Q-A_LCNF.doc
DOC document 23 KB Posted
- Solicitation number
- AG-03K0-S-09-0025
About this file
Response to Question
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATCH_3_MASTER_1.pdf | ||
| ATCH_4_Exp_Questionnaire.doc | DOC document | |
| ATCH_2_Forest Service Supp.Specs.doc | DOC document | |
| ATCH_1_Wage_Determination.doc | DOC document | |
| CONSTRUCTION_RFP.doc | DOC document | |
| ATCH_3_MASTER_2pdf.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
September 9, 2009
QUESTIONS AND ANSWERS
AG-03K0-S-09-0025
Deadman-Memorial Way Roads ReConstruction Phase I Lewis & Clark National Forest
1. QUESTION: Are the gates for Deadman Road #837 Government Furnished?
ANSWER: The two closure gates specified on sheet 25 are NOT REQUIRED. It was identified at the time of solicitation issuance that these two gates are not needed. Reference to these gates was deleted from Schedule B and will be deleted in the forthcoming contract in the drawing but time did not permit revising the drawing. Any reference to these two closure gates on Deadman Road in the solicitation should be ignored. This clarification is addressed as a Response to a Question so as not to require amending the solicitation. The proposal closing date and time of 4:00 local time, September 10, 2009 REMAINS UNCHANGED.