 1/4, 1/4 section, township, and range, and tax parcel number;
c. Proposed use; (if the intended withdrawal requires a water right, the permit or certificate shall be attached to the notice of intent);
d. Approximate start and completion dates;
e. Contractor registration number;
f. Operator/trainee name and license number; and
g. Drilling company name.
b) In an emergency, a public health emergency, or in exceptional instances, the department may allow verbal notification to the appropriate regional office, with a notice of intent and payment of fee submitted within twenty-four hours. An emergency situation may consist of a failing well, or water quality issues which could result in a public health or safety concern.
c) The notice must be accompanied by the following fees which apply to all newly constructed or altered wells:
a. The fee to decommission a water well is fifty dollars.
d) A new notice of intent and fee shall be required on all follow-up construction after the drilling equipment has left the drill site.
e) A refund shall be made on any well that has not been constructed provided, a written request on an approved form is made by the person who paid the fee and is submitted to the department within six months from the date the notice and fee were received by the department.
[Statutory Authority: Chapter 18.104 RCW. WSR 09-01-125 (Order 08-10), § 173-160-151, filed 12/19/08, effective 1/19/09; WSR 06-23-121 (Order 06-08), § 173-160-151, filed 11/21/06, effective 12/22/06. Statutory Authority: Chapter 18.104 RCW and RCW 43.21A.080. WSR 98-08-032 (Order 97-08), § 173-160-151, filed 3/23/98, effective 4/23/98.]
214.11 Well Decommissioning Standards WAC 173-160-381
Any well which is unusable, abandoned, or whose use has been permanently discontinued, or which is in such disrepair that its continued use is impractical or is an environmental, safety or public health hazard shall be decommissioned. The decommissioning procedure (as prescribed by these regulations) must be recorded and reported as required by the department.
a) Cased wells. Remove all liners, debris, accumulated sediments, and obstructions from the well casing, except well screens and packers. All cased water wells, including driven and jetted wells shall be decommissioned in one of the following ways:
a. Perforate the casing from the bottom to within five feet of the land surface and pressure seal the casing.
i. Perforations shall be at least four equidistant cuts per row, and one row per foot. The perforations must be sufficient enough to allow neat cement grout or neat cement, or bentonite slurry to migrate outside the casing and effectively prevent the movement of water.
ii. Apply enough pressure to force the sealing material through the perforations, filling any voids on the outside of the casing.
iii. The casing shall be filled completely with neat cement grout, neat cement, or bentonite slurry. The screen and up to five feet of riser pipe may be filled with unhydrated bentonite. The remainder of the riser pipe must be removed.
iv. The casing may be cut off at a maximum of five feet below land surface; or
v. Withdraw the casing and fill the bore hole with concrete, neat cement grout, neat cement, unhydrated bentonite, or bentonite slurry as the casing is being withdrawn.
b) Uncased wells - Remove all liners, debris, accumulated sediments, and obstructions. Seal uncased wells with concrete, neat cement grout, neat cement, or bentonite.
c) Placement of sealing material.
a. Sealing material placed below the water level shall be piped directly to the point of application or placed by means of a dump bailer or pumped through a tremie tube. As the sealing material is placed, the existing well tile may be encapsulated into the seal material. If concrete, neat cement grout, bentonite, bentonite slurry, or neat cement is used to seal below the static water level in the well, the material shall be placed from the bottom up by methods that avoid segregation or dilution of the material. When used to place concrete, neat cement, neat cement grout, or bentonite slurry the discharge end of the tremie tube shall be submerged in the sealing material to avoid breaking the seal while filling the annular space.
b. All authorized sealing material placed above the static water level or into the dewatered portion of the well may be hand poured above the static water level, provided the material does not dilute or segregate, and result in a seal free of voids.
c. When decommissioning wells that were originally constructed without casing, unhydrated bentonite chips or pellets may be hand placed, provided it forms a continuous seal.
[Statutory Authority: Chapter 18.104 RCW. WSR 09-01-125 (Order 08-10), § 173-160-381, filed 12/19/08, effective 1/19/09; WSR 07-06-004 (Order 06-16), § 173-160-381, filed 2/22/07, effective 3/25/07; WSR 06-23-121 (Order 06-08), § 173-160-381, filed 11/21/06, effective 12/22/06. Statutory Authority: Chapter 18.104 RCW and RCW 43.21A.080. WSR 98-08-032 (Order 97-08), § 173-160-381, filed 3/23/98, effective 4/23/98.]
214.06 Acceptance. Well decommissioning will be evaluated under Subsection 106.02.
Measurement
214.07 Measure the Section 214 items listed in the bid schedule according to Subsection 109.02.
Payment
214.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 203 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.