REQUEST FOR QUOTATION PAGE OF PAGES
(THIS IS NOT AN ORDER) THIS RFQ IS IS NOT A SMALL BUSINESS SET- ASIDE 1 65
1. REQUEST NO. 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT.DEF. RATING
AG-0398-S-10-0014 June 16, 2010 411539 UNDER BDSA REG. 2
AND/OR DMS REG. 1
5a. ISSUED BY 6. DELIVER BY (Date) East Side Acquisition Team (ESAT) Beaverhead-Deerlodge National Forest 420 Barrett Street Dillon, MT 59725
See date in Schedule
5b. FOR INFORMATION CALL (NO COLLECT CALLS) 7. DELIVERY FOB DESTINATION NAME TELEPHONE NUMBER OTHER (See Schedule)
AREA CODE NUMBER 9. DESTINATION
Lisa Rakich (contracting) Dale White (technical specs)
683-3968 587-6752
a. NAME OF CONSIGNEE
8. TO: Gallatin National Forest Bozeman Ranger District
a. NAME b. COMPANY b. STREET ADDRESS
3710 Fallon Street, Suite C
c. STREET ADDRESS c. CITY
Bozeman
d. CITY e. STATE f. ZIP CODE d. STATE e. ZIP CODE
MT 59718
10. PLEASE FURNISH QUOTATIONS TO THE
ISSUING OFFICE IN BLOCK 5A ON OR
BEFORE CLOSE OF BUSINESS
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5A.
This request does not commit the Government to pay any costs incurred in the preparation of the
July 12, 2010 @ 4:00 PM MST submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT
PRICE
AMOUNT
(a) (b) (c) (d) (e) (f)
001 Greek Creek Campground Water Line and Pump House Replacement on the Bozeman Ranger District
1 JOB xxxxxxxx Please place prices on Schedule B, page 2.
Contractor
DUNS:__________________________
Contractor
TIN:____________________________
Payment Bond is required for award over $30,000.
a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS
12. DISCOUNT FOR PROMPT PAYMENT NUMBER PERCENTAGE
NOTE: Additional provisions and representations are are not attached.
13. NAME AND ADDRESS OF QUOTER 14. SIGNATURE OF PERSON AUTHORIZED TO 15. DATE OF
a. NAME OF QUOTER SIGN QUOTATION QUOTATION
b. STREET ADDRESS 16. SIGNER
a. NAME (Type or print) b. TELEPHONE
c. COUNTY AREA CODE
d. CITY e. STATE f. ZIP CODE c. TITLE (Type or Print) NUMBER
NSN 7540-01-152-8084
Previous edition not usable
18-121 STANDARD FORM 18 (Rev. 6-95) Prescribed by GSA-FAR (48 CFR) 53.215-1(a)
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
Greek Creek Campground Waterline and Pump House Replacement
Bozeman Ranger District Gallatin County, MT
SCHEDULE OF ITEMS
B- 1 - BID SCHEDULE
ITEM
NO. DESCRIPTION Measurem ent
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
01 Mobilization LSQ Lump Sum 1
02120(1) Removal of Structures and Obstructions LSQ Lump Sum 1
02713(1) Install 1-in. PE Water Line,18 in. to 3 ft. bury AQ LF 520
02713(2) Install Rock Sump Drain, complete LSQ Lump Sum 1
02713(3) Install Campground Water Hydrant, complete AQ Each 2
02713(4) Install Host Site Water Connection, complete AQ Each 1
13122(1) Precast Concrete Utility Building LSQ Lump Sum 1
15146(1) Mechanical Work LSQ Lump Sum 1
16440(1) Electrical Work LSQ Lump Sum 1
TOTAL BID PRICE $ _________________
DESIGNATED METHOD OF MEASUREMENT
AQ Actual Quantities LSQ Lump Sum Quantities DQ Design Quantities
B-2 - NOTE:
a. The bidder must bid on all items. Round to the nearest cent.
b. In the event of an error in extending the bid prices, unit prices will govern unless otherwise determined by the Contracting Officer in accordance with applicable regulations.
c. Offers for quantities less than those listed in the numbered items may be rejected.
B-3 - NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed- Price Construction Contracts, shall not be in addition to the contract price. Include payment bond under Item 01 Mobilization.
AG-0398-S-10-0014
Greek Creek Waterline and Pump House Replacement
Bozeman RD
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C-1 - PROJECT DESCRIPTION AND LOCATION
(a) Description of Work. Furnish all labor, materials, equipment, supervision, and transportation necessary to complete the Greek Creek Campground Water Line and Pump House Replacement work as shown and specified.
The major items of work include the following:
1. Remove and dispose of existing concrete pump control vault.
2. Remove and dispose of three existing water hydrants.
3. Salvage meter base, pump control box, and load center from existing pump control vault and re-install in new pump house.
4. Install a new branch circuit from the circuit breaker load center to well head.
5. Furnish and install new concrete pump house and associated electrical and mechanical work in accordance with the drawings and specifications.
6. Install a new pressure tank, new pressure switch/gauge, new pressure relief valve, new vacuum breaker, new sampling tap, and associated piping.
7. Install approximately 520 linear feet of 1-inch HDPE water line, and associated fittings, and couplings.
8. Install two (2) accessible water hydrants with concrete pads, and install one (1) host site water hydrant.
9. Install 3-inch diameter steel pipe sleeve at roadway crossings. Pipe sleeves shall be “pushed” under roadway crossings.
10. Work required at well include installing a new pit-less adapter, new 1-1/4-inch galvanized steel drop pipe, and a new vented well cap.
11. Install an isolation valve/box at new water hydrants.
12. Construct a 6 ft. x 6 ft. x 3 ft. rock sump, and install a curb stop and curb box.
b) Project Location
Project work is located at Greek Creek Campground, Bozeman Ranger District, Gallatin National Forest, Gallatin County, Montana. See site location shown on the project drawing cover sheet.
c) Pre-Bid Tour
There will not be a pre-bid tour but potential bidders are encouraged to visit the project site on their own. Interested contractors with project questions may contact Dale White at the Gallatin Supervisors Office at (406) 587-6752.
C-2 GENERAL SPECIFICATIONS
a) Existing Facilities. In addition to the requirements of the Use of Premises Clause, AGAR 452.236- 70, all existing facilities structures damaged by the Contractor shall be replaced or repaired by the Contractor at no additional cost to the Government. This includes any facilities inside or outside the project limits, including along any access routes.
Do not cut, trim, or damage vegetation except with specific Contracting Officers Representative (COR) approval. Limit all construction activities and ground disturbance, including storage and stockpiling, to areas designated by the COR.
b) Pollution and Erosion Control. During all operations under this contract, the Contractor shall exercise reasonable measures to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and solid or liquid wastes, from the Contractor's operations, including camps, parking areas, and equipment maintenance areas shall be stored, collected, and disposed of off of government land in a legal manner. Refuse shall be disposed of in State-approved landfills unless otherwise approved by the Contracting Officer's Representative
(COR).
c) Public Safety and Access. Safety on the project site shall be the sole responsibility of the
Contractor. The Contractor shall maintain warning signs and barricades to safeguard the public.
Public access to at least one loop on the river side of the campground shall be maintained at all times. Adequate signs, barricades, cones, and other methods or devices shall be utilized in accordance with the MUTCD.
d) Traffic Control. Traffic control shall be the sole responsibility of Contractor. Adequate signs, barricades, cones, and other methods or devices shall be utilized in accordance with the MUTCD.
e) Permits. The government will obtain an Encroachment Permit for the installation of the waterline under the highway embankment. The Contactor shall comply with all terms and conditions of the Encroachment Permit.
f) Storage and Stockpiling. The Contractor shall confine storage of equipment, materials, and vehicles to within the limits delineated by the Contracting Officers Representative. Materials subject to damage from the weather shall be adequately protected by the Contractor.
g) Worksite Cleanliness and Final Cleanup. Maintain the project work areas in a clean and orderly condition throughout the progress of work under this contract. Upon completion of the work, clean entire work area to meet COR-approval.
h) Equipment Specifications. Equipment and tools shall be in good mechanical and operating condition, fully capable of performing all phases of the specified work.
i) Use of Government Facilities while Conducting Work.
1. Sanitary Facilities: Campground toilets may be used by the Contractor.
2. Electrical Power: Electrical power is available at the site and may be used by the Contractor for construction purposes while construction is underway.
3. Potable Water: The potable water system to be worked on under this contract is the only potable water system at the site. The Contractor may use the system as a water source while construction is underway.
4. Camping: No camping on Forest Service lands except by written approval of the Bozeman District
Ranger.
j) Locating and Protecting Utilities. The Contractor shall contact Montana One Call at (800) 424- 5555 and pay any fees required for locating and marking utility-owned and government-owned underground electrical lines, telephone lines, plastic water lines with tracer conductors, and fiber optic lines, and any other underground utilities in the construction area a minimum of 2 business days prior to any excavation, trenching, or other ground disturbing activity at the site.
NOTE: ELM Locating & Utility Services of Missoula, MT is the current contractor for Montana One Call. They can be contacted for additional fees for private locates at (406) 728-9343.
k) Disposal Site. Unsuitable or excess excavated material and vegetation will be disposed of in areas approved by the COR. All other project waste materials shall be removed from the project site and disposed of at an approved sanitary landfill or other acceptable disposal site. No burning of construction materials or debris will be allowed at the project site.
l) Submittals.
1. It shall be the Contractor's responsibility to submit all items with such promptness as to cause no delay in the work. Approvals must be obtained before starting work which involves the item. The Contractor shall allow 10 days for processing of submittals by the Government.
2. Manufacturer's Literature: Submit one copy to the COR for approval for all items and materials furnished for use on the project.
C-3 MEASUREMENT AND PAYMENT
One of the following methods of measurement for determining final payment is DESIGNATED IN THE SCHEDULE OF ITEMS for each PAY ITEM.
A. Designed Quantities (DQ). These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and presentation in the contract. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under any of the following conditions:
(1) Changes in the work authorized by the CO.
(2) A determination by the CO that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.
(3) A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.
B. Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.
C. Actual Quantities (AQ). These quantities are determined from measurements of completed work.
Payment will be by units defined and determined according to measure. Unless otherwise specified, the meanings of the following terms are as follows:
A. Each. One entire unit, which may consist of one or more parts. The quantity is the actual number of units completed and accepted.
B. Lump Sum (LS). Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item.
B. Lineal Foot (LF). The measurement taken along the centerline of the water line.
C-4 TECHNICAL SPECIFICATIONS
SECTION 02120
REMOVAL OF STRUCTURES & OBSTRUCTIONS
PART 1 - GENERAL
1.1 DESCRIPTION OF WORK
This section includes removing and disposing of existing concrete pump control vault, water hydrants, utilities, and other obstructions, and salvaging items identified in the specifications.
1.2 RELATED WORK IN OTHER SECTIONS
Water System Mechanical Work - Section 15146
PART 2 - PRODUCTS
Not Used.
PART 3 - EXECUTION
3.1 PROTECTION
A. Locate, identify, and protect existing utilities from damage.
B. Protect benchmarks and existing structures from damage or displacement.
3.2 VEGETATION REMOVAL
Remove only brush and trees that have been pre-approved for removal by the CO. Dispose of brush and slash on site at locations designated by the CO. Saw trees into 18 inch long rounds and place rounds were designated by the CO.
3.3 EXISTING CONCRETE PUMP CONTROL VAULT
Verify electric power disconnect by power company in accordance with Section 15146. Salvage the existing submersible pump controls; meter base, and circuit breaker load center from the existing pump control vault. Salvaged materials to be re-installed in new pump house building.
Remove the existing concrete pump control vault in its entirety and dispose of it off Forest Service lands at an approved sanitary landfill, or other acceptable disposal site.
3.4 EXISTING WATER HYDRANTS
Remove three existing water hydrants in their entirety and dispose of them off Forest Service lands at an approved sanitary landfill, or other acceptable disposal site.
3.5 ABANDONING UNDERGROUND UTILITIES
Cut existing underground lines to be abandoned a minimum 1 foot below the surrounding ground surface.
PART 4 – MEASUREMENT AND PAYMENT
4.1 GENERAL
The method of measurement will be as designated in the SCHEDULE OF ITEMS.
The accepted quantities will be paid for at the contract unit price for each Pay Item shown below and in the SCHEDULE OF ITEMS.
For each pay item, payment will be for all labor, equipment, transportation, supervision, operating supplies, materials, and incidentals necessary to complete the pay item work as shown on the Plans and specified in this section and referenced specification sections.
Pay Item Description Pay Unit
02120(1) REMOVAL OF STRUCTURES & OBSTRUCTIONS Lump Sum
Measurement and payment will be for the removal and disposal of existing concrete pump control vault, and three water hydrants, including excavation, backfill material, backfilling, and other required work, complete.
END OF SECTION
SECTION 02221
TRENCHING, BACKFILLING, AND COMPACTING FOR UNDERGROUND UTILITIES
PART I – GENERAL
1.1 SCOPE
This section covers trenching, clearing and grubbing, excavation, backfilling, and compaction for underground utilities including water and electrical lines, concrete pump house, concrete pads, and water hydrants.
A. Water Lines and Appurtenances – Section 02713
B. Water System Mechanical Work – Section 15146
C. Electrical Work - Section 16440
1.3 CODES AND REGULATIONS
All work shall comply with the rules and regulations of Federal, State, and local agencies having jurisdiction.
1.4 REFERENCE POINTS
Maintain all benchmarks, monuments, and other reference points. Any benchmarks, monuments and other reference points that are disturbed or destroyed during construction shall be replaced as directed by the CO.
PART II - PRODUCTS
2.1 DETECTABLE BURIED WARNING TAPE
Detectable buried warning tape is to have a minimum 6-inch width and 5 mil thickness with a solid aluminum core running the full length and width of the tape enclosed in a color coded inert plastic jacket, impervious to alkalis, chemical reagents and solvents in the soil. The tape shall be green color for sewer lines and shall be imprinted with “CAUTION: BURIED WATER LINE BELOW”, “CAUTION: BURIED ELECTRICAL LINE BELOW”, or similar message as appropriate at maximum intervals of 36 inches. Install separate warning tape over each utility line when more than one utility line is buried in the same trench. “Detectatape” by Allen Systems or approved equal.
2.2 TRACER WIRE
Insulated number 18 AWG copper wire, green insulation.
2.3 PIPE OR CONDUIT BEDDING MATERIALS
A. Type 1 Pipe Bedding: Shall be select excavated material. Shall be sand, sandy gravel, or fine gravel, free from rubbish, litter, organic matter, and rock over 1-inch in maximum dimension. Where trench excavation encounters wet or unstable material, Type 1 Pipe Bedding must be free draining and non-plastic.
B. Type 2 Pipe Bedding: Type 2 Pipe Bedding shall be used as directed by the CO to replace unsuitable material encountered in the trench bottom. Place Type 2 Pipe Bedding from the bottom of the Type 1 Pipe Bedding material to the depth required to adequately support the pipe. The Type 2 Bedding consists of imported granular material meeting the following gradation:
Sieve Opening % Passing 1 Inch 100 No. 4 0-25 No. 8 0-10
Note: If Type 2 bedding material is required, the Contractor shall notify the CO prior to importing material. An equitable adjustment to the contract amount will be negotiated to pay for importing, placing, and compacting of Type 2 bedding material.
2.4 BACKFILL MATERIAL
Materials from excavations: Backfill material must be free of cinders, ash, refuse, organic or frozen material, rocks larger than 6-inches in maximum dimension, or other deleterious materials.
PART III – EXECUTION
3.1 MARKING OF UNDERGROUND UTILITY LINES
A. Install warning tape 6-8 inches below finish grade in all trenches containing pipe lines or electrical conduit.
B. Install continuously along total length of trench.
C. Overlap marking tape at least 12 inches at splices and provide positive contact between metalized foil cores.
D. Install electrically continuous copper tracer wire in the trench with plastic water piping. Tracer wire shall be visible in all valve boxes and terminate above ground or in valve boxes at each end.
Loop 3 feet of tracer wire as slack inside valve boxes. When it is necessary to splice tracer wire, remove insulation and twist together for a minimum of 6 inches. Wrap splice with several layers of electrical tape for several inches on both sides of splice. Splices made in valve boxes shall not be taped.
3.2 CLEARING AND GRUBBING
A. The Contractor and CO will consult on shifting the water line alignment as needed to minimize the number of trees and brush to be removed for installation of the water lines. Final location of the water lines will be subject to approval by the CO.
B. Clearing limit shall not exceed 10 feet on both sides of center line of water and lines.
3.3 EXCAVATION
A. OSHA Trenching Standards: Meet current OSHA Safety and Health Standards for all excavation, trenching, shoring, and related work under this contract. Trench boxes, trench shields, sloping or benching systems, or suitable shoring meeting trench excavation standards of “Occupational Safety and Health Standards for the Construction Industry” (29 CFR Part 1926, Subpart P-Excavations) shall be used for trenches over 5 feet deep.
B. Water in Excavations: Prevent surface water from flowing into excavations. If water is encountered during trench excavation, provide adequate pumping equipment and piping to keep trench free from water. Coordinate with CO to dispose of water by methods that will not impact water courses.
C. Salvage topsoil to a minimum depth of 6 inches and windrow parallel to the trench. Do not mix other excavated material with subsoil.
D. Excavate only when materials are available on site for installation and required testing.
E. Material to be excavated for installation of utilities is unclassified.
F. Excavate the depth as required for the invert grade as specified in the contract documents, allowing space for specified bedding layer. If rocks over 1-inch in maximum dimension are encountered in the lower 12 inches of trench sidewall or at the bottom of the trench, excavate at least 4 inches below the bottom of the pipe for backfilling with Type 1 Pipe Bedding.
G. Electrical Conduit: Excavate to provide minimum cover of 24 inches over top of electrical conduit except where buried deeper in the same trench with other utility lines. No excavation is authorized below the indicated depths unless approved by the CO to obtain suitable bearing materials or to remove objectionable debris.
H. Water Lines: Excavate to provide minimum cover of 18 inches at hydrants and minimum of 3 feet over top of new HDPE water line unless otherwise shown on the drawings.
I. Complete excavations to the lines shown on the drawings.
3.4 OVER-EXCAVATION
Unauthorized over-excavation beyond limits indicated on the drawings shall be backfilled with Type 2 Bedding Material. Backfill material and compaction of unauthorized over-excavation shall be completed at the Contractor's expense.
3.5 PIPE AND CONDUIT BEDDING
A minimum of 4 inches of pipe bedding material shall be placed below piping or conduit when the trench is sub-excavated due to rocks larger than 1-inch in maximum dimension. If bedrock or hardpan is encountered in excavation, a minimum of 4 inches of pipe bedding material shall be placed on the bottom of the trench as a cushion layer for piping or conduit.
3.6 BACKFILLING OF PIPING AND CONDUIT
A. Installation of piping and conduit shall be approved by the CO prior to backfilling.
B. The pipe or conduit shall be uniformly and continuously supported over its entire length on firm stable material.
C. Type 1 bedding material shall be placed to a loose depth of 6 inches above the top of the pipe or conduit and hand tamped.
D. Backfill remaining depth of trench with trench backfill material, covered by a layer of salvaged topsoil minimum 4 inches thick. Mound material neatly over the trench.
3.7 COMPACTION OF TRENCHES
A. Bottom of trench and bedding shall be hand-tamped. Compaction of remaining backfill will not be required unless otherwise specified. Cover subsoil with a layer of salvaged topsoil minimum 4 inches thick. Mound material neatly over the trench.
3.8 ROADWAY CROSSINGS
A. All roadway crossings, including the crossing of Highway 191, shall require a pipe sleeve jacked or bored under roadway. Trenching at roadway crossings is prohibited.
B. Steel pipe for sleeve shall conform to ASTM A-120 and shall have a minimum interior diameter of 3 inches. The Contractor shall cut sections and join sections with a continuous butt weld to provide the necessary overall length as part of the coring and pushing operations.
C. The installation shall be carried out by jacking or boring a steel pipe through the highway embankment without disturbing the existing pavement or embankment structure in a manner approved by the C.O. Boring or jacking shall be accomplished without jetting, sluicing, or wet-boring.
D. Bored installations shall have a bored-hole diameter essentially the same as the outside diameter of the sleeve pipe to be installed.
E. The steel pipe sleeve shall extend 10 feet beyond the toe of the future highway embankment, as staked by the C.O. The invert elevations shall be as shown on the drawings. Care shall be taken to ensure that pipe installed by the boring and jacking method will be at the proper alignment and grade.
F. Adequate sheeting, shoring, and bracing for embankments, operating pits, and other appurtenances shall be placed and maintained while work is under way to ensure that work proceeds safely and expeditiously. Operating pits shall be of minimal size to accomplish the work safely and efficiently. Any solidification of embankments, boring headings, or sides shall be the Contractor's responsibility and shall be done at his own expense. The Contractor shall maintain and operate pumps, well points, and drainage system equipment to keep work de-watered at all times.
G. The Contractor shall be responsible for correcting and repairing, at his own expense, any roadway slides or failures that occur as a result of activities associated with the work.
3.9 HAND TAMPING
Hand tamping will be defined as one pass over the entire trench with the following or equivalent approved by the CO.
1. Hand tamper weighing minimum of 8 pounds.
2. Maximum area of tamping foot - 40 square inches.
3. Minimum gravity free-fall of tamper - 12 inches.
3.10 MOISTURE CONTENT
Maintain adequate moisture content in backfill and bedding material to ensure optimum densities of compacted material.
3.11 SURFACE GRADING
After completion of backfilling, fine grade with hand tools or equipment as required to provide a smooth transition with adjacent undisturbed material.
3.12 DISPOSAL OF EXCESS OR UNSUITABLE EXCAVATION
Excess or unsuitable excavated material shall be disposed of in accordance with Section 02200.
3.13 MEASUREMENT AND PAYMENT
Work performed under this Section is incidental to work performed under Sections 02713, 15146, and 16440. No separate payment will be made for work under this Section.
SECTION 02713
WATER LINES AND APPURTENANCES
PART I - GENERAL
This section covers the construction of buried potable water lines and related appurtenances under this contract. The work consists of furnishing and installing pipe and fittings, testing, cleaning, and disinfection of water lines and other related work.
A. Trenching, Backfilling, and Compacting for Underground Utilities - Section 02221.
1.3 SUBMITTALS
A. It shall be the Contractor’s responsibility to submit all items with such promptness as to cause no delay in the work. Approvals must be obtained before starting work which involves the item.
Contractor shall allow 10 business days for processing of submittals by the Government.
B. Manufacturer’s Literature: Submit 3 copies to the CO for approval on the items required herein.
Literature shall be marked or otherwise designated to indicate the exact model, size, etc., the Contractor proposes to use. Information shall be adequate to determine compliance with the specifications without additional research by the CO. One copy of approved submittals will be returned to Contractor.
C. Provide manufacturer’s literature on the following:
1. Polyethylene (PE) pipe.
2. Curb Stop and Curb Box.
3. Bronze Compression Coupling.
4. Ball Valve.
5. Plastic Valve Box.
6. Plastic Lumber.
2.1 POLYETHYLENE (PE) PIPE
PE 3408, SIDR 7, 200 psi, NSF listed, equal to Eagle 3408 by Eagle Plastics, Inc. shall be PLASTIC- PIPE size. Provide sizes as shown on the drawings.
2.2 FITTINGS FOR PE PIPE
All fittings for joining PE pipe to PE pipe or for joining PE pipe to galvanized steel pipe or copper pipe shall be cast bronze compression fittings, Pack Joint Couplings by Ford or equal. Insert stiffeners are required with pack joint couplings. Verify that fittings are for 200 psi pipe. THE USE OF
INSERT FITTINGS WITH HOSE CLAMPS WILL NOT BE PERMITTED.
Fusion butt welding is another acceptable method for joining PE pipe to PE pipe.
2.3 GALVANIZED STEEL PIPE AND FITTINGS
Steel pipe and fittings shall be galvanized Schedule 40.
2.4 BALL VALVE
Bronze body, bronze or chrome-plated bronze ball, BUNA-N or TEFLON seat, lever handle. Rated for minimum non-shock working pressure of 200 psi WOG for cold water.
2.5 CURB STOP QUARTER TURN CHECK
Curb stop conforming to AWWA C800, quarter turn check and Minneapolis top thread, stop feature, pack joint for PE pipe or iron pipe threaded as necessary to fit the installation, size as shown on the drawings. Use Mueller H-15156 or Ford B-66, or approved equal.
2.6 CURB BOX
Cast iron extension type curb box, Minneapolis pattern, cast iron lid with brass pentagon plug, compatible with curb stop top thread and bury depth. Stationary rod extending to within 3 to 15 inches of finished grade. Provide an operating key per box to operate curb stop with the stationary rod. Use Mueller H-10302, or approved equal.
2.7 VACUUM RELIEF VALVE FOR HOST SITE WATER, WELL, AND PUMP HOUSE
Vacuum relief valve automatically vents closed system if a vacuum occurs. All brass body with polypropylene protective cap. Rated for maximum water working pressure of 200 psi, opens at less than 1/2 inch vacuum with a venting capacity of 15 cubic feet per minute. Male NPT inlet connection, 3/4 inch size.
Model N36-M1 vacuum relief valve by Watts Regulator Company or approved equal.
2.8 BACKFLOW PREVENTER FOR HOST SITE WATER CONNECTION
Dual check valve backflow preventer for low hazard applications. Cast bronze body, stainless steel spring, union on inlet end with O-ring union seal, Female NPT inlet and outlet, 3/4 inch size. Rated for maximum working pressure of 150 psi. Maximum pressure loss through backflow preventer at flow rate of 20 gallons per minute shall not exceed 7 psig.
Series 7 residential dual check valve backflow preventer with specified options by Watts Regulator Company or approved equal.
2.9 HOSE BIBB FOR HOST SITE WATER CONNECTION
Cast brass spigots approved by the CO.
2.10 PLASTIC VALVE BOX
Rigid high density polyethylene utility box, equal to Model No. 1320 (Jumbo) by Applied Engineering Products, Chino, CA (909) 393-9800, www.aepvalvebox.com or approved equal. Box color: Green. Provide bolt-down solid cover, high density polyethylene. Provide 6-inch box extensions as required.
2.11 SELF-CLOSING CAMPGROUND FAUCET
Self-closing, plain end, lead-free bib faucet with rough brass finish and a special extended lever handle which is locked to valve; requiring less than 3.5 pounds to activiate. One-half inch male NPT inlet.
Model # 6252EHLF by Haws Corporation, www.hawsco.com or approved equal.
2.12 PLASTIC LUMBER MATERIAL (Water Hydrant Posts and Grates)
Plastic lumber material shall be made of high density polyethylene plastic with colorants and ultraviolet stabilizers added to provide longevity in outside applications. Lumber shall be solid with pigment throughout to provide consistent color and uniformity even after cutting. Colors of lumber materials shall be the manufacturer’s total color range. Proposed color selection and texture will be made by the CO.
Bedford Technology, LLC, www.plasticboards.com or approved equal.
PART III - EXECUTION
3.1 REMOVAL AND DISPOSAL OF EXISTING INSTALLATION
Existing Water Lines: Existing buried water lines that are exposed while trenching for installation of new water lines shall be removed and disposed of at an approved sanitary landfill, or other acceptable disposal site Removal of existing concrete pump control vault is covered under Section 02120.
3.2 INSTALLATION OF PIPING AND FITTINGS
A. Installation of water piping and valves shall be in accordance with the Uniform Plumbing Code and other applicable laws and regulations.
http://www.aepvalvebox.com/� http://www.hawsco.com/� http://www.plasticboards.com/�
B. All trenching, backfilling, and other work incidental to water line construction, including excavation for valves, fittings, hydrants, or other pipe line structures shall be done in accordance with Section 02221 – Trenching, Backfilling, and Compacting for Underground Utilities.
C. Drainage: It is critical that all piping be installed so it will drain by gravity to rock sump. Verify drainage with CO prior to excavation. Minimum pipe line slope to drain shall be 0.35 percent.
Piping shall be installed at uniform slopes to drain points.
D. Pipe sizes shall be as shown on the drawings. Valves and unions shall be line-size.
E. Kinking of pipe will not be allowed. Curves or bends shall be made within the limits specified in the installation specifications provided by the pipe manufacturer. Bends exceeding these limits shall be made with standard fitting(s) meeting the requirements of Item 2.2.
F. Snake PE pipe in trench to allow for expansion and contraction.
G. Mechanical Compression Joints for HDPE Pipe
1. Provide mechanical joints consisting of, at a minimum, a threaded compression nut or a follower and bolt arrangement, and elastomer seal ring, and a stiffener.
2. Insert pipe stiffeners to provide support under the seal ring and gripping ring. Assure stiffener is long enough to prevent collapse of the pipe.
3. Compress the seals by tightening the threaded compression nuts or follower and bolt arrangements. Assure seals are pressure-tight.
4. Each joint must be inspected by the Contractor personnel.
H. Thermal Fusing HDPE Pipe
1. Clean pipe ends thoroughly with cotton cloth. Assure no HDPE cuttings remain in the pipe. Face the pipe ends to establish clean, parallel mating surfaces. Continue facing until a minimal distance exists between the fixed and movable jaws. Provide a perfectly square face, perpendicular to the pipe centerline on each pipe end and with no detectable gap.
2. Align and round the pipe profiles with each other to minimize mismatch (high-low) of the pipe walls. Clamping jaws must be loosened during fusion. Clamp the pipe as close to the joint areas as possible to ensure proper pipe alignment.
3. Use heating tool with internal thermometer, assuring heater faces are clean, oil-free, and coat with a nonstick coating as recommended by the manufacturer. Periodically verify the proper surface temperature using a pyrometer of surface temperature measuring device.
Melt the pipe interfaces until the proper bead size is formed per manufacturer’s recommended temperature and bead size, without applying pressure.
4. Join the pipe ends rapidly, but carefully, with sufficient pressure to mix the pipe materials and form a homogenous joint. Follow manufacturer’s recommendations for internal pressure or bead size of molten material.
5. Hold molten joint immobile under pressure as indicated until cooled adequately to develop strength. Use cooling times established by the pipe manufacturer. Do not apply water, wet clothes, or similar to shorten cool time.
6. Each fused joint must have a complete double roll-back bead and be inspected by
Contractor personnel.
3.3 PRECAUTIONS
A. Load and unload pipe, fittings, valves, and accessories carefully to prevent damage. Do not permit pipe handled on skidways to skid or roll against pipe already on the ground. Do not drop or dump material into the trench.
B Preventive Measures During Construction: Precautions shall be taken to protect pipe interiors from contamination with dirt, dust, organic debris, oils, fuels, paints, or any other foreign material when in stockpile at the site and during installation.
C. Care shall be taken to protect pipe interiors from contamination after each day's work by plugging or otherwise preventing the entrance of dirt or mud.
D. Maintain a dry trench until pipe ends are sealed. Do not allow any trench water to enter the pipe at any time.
3.4 CURB STOP AND CURB BOX
Install curb box plumb on curb stop as shown on the drawings. Set the curb box top approximately 1-inch above natural grade. Hand place several shovels full of topsoil material flush with the cover and blend in with the natural grade.
3.5 CAMPGROUND WATER HYDRANT WITH CONCRETE PAD
Construct as shown on the drawings
3.6 HOST SITE WATER CONNECTION
Construct as shown on the drawings.
3.7 TESTING
A. Notify CO at least 5 business days prior to performing testing.
B. Test required on all piping installed under this contract. All equipment required shall be provided by the Contractor.
C. After the pipe is laid, the joints completed, and the trench partially backfilled, leaving the joints exposed for inspection, the newly laid piping or any valve section of piping shall be subjected to a hydrostatic pressure test as listed below.
D. Expel all air from line before applying test pressure.
E. Test pressure 75 psi with no reduction in pressure in 10 minutes and no visible leaks.
F. Test must be observed by CO.
G. Repair all leaks by methods approved by CO. Re-test until a successful test is achieved.
3.7 DISINFECTION
A. Notify CO at least 5 business days prior to performing disinfection.
B. After completion of piping/plumbing work, the entire distribution system shall be disinfected. All materials and equipment required for disinfection shall be provided by the Contractor.
C. Coordination: Coordinate with CO prior to beginning chlorination procedure. Extreme caution must be taken to ensure that chlorinated water does not reach surface water.
D. The water lines shall be flushed, disinfected, and flushed again with potable water. Each flushing and disinfection step must be observed and approved by the CO.
E. Pipes shall be flushed until discharge is clear.
F. After initial flushing, a sodium hypochlorite solution shall be injected at locations described below to obtain a chlorine concentration of approximately 50 mg/l throughout the distribution system. Test all outlets and ends of pipe works to ensure chlorine solution has reached the entire distribution system.
G. Retain chlorine solution in the system for a minimum of 4 hours. Test for chlorine residual at representative number of outlets. If free chlorine residual is below 10 mg/l, repeat disinfection cycle. After disinfection, flush treated distribution system until the chlorine residual has been reduced to less than 1 mg/l.
H. Disposing of Chlorinated Water: Dispose of chlorinated water by methods that will ensure chlorinated water does not enter surface water courses or cause erosion.
3.8 MEASUREMENT AND PAYMENT
A. The method of measurement will be as designated in the SCHEDULE OF ITEMS.
B. The accepted quantities will be paid for at the contract unit price for each Pay Item shown below and in the SCHEDULE OF ITEMS.
Payment will be made under:
02713(1) Install 1-Inch PE Water Line, Lin. Ft.
18 Inch to 3 Feet bury
The actual linear feet of 1-inch PE water line installed will be paid for under this Pay Item.
Measurement will be made through the centerline of pipe and fittings. Payment will be for excavation, bedding and backfill material, backfilling, compaction, and water line and fittings installed, installation of 3-inch galvanized steel pipe sleeve at road crossings, materials, testing and disinfection, and miscellaneous other required work, complete.
02713(2) Install Rock Sump Drain Lump Sum
Measurement and payment will be made for the completed installation of a rock sump drain and a 1-inch curb stop and curb box, including washed rock, geotextile fabric, galvanized steel pipe and fittings, excavation, bedding and backfill material, backfilling, compaction, and other required work and materials, complete.
02713(3) Install Campground Water Hydrant Ea.
Measurement and payment will be made for the completed installation of water hydrant including concrete pad, plastic lumber for post and grate, self-closing faucet, irrigation box, ball valve, piping and fittings, excavation, compaction, backfilling, and connection to water lines, complete.
02713(4) Install Host Site Water Connection Ea
Measurement and payment will be made for the completed installation of Host Site Water Connection including excavation, backfill material, backfilling, compaction, plastic lumber post, piping and fittings, backflow preventers, vacuum breaker, hose bibbs, fittings, and the 3/4 inch galvanized steel water line connection to valve box and main water line, complete.
SECTION 13122
PRECAST CONCRETE UTILITY BUILDING
PART 1 – GENERAL
This specification covers the Placing of the precast pump house building as produced by Missoula Concrete Construction (MCC). Full building specifications including roof, wall and floor construction specifications are included here by reference and may be viewed at www.missoulaconcrete.com Utility Building Specifications.
PART 2 – PRODUCTS
Precast concrete Utility Building per Missoula Concrete Construction (MCC) standard specifications or approved equal. Building design shown in drawings is based on standard materials and methods of the precast manufacturer. Colors of building components shall be as designated by the CO.
Available from:
Missoula Concrete Construction 8012 Deschamps Lane Missoula, MT 59808 406 549 9682
PART 3 – EXECUTION
3.1 INSTALLATION
A. Scope of Work
1. Work specified under this Section includes necessary clearing, grading, excavation, backfill and placement of precast utility building.
B. Materials
1. Bedding material to be sand or 3/8-inch minus crushed or screened aggregate.
C. Location and Access to the Site. Locate the Utility Building where staked by the CO.
1. The area must be free of overhead or underground obstructions.
2. Care must be taken to not place excavated material in the area where the crane must sit.
3. Verify that bridges/culverts enroute to the site are rated for HS-20 loading.
4. Deliveries may be delayed if road conditions are hazardous or unsuitable for normal trucks and trailers.
5. Trucks must be able to reach the site under their own power.
http://www.missoulaconcrete.com/�
D. Excavation and Elevation
1. Comply with all applicable OSHA Standards for excavation.
2. Pipes under building should be installed with stub outs and, backfilled and compacted before completing subgrade grading.
3. Finish floor elevation will be at a minimum 6 inches above natural grade. The Forest
Service will specify a finish floor elevation for the floor slab. The contractor will install building with the floor elevation within ±0.05 feet of the specified floor elevation.
E. Bedding and Compaction
1. Buildings Placed Upon Compacted Gravel Pad.
a. Care must be taken to allow slack in electrical wire entries and swing joints or flexible pipe in plumbing entries as the building will be subject to several inches of up and down movement during frost cycles.
b. Oversize penetrations in floor slab for pipe or electrical entries. Place sand or screened gravel in the extra space, DO NOT GROUT.
c. Backfill exterior of building up to finished floor elevation allowing drainage away from the structure.
1. Remove grass and vegetation from the building pad area. Excavate pad area as required to level the subgrade. Compact the natural ground after stripping and excavation with a minimum of 3 passes with a plate-type mechanical compactor or approved equivalent.
2. Install sand or aggregate bedding material for leveling course. Compact leveling course with one pass with a plate-type mechanical tamper or approved equivalent. Grade leveling course so there will be no high spots in the middle of the vault bottom. Compact with a second pass with an approved compactor.
F. Finish Grading
1. Intended final grade is flush with the top of the front slab. Allow for placement of topsoil to reach that grade. Grade backfill away from structure at maximum slope of 5 percent unless otherwise approved by the CO.
2. Spread stockpiled topsoil as final layer after rough grading is completed. Areas disturbed by excavation, backfilling and stockpiling of excavated materials will be handed raked to remove exposed rocks over 1-inch in maximum dimension. Oversized rocks removed from the surface shall be disposed of in a designated area as directed by the CO.
3.2 MEASUREMENT AND PAYMENT
B. The accepted quantities will be paid for at the contract unit price for the Pay Items shown below and in the SCHEDULE OF ITEMS.
13122(1) Precast Concrete Utility Building Lump Sum
Measurement will be made for all labor, materials, equipment, supervision, and transportation to furnish and install a new precast concrete pump house completed in accordance with the drawings and specifications. Payment will also include site prep, excavation, and crushed gravel pad.
SECTION 15146
WATER SYSTEM MECHANICAL WORK
PART I - GENERAL
This section covers mechanical work under this contract. The work includes installation of a new pressure tank, new drop pipe, new pitless adapter, new submersible pump conductor wire, new safety rope, new well cap, and re-installation of salvaged items; meter base, load center, and pump control box, and all new plumbing in new pump house as specified on the drawings, complete.
A. Trenching Backfilling, and Compacting for Underground Utilities– Section 02221.
B. Water Lines and Appurtenances – Section 02713.
C. Electrical Work – Section 16440.
1.3 CODES
All work shall be in accordance with all applicable codes and regulations.
1.4 SUBMITTALS
Submit to CO for approval two copies of manufacturer’s literature on the following:
1. Vented Well Cap.
2. Pitless Adapter.
3. Submersible Pump Cable.
4. Pressure Relief Valve.
5. Vacuum Relief Valve.
6. Ball Valves.
7. Pipe Supports.
8. Sampling Faucet.
9. Pressure Tank.
2.1 PIPE SUPPORTS
Pipe saddle supports, adjustable with cast iron saddle, locknut nipple and cast iron reducer, galvanized finish. Complies with MSS-SP-69 (Type 38). Figure 264 by Anvil International, Inc. or approved equal.
2.2 PRESSURE TANK
A. Pressure Tank: Sealed diaphragm type, free-standing model, rated for maximum working pressure of 100 psi.
B. Pre-charged with air to 28 psi for 30–50 psi on-off cycle of submersible well pump, minimum drawdown of 11.6 gallons of water per on-off cycle.
Well-X-Trol Model WX-205 or approved equal.
2.3 PRESSURE GAUGE
2-inch face diameter, 0-100 psi, steel body, 1/4 inch NPT.
2.4 HOSE BIBB
Bronze body, 3/4-inch threaded inlet, 3/4-inch standard male hose threaded outlet.
2.5 SAMPLING FAUCET
1/2-inch threaded inlet, open and close manually, brass or chrome finish, smooth outlet.
2.6 BALL VALVE
Bronze body, bronze or chrome-plated bronze ball, BUNA-N or TEFLON seat, lever handle.
Threaded or solder-joint ends, rated for 200 psi WOG.
2.7 PRESSURE SWITCH
Pressure Switch: Model FSG-2, Square D or approved equal. Standard on-off setting of 30-50 psi.
2.8 VACUUM RELIEF VALVE
Vacuum relief valve automatically vents closed system if a vacuum occurs. 3/4 inch size male NPT inlet connection, all brass body with polypropylene protective cap, rated for maximum water working pressure of 200 psi, opens at less than 1/2 inch vacuum with a minimum venting capacity of 15 cubic feet of air per minute.
Model N36-M1 vacuum relief valve by Watts Regulator Company or approved equal.
2.9 PRESSURE RELIEF VALVE
Brass or bronze construction, 1 inch size, adjustable relief pressure gauge of 10-200 psi. Adjust relief pressure to 75 psi.
Campbell part number RV-4 or approved equal.
2.10 GALVANIZED STEEL PIPE AND FITTINGS
Steel pipe and fittings shall be galvanized Schedule 40.
2.11 ELECTRICAL RACEWAY AND FITTINGS
Flexible Metal Conduit - Galvanized steel, UL 1. Fittings UL 514.
2.12 WELLHEAD
A. Well Cap: Painted cast iron watertight well cap, 1 inch NPT conduit connection, 9/16 inch vent screen and 1-inch NPT plugged tap in cover. Two piece with inner gasket that compresses against outside of well casing when bolts are tightened. Campbell part number WTC6M or equal for 6- 5/8 inch outside diameter (OD) well casing. Verify existing casing OD before ordering.
B. Pitless Adapter: Cast iron construction with slide-away coupling for removal of submersible pump and drop pipe through the wellhead without loosening threaded fittings or excavation.
Funnel-top female and matching tapered male mating surfaces inside well to form watertight seal with Teflon coated neoprene O-ring. Flanged neoprene gasket and contoured brass collar for watertight seal on nipple and well casing. Drop pipe size of 1-1/4-inch. Campbell part B-20 or equal.
C. Drop Pipe: Galvanized steel, Schedule 40, and fittings shall be threaded galvanized steel, Schedule 40. Provide reducers at pitless adapter.
D. Bleeder Valve: Brass, 3/4 inch, Campbell Part No. BOB-3 or approved equal.
E. Safety Rope: 1/4 inch braided polypropylene, tested to exceed 1,000 pounds breaking strength.
F. Cable Guard: Molded thermoplastic construction, protective submersible pump wire from abrading against well casing. Snap-in feature eliminates need to fish wire through wire openings.
Campbell Part No. WG6 or equal.
G. Torque Stop: Buna-n rubber or FDA-approvable PVC torque stop with all-stainless steel clamps to protect pump and well components from starting torque damage. Campbell part numbers TRC or TS48 or equal.
2.13 SUBMERSIBLE PUMP CABLE
Four-wire cable, all conductors are stranded copper with type RW, RUW, TW, or TWU insulation, suitable for use with submersible pumps. One conductor shall be used for ground connection to pump motor frame.
2.14 CHECK VALVE
In-line Check Valve, 1-inch Brass, Watts Series 6 or approved equal.
3.1 REMOVAL OF EXISTING SUBMERSIBLE PUMP
The existing well is approximately 26.5 feet deep. Remove existing submersible pump, galvanized steel drop pipe, pump cable, and well cap. The existing drop pipe, pump cable, and well cap will become the property of the Contractor for disposal off site in an approved manner. The existing submersible pump shall be salvaged and re-installed.
3.2 EXISTING SUBMERSIBLE PUMP INSTALLATION
A. Install salvaged submersible pump inside well casing, bottom of pump shall be approximately 22 feet below existing ground level. Verify existing well depth before installing submersible pump.
B. Pitless Adapter: Install 1-1/4-inch pitless adapter approximately 3 feet below ground level.
C. Drop Pipe: Install 1-1/4-inch galvanized steel drop pipe. Utilize suitable pipe thread compound.
D. Bleeder Valve: Install bleeder valve in drop pipe, approximately 6 feet below ground surface.
Install a 1-1/4-inch galvanized steel tee fitting and reducer bushing as required.
E. Submersible Pump Cable:
Place a protective cover over the edge of the casing to protect cable from damage as pump is lowered into well.
Secure cable to drop pipe every 10 feet with polyethylene plastic cable guards or nylon cable clips. Install cable taut and on same side of drop pipe during the complete installation. Place final clip just below pitless adapter and leave a small amount (3 feet) of slack cable at the wellhead.
Splicing Motor Cable: Utilize a heat shrink splice…