AttachmentJ2Deadman&PeteKingFSSS.pdf
PDF 413 KB Posted
- Solicitation number
- AG-02RC-S-17-0063
About this file
Solicitation Attachment J-2, Forest Service Supplemental Specifications, 45 pages
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend2_WFDeadmanPeteKing0001.pdf | ||
| FinalRFPWFDeadmanPeteKing.docx | DOCX document | |
| Amend1.doc | DOC document | |
| AttachJ3WFDeadmanPeteKingSignedFinalPlans.pdf | ||
| RFPWFDeadmanPeteKing.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOREST SERVICE
SUPPLEMENTAL SPECIFICATIONS
For
WEST FORK DEADMAN CREEK
PETE KING CREEK
CULVERT REPLACEMENTS
DJ&A, P.C.
Engineers - Planners - Surveyors
3203 So. Russell St Missoula, MT 59801
U.S.D.A. FOREST SERVICE
CLEARWATER–NEZ PERCE NATIONAL FORESTS
February 2016
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
102 - Bid, Award, and Execution of Contract
103 - Scope of Work
104 - Control of Work
105 - Control of Material
106 - Acceptance of Work
107 - Legal Relations and Responsibility to the Public
108 - Prosecution and Progress
109 - Measurement and Payment
152 – Construction Survey and Staking
153 – Contractor Quality Control
155 - Schedules for Construction Contracts
156 - Public Traffic
157 - Soil Erosion Control
201 – Clearing and Grubbing
203 - Removal of Structures and Obstructions
204 - Excavation and Embankment
208 - Structure Excavation and Backfill for Selected Major Structures
251 - Riprap
272 - Geocell Abutment Stabilization
308 - Minor Crushed Aggregate
553A – Precast Concrete Structures
554 – Reinforcing Steel
603 - Structural Plate Structures
622 - Rental Equipment
626 - Plants, Trees, Shrubs, Vines, and Groundcovers
703 - Aggregate
705 - Rock
725 - Miscellaneous Material
736 - Geocell
Preface
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
Deletions
Delete all but subsection 103.01 Intent of Contract.
West Fork Deadman Creek 5541-3.30
The intent of the contract is to remove an existing corrugated steel pipe on the West Fork of Deadman Creek on Road No. 5541 at mile post 3.30 in the Nez Perce-Clearwater National Forests. The structure is located in the Lochsa/Powell Ranger District in Section 14, T. 34 N., R.
7 E., Idaho County, Idaho.
This project includes removing and disposing an existing culvert, structure excavation, roadway embankment, backfilling, compacting, furnishing and installing a new structural plate arch culvert on precast footings, riprap, and hauling and placing crushed aggregate surfacing. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.
Pete King Creek 418-1.13
The intent of the contract is to remove an existing corrugated steel pipe on Pete King Creek on Road No. 418 at mile post 1.13 in the Nez Perce-Clearwater National Forests. The structure is located in the Lochsa/Powell Ranger District in Section 21, T. 33 N., R. 6 E., Idaho County, Idaho.
This project includes removing and disposing an existing culvert, structure excavation, roadway embankment, backfilling, compacting, furnishing and installing a new structural plate arch culvert on precast footings, forming and placing concrete for headwalls, riprap, and hauling and placing crushed aggregate surfacing. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.
104 - Control of Work
Deletions Delete Sections 104.01, 104.02, and 104.04.
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02 Material Sources
Add the following before the first paragraph.
Sources have been designated for this project as follows:
Unclassified Borrow Source: Pete King – Government Furnished. The Government source for Unclassified Borrow for the Pete King Site is the Jungle Point Pit at the end of FS Road #5513. This is in Section 22 of T33N, R6E.
Unclassified Borrow Source: WF Deadman – Government Furnished. A Government source for Unclassified Borrow for the W.F. Deadman Creek Site is at Mile Post 25.4 on FS Road #101. This is in Section 4 of T34N, R7E.
Riprap – Contractor Furnished – There is no designated Government source for Riprap for this project.
Crushed Aggregate – Contractor Furnished – There is no designated Government source for crushed aggregate for this project.
Coarse Granular Backfill – Contractor Furnished – There is no available Government source for Coarse Granular Backfill for construction of the geocell abutment stabilization.
Waste Site – Government Furnished. The waste site for excess and unsuitable material is the Jungle Point Pit described above for Pete King and the Pit at MP 25.4 on Road #101 for Deadman Creek. All other materials designated for removal and disposal must be disposed of away from Forest Lands as per SPS Section 202.
Add the following to section (b) Contractor-located sources.
Prior to any pit development or use of materials, the Contractor shall provide to the CO a State certification that the pit site is free of noxious weed as listed on the "All States Noxious Weeds List”.
106 - Acceptance of Work
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.02 Protection and Restoration of Property and Landscape.
Add the following:
Work within the wetted perimeter of streams will be allowed only as specified in the approved project permits.
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
108 - Prosecution and Progress
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
Add the following Subsection:
109.10 Methods of Measurement
One of the following methods of measurement for determining final payment is DESIGNATED IN THE SCHEDULE OF ITEMS for each PAY ITEM:
(a) Actual Quantities (AQ). These quantities are determined from measurements of completed work.
(b) Contract Quantities (CQ). As defined in 109.02 (b) and supplemented above.
(c) Lump Sum Quantities (LSQ). As defined in 109.02(h)
152 – Construction Survey and Staking
152.01(a) Personnel.
Add the following:
Conduct all construction staking under the direction of a licensed professional engineer or land surveyor who is closely associated and familiar with construction staking.
153 – Contractor Quality Control
Add the following.
153.07. Project Submittals
At a minimum the contractor shall provide project submittals as shown on the below Submittal Log. Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.
Submittal Log
Log No.
Incidental to
Pay Item(s) Description of Submittal
Type of Submittal
Requirement found in
Specification No.
/Drawings
Additional Specification References
1 151 Weed Free Material Source Certification
Material Certification
FSSS 105.02(b)
2 151 Contractor Quality Control Plan Plan 153.02 552.09
3 151 Traffic Control Plan Plan FSSS 156.03
4 157 Dewatering and Soil Erosion and Pollution Control Plan
Plan FSSS 157.03
5 157 Straw Wattle Certification Material
Certification
157.14 713.13
6 204 Material Moisture/Density Testing Test Results Table 204-1 106
7 204 Embankment Compaction Testing Test Results 204.11 106
8 208 Excavation Plan Plan FSSS 208.04
9 208 Material Moisture/Density Testing Test Results Table 208-1 106
10 208 Structure Backfill Compaction Testing
Test Results 208.11, 208.12 106
11 272 Geocell Abutment Stabilization Material
Certification 272.06
106, FSSS 736,
Drawings
12 272 Geocell: Course Granular Backfill Material
Certification 272.06
106, FSSS 703.03,
Drawings
13 272 Geocell: Geotextile – Type II Material
Certification 272.06
106, 714, Drawings
14 552 Structural Concrete: Mix Design Mix Design 552.03 553, 553A, Drawings
15 552 Structural Concrete: Testing Test Results 552.19 106, Drawings
16 553A Miscellaneous Material: Grout Material
Certification
FSSS 725.40
553, Drawings
17 553A Miscellaneous Material: Grout Product
Approval
FSSS 725.40
553, Drawings
Submittal Log
Log No.
Incidental to
Pay Item(s) Description of Submittal
Type of Submittal
Requirement found in
Specification No.
/Drawings
Additional Specification References
18 553A Welder Certification Copy of
Certification Sheet 2 of Plans
19 553A Precast Concrete Structures Shop Drawing FSSS 553A.03 104, 552, 553, 20 553A Precast Concrete Structures: Industry Certification
Fabrication Certification
FSSS 553A.02
21 553A Precast Concrete Structures: Testing Test Results FSSS 553A.06 106, 554, 562
22 553A Reinforcing Steel Order List 554.03 553A, 709, Drawings
23 601 Concrete Mix Design Mix Design 601.03
24 603 Structural Plate Structures Assembly
Instructions 603.04
106, Drawings
25 603 Structural Plate Structures Material
Certification 603.04
106, Drawings
26 622 Equipment Rental Equipment Approval
FSSS 622.02
27 625 Seed Mix & Mulch Material
Certification 625.07
106, FSSS 625,
155 - Schedules for Construction Contracts
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.03 Accommodating Traffic During Work.
Delete the first paragraph and replace with the following:
Accommodate traffic according to the requirements set forth below, MUTCD, and Section 635.
Submit a traffic control plan for acceptance at least 30 days before intended use.
Add the following project specific requirements:
West Fork Deadman Creek 5541-3.30
The contractor will be allowed to close Road No. 5541 to through traffic in the immediate vicinity of the culvert during construction.
Give the CO at least 21 days advance written notice prior to any road closure period to allow public notice of the closure by the Forest Service.
Pete King Creek 418-1.13
The contractor will be allowed to close Road No. 418 to through traffic in the immediate vicinity of the culvert during construction.
Give the CO at least 21 days advance written notice prior to any road closure period to allow public notice of the closure by the Forest Service.
Delete the following from the last sentence of the last paragraph:
according to Subsection 106.07(b)
156.04 Maintaining Roadways During Work.
(a) Add the following:
A detour road will not be allowed at this site.
156.08 Traffic and Safety Supervisor.
Delete this subsection in its entirety.
157 - Soil Erosion Control
157.02 Materials
Add the following:
Provide bales, wattles, logs and rolls from a certified noxious weed free source.
157.03 General.
Delete the first two paragraphs and replace with the following:
Submit a Dewatering and Soil Erosion and Pollution Control Plan detailing permanent and temporary control measures to minimize erosion and sedimentation during and after construction in accordance with the plans. Do not modify the type, size, or location of any control or practice without approval. Submit the erosion control plan proposal at least 7 days before operations begin to the CO for approval.
Reflect in the Dewatering and Soil Erosion and Pollution Control Plan special concerns and measures necessary to protect resources and government improvements. Include:
(a) The construction activities and sequence of implementation relating to specific erosion control measures.
(b) The location and type of permanent controls to be implemented during construction.
(c) The location and type of temporary controls to be implemented during construction. The following pollution prevention measures are a requirement for endangered species protection:
i. All equipment will be inspected for leaks prior to commencing work each day and any identified problems corrected before equipment is allowed to operate.
ii. Fueling, maintenance and staging of equipment will occur in designated areas away from water bodies.
iii. A spill containment kit will be available onsite at all times during construction, and proper notification procures will be in place in the event of a hazardous release.
iv. Absorbent pads will be placed beneath fuel tanks during fueling and maintenance.
Pads will also be placed under any pumps while operating.
(d) For work in stream channels with running water a detailed dewatering plan is required.
The following dewatering, fish salvage, and turbidity control measures are a requirement for endangered species protection:
i. All instream work must be completed during the designated instream fisheries work window.
ii. The Contracting Officer shall be notified at least 72 hours in advance of commencing dewatering and rewatering activities.
iii. The Contractor shall coordinate and participate in the fish salvage operations in cooperation with the Contracting Officer’s fisheries biologist(s). The Contracting
Officer will provide fisheries biologists and capture equipment to lead the fish salvage effort. The Contractor shall provide pumps, equipment, labor and resources during the fish salvage operations to ensure fish passage and flow conditions per the Drawings and specifications.
iv. Work area isolation and fish capture activities will occur during periods of the coolest air and water temperatures possible, normally early in the morning, and during conditions appropriate to minimize mortality for the species present.
Electrofishing during cooler water temperatures would reduce the stress levels of salmonids.
v. Flows will be completely diverted around the instream work site through a combination of pumping and/or pre-approved, alternative methods and returned to the channel below the project area. Pump screen openings shall not exceed 3/32 or
0.0938 inches (2.38 mm). If the diversion inlet is not screened, the diversion outlet will be placed in a location that facilitates safe reentry of fish into the stream channel.
vi. Flow diversion structures will be constructed with sand bags covered with plastic sheeting. Cofferdams, portable bladder dams, or other technologies constructed of non-erodible material may also be used to contain stream flow.
vii. Once channel rehabilitation is complete, the streambed will be washed and sediment-laden water within the isolation area should be pumped to the forest floor and not allowed to return to the stream. Once the isolated streambed is washed, water will be slowly released back into the channel to minimize sediment suspension, reaching full streamflow over a period of at least one hour.
(e) For work in stream channels without flowing water describe level of ground and vegetative disturbance and measures to reduce potential sediment delivery.
(f) Description of the monitoring plan.
Add the following to the third paragraph:
Upon completion of construction at the site, remove all temporary erosion control devices, dewatering materials and equipment from Government property.
157.08 Water Crossings.
Add the following:
At any channel crossing where there is running water, dewater by rerouting water flow around the site before and during excavation and embankment operations.
201 – Clearing and Grubbing
Construction Requirements
201.06 Disposal. Delete this subsection and substitute the following:
Dispose of construction slash by placing on finished embankment slopes to reduce soil erosion.
When placing slash on embankment slopes start at the toe of the fill and place as flat as practicable on the completed slope.
If trees are removed from within a Riparian Habitat Conservation Area during project work, trees are to remain on-site and will be placed as directed by the CO.
If trees are removed from outside of a Riparian Habitat Conservation Area during project work, trees could be merchantable timber. In this instance, merchantable timber is the Government’s property. Limb and deck merchantable timber on site as directed by the CO.
203 - Removal of Structures and Obstructions
203.05 Disposing of Material.
Modify this subsection as follows:
(a) Remove from project. Add the following:
All materials designated for removal become the property of the Contractor and are to be disposed of by removing off of Forest Service Lands in accordance with all local, state and federal requirements.
(b) Burn. Delete this section.
(c) Bury. Delete this section.
Add the following:
(e) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes or scatter as directed by the CO to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.
204 - Excavation and Embankment
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph and substitute the following:
Dispose of unsuitable or excess material at designated sites approved by the CO.
208 - Structure Excavation and Backfill for Selected Major Structures
208.02 Add the following:
Backfill material 704.03
208.04 General.
Add the following:
Use all suitable material in the construction of the roadway embankment and for structural backfill. Field drain and dry excessively wet material that is otherwise suitable for embankment before placement. Place and shape unsuitable or excess material at designated sites shown on the drawings or as directed by the CO.
Submit an Excavation Plan for approval that demonstrates conformance with all applicable OSHA regulations and as a minimum includes the following: drawings and a written outline illustrating and describing the proposed excavation limits, methods, equipment to be used, location of stockpiles, and estimated quantities. The Excavation Plan must comply with all applicable OSHA requirements and list the soil type assumed. Due to the depth of excavation at the Deadman Creek site, maximum allowable excavation sloping and/or benching must be determined by a qualified Professional Engineer to conform to OSHA regulations.
208.10 Backfill.
Delete the first sentence and replace with the following:
Backfill to at least 2’ above the top of the structure with material meeting the requirements of Subsection 704.03, Backfill Material. Backfill the remaining material to finished subgrade as specified in Section 204.
251 - Riprap
251.01 Description
Delete the first sentence and add the following:
This work consists of furnishing, hauling, and placing of riprap for bank protection, slope protection, drainage structures, erosion control, and other features shown on the plans.
Add the following:
251.04a Grade Control Structure.
Furnish riprap in accordance with section 705.05 and as shown on the drawings from the source described in FSSS section 105. Place or rearrange individual rocks by mechanical methods to obtain a shape as shown on the drawings.
Fill all voids left during placement of grade control structures adjacent to concrete footings or corrugate pipes with excess structural excavation material.
All grade control structure locations must be approved by the CO prior to excavation or placement of rock.
251.04b Fish Rest Stop Rock.
Furnish riprap for Fish Rest Stop Rocks in accordance with FSSS 105 and as shown on the drawings. Randomly place individual rocks by mechanical methods as shown on the drawings.
Fill all voids left during placement of rocks adjacent to corrugate pipes with excess structural excavation material.
251.07 Acceptance
Delete the fourth sentence and add the following:
Structure excavation and backfill will be evaluated under section 208.
Delete the fourth sentence and add the following:
Structure excavation and backfill will be evaluated under Section 208.
272 - Geocell Abutment Stabilization
Description
272.01 This work consists of constructing geocell abutment stabilization at each abutment using a cellular confinement system such as Presto Geoweb Cellular Confinement System or Webtec TerraCell in accordance with the plans and manufacturers recommendations.
Materials
272.02 Requirements. Ensure that material conforms to specifications in the following subsections:
Granular Backfill Type (c) 703.03 Geotextile, Type II (A, B, C) 714.01 Geocell 736
Construction Requirements
272.03 General. Perform the work specified in Section 208 or 209. Use ditches, grading or similar methods to prevent surface runoff that may occur during inclement weather from ponding in the foundation excavation.
272.04 Storage and Handling of Material. During shipment and storage, wrap geotextile materials in heavy-duty protective covering. Protect the material from mud, soil, dust, debris and sunlight prior to installation.
272.05 Geotextile Installation. Place the geotextile according to Section 207. Have the surface approved by the CO prior to placing geotextile.
Sew or overlap adjacent strips a minimum of 12” at joints. Insert securing pins through both strips of overlapped geotextile at minimum intervals of 3 feet, but no closer than 2 inches to each edge, to prevent the geotextile from being displaced.
Have the installed geotextile approved by the CO prior to setting the geocells.
272.06 Geocell Installation. Furnish the CO with product literature and certification as required in Section 106.03 for review and approval 7 days prior to installation. When requested by the CO, furnish a sample of the geocell from each lot for verification testing.
Place the geocell sections directly on the prepared subgrade. Expand the geocell sections into position at the grades and lines as shown on the plans. Hold the expanded geocell sections with suitable “stretcher frames”, steel stakes driven inside selected outer cell walls, or other similar methods as allowed by the manufacturer prior to filling. Ensure that the individual cells have expanded to the minimum dimensions required by the manufacturer. If necessary field cut sections as per the manufacturer’s recommendations to the lines shown on the plans.
Connect geocell panels in accordance with the manufacturer’s recommendations.
272.07 Infill Placement. Furnish the CO with the manufacturer’s specific recommendations for backfilling 7 days prior to placement of the geocells.
Place coarse granular backfill meeting Subsection 703.03 into the expanded cells with equipment appropriate for the site conditions such as a backhoe or a front-end loader. Do not drop infill material more than 3 feet to avoid damage or displacement of the cell walls.
Overfill the geocell cells and level to a minimum of 2 inches above the top of the cell walls. A front-end loader may be used to place the infill provided that it only traffics above geocell sections that have been filled and covered with the minimum 2 inches of additional material.
Compact the infill material with a vibratory plate compacter. Operate compaction equipment over the full width of the geocell. Make at least three complete passes or until visible deformation of the infill ceases. Grade the surface to be ½ inch above the top of the cells.
Ensure that the cell walls are not exposed after fine grading is completed.
Use the geocell manufacturer’s specific recommendations for backfilling if they are more stringent than stated above.
272.08 Acceptance. Geotextile will be evaluated under Subsections 106.02 and 714.01.
Material for geocell will be evaluated under Subsections 106.2 and 106.03.
Granular backfill material will be evaluated under Section 106.02 and 106.04.
Measurement
272.09 Method. Measure the items listed in the bid schedule according to Subsection 109.02 and the following.
Measure geocell by the square yard in place, exclusive of wastage.
Payment
272.10 Basis. The accepted quantities will be paid for at the contract price per unit of measurement for the Section 272 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
The cost for furnishing and placing the granular backfill required in Sections 207, 208, and 209 for geocell infill is incidental to this pay item and no separate payment will be made.
The cost for furnishing and placing geotextile for the geocell installation is incidental to this pay item and no separate payment will be made.
308 - Minor Crushed Aggregate
Delete section 308 in its entirety and replace with the following:
Description
308.01 This work consists of placing Government furnished aggregate or furnishing and placing crushed aggregate for bedding, backfill and roadway aggregate course.
Material
308.02 Conform to the following Subsections:
Crushed aggregate 703.06 Water 725.01
Construction Requirements
308.03 Preparing Surface. Prepare the roadway surface on which aggregate course is placed as shown on the plans.
308.04 Placing Crushed Aggregate.
(a) Roadway aggregate. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for compaction. Spread and shape the mixture on the prepared surface in a uniform layer.
Do not place the mixture in a layer exceeding 6 inches in compacted thickness. When more than one layer is necessary, compact each layer according to Subsection 308.05, Method 2 before placing the next layer.
(b) Bedding and backfill aggregate. Place and shape the mixture in layers that, when compacted, do not exceed 6 inches in depth.
308.05 Compacting and Finishing Crushed Aggregate.
Roadway aggregate. Compact using the methods below, specified in the Schedule of Items.
(1) Method 1. Operate equipment over the full width of spread aggregate.
(2) Method 2. Compact the aggregate by operating compaction equipment over the total width until visible deformation ceases. A minimum of three complete roller passes shall be made at a moisture content suitable for compaction.
308.06 Acceptance. Crushed aggregate will be evaluated under Subsections 106.02 and 106.03.
Furnish a production certification including gradation and quality properties for each source.
Construction of roadway aggregate courses will be evaluated under Subsections 106.02 and
106.04. Method 2 compaction will be evaluated under Section 106.04.
Placement of bedding and backfill aggregate will be evaluated under Subsection 106.02 and Section 209.
Preparation of the surfaces on which crushed aggregate is placed will be evaluated under Section 303 and 209 as applicable.
Measurement
308.07 Measure the Section 308 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.
Measure crushed aggregate by the cubic yard in-place on the road.
Measure width horizontally to include the top of aggregate width including designed widenings.
Measure the length horizontally along the centerline of the roadway.
Payment
308.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 308 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
553A – Precast Concrete Structures
Description
553A.01 Work. Construct precast concrete members. In addition, manufacture, test materials for, transport, store, and install all precast concrete portions except piling, and perform all necessary grouting, welding, or other connections. Furnish precast concrete members complete and in place, including all concrete reinforcing steel and incidentals connected therewith.
Materials
553A.02 Requirements. Provide materials that meet the requirements specified in the following subsections:
High-Strength Nonshrink Grout ……………………………… 725.40 Mortar ………………………………………………………… 725.40 Reinforcing Steel ……………………………………………… 709.01 Sealants, Fillers, Seals, & Sleeves …………………………….. 712.01 Structural Concrete ……………………………………………. 552 Structural Steel ………………………………………………… 717.01
Provide precast concrete members of the size, shape, strength, air content, and finish that are SHOWN ON THE DRAWINGS. Precast concrete members must be manufactured by a plant with any of the following certifications:
Precast / Prestressed Concrete Institute (PCI) o Bridge 1, Precast Bridge Products (no prestressed reinforcing).
o Commercial 1, Precast Concrete Products (no prestressed reinforcing).
National Precast Concrete Association (NPCA) o Precast
American Concrete Pipe Association (ACPA) o QCast
Submit a copy of the transmittal letter of the latest PCI, NPCA, or ACPA inspection/certification with the shop drawings.
In lieu of the above certifications, the Contractor shall retain a professional engineer to provide quality assurance for the work by inspecting and certifying in writing the concrete members are constructed in accordance to the specification and shall include but not limited to:
a) Shop drawing review.
b) Concrete member dimensions.
c) Concrete mix design.
d) Aggregate sources and test results.
e) Steel reinforcing placement.
f) Concrete curing and strength test results.
g) Concrete material certifications.
h) Placement mixing, delivery and sampling.
Certification of the above shall be received by the CO prior to shipment and installation at the job site.
Perform all sampling, testing, and inspection necessary to ensure quality control of the component materials and the concrete. Sample and test for quality control and acceptance testing in accordance with the AASHTO or ASTM test methods prescribed in Section 552.
Maintain adequate records of all inspections and tests. Keep records that indicate the nature and number of observations made, the number and type of deficiencies found, the quantities approved and rejected, and the nature of any corrective action taken.
Construction
553A.03 Performance. Construct precast concrete structural members in accordance with the following sections and subsections, as applicable:
Reinforcing Steel ………………………………………………... 554 Storing, Transporting, & Erecting ………………………………. 553.08 Structural Concrete ……………………………………………… 552
Submit four sets of shop drawings to the CO for approval, including the concrete mix design for each class of concrete proposed for use, a minimum of 21 days before fabrication of the precast member(s).
553A.04 Casting Yard. The precasting of concrete structural members may be done at either a casting yard of an precast industry certified plant or a casting yard of the Contractor’s choice with the appropriate certifications discussed above.
553A.05 Handling, Transporting, & Erecting. Provide additional reinforcement, as needed, to meet the requirements of handling, transporting, and erecting precast members.
553A.06 Acceptance. Reinforcing steel, anchor devices, elastomeric bearings, and material for concrete and grout will be evaluated under Subsection 106.03. Furnish production certifications for hydraulic cement, and reinforcing steel.
Concrete for precast concrete members will be evaluated under Subsections 106.02, 106.03, and 106.04.
Construction of precast concrete members will be evaluated under Subsections 106.02 and 106.04.
Reinforcing steel will be evaluated under Section 554.
Falsework and forms will be evaluated under Section 562.
Measurement
553A.07 Measure the Section 553A items listed in the bid schedule according to Subsection
109.02 and the following as applicable.
Do not measure reinforcing steel, concrete, anchorages, plates, nuts, and other material contained within or attached to the unit for precast concrete structural members.
Payment
553A.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 553A pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
554 – Reinforcing Steel
Construction Requirements
554.03 Order Lists. Delete the contents of this subsection
603 - Structural Plate Structures
603.03 General.
Delete the first sentence and add the following:
Excavation and backfill will be evaluated under Section 208.
603.05 Acceptance.
Delete the third sentence and add the following:
Excavation and backfill will be evaluated under Section 208.
622 - Rental Equipment
622.02 Rental Equipment
Delete the first two sentences of the first paragraph and add the following:
Provide equipment of the type listed in the Schedule of Items. Provide equipment of at least the minimum size needed to efficiently perform the work. Submit the model number of the equipment to the CO for approval before delivery to the project site. Equipment shall be reasonably free of leaks and other mechanical deficiencies.
626 - Plants, Trees, Shrubs, Vines, and Groundcovers
626 Delete entire section and replace with the following:
Description
626.01 This work consists of furnishing or excavating on site, transporting and re-planting trees, shrubs, vines groundcovers, and other native plants with machinery.
Materials
626.02 Existing plant material will be made available within 500 feet of project site for re-planting on newly constructed embankment slopes, and stream channel banks. Do not excavate plant materials unless the Contractor’s operations will permit re-planting within 1 hour.
Construction Requirements
626.03 General. Do not plant in frozen ground, when snow covers the ground, or when the soil is over saturated, extremely dry, or is otherwise unsatisfactory for planting.
Plant clumps shall not be excavated from critical locations, riparian areas, along streams, areas that may be prone to future erosion, or as determined by the CO. When excavating plants contractor shall leave minimum spacing of 10’ to 20’ between removals. Excavated plant areas shall have holes refilled with good quality native material. Pack soil firmly into hole.
The excavated plant shall have the entire root system, and native dirt clump, including duff layer to establish a healthy growing condition. Plants shall be healthy,and growing vigorously.
Loosen soil at the sidewalls and bottom of plant pit to a sufficient depth before setting the plant.
Remove all weeds, roots and other unsuitable material from the planting site. Remove air pockets from around the root mass when planting. Spacing of clump plantings shall be shown on the drawings or determined by the CO.
Keep all plant material moist and exercise care to prevent damage to bark, branches, and root systems. Employ all necessary means to preserve the plants in a healthy growing condition during plant establishment period.
626.04 Acceptance. Planting of trees, shrubs, and other native plants will be evaluated under Subsections 106.02 and 106.04.
Measurement
626.05 Measure the Section 626 items listed in the bid schedule according to Subsection 109.02.
Payment
626.06 The accepted quantities will paid at the contract price per unit of measurement for section 626 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this section. See Subsection 109.05
703 - Aggregate
703.03 Granular Backfill.
Add the following:
(c) Coarse Granular Backfill. Furnish backfill material that consists of clean, hard durable particles or fragments of crushed stone, crushed slag or crushed gravel meeting the gradation shown below.
Sieve Size Percent Passing
1 inch 100 ¾ inch 75 to 100 No. 4 0 to 60 No. 40 0 to 50 No. 200 0 to 5
705 - Rock
Add the following:
705.07 Streambed Simulation Rock.
(a) General. Furnish a mixture of soil, gravel, cobble, and boulders to simulate a natural streambed. The cobbles and boulders should be hard, durable rock that conforms to test values in 705.02.
Table 705-5 – Gradation requirements for Streambed Simulation Material inches or sieve size
Bed Class 100% passing 84% passing 50% passing 16% passing 10% passing
2 5 2 3/4 1/4 No. 10
4 10 4 1 3/4 1/2 No. 10
6 14 6 2 1/2 3/4 No. 10
8 22 8 3 1 No. 10
10 24 10 4 1 No. 10
12 30 12 5 1 1/2 No. 10
14 36 14 6 1 3/4 No. 10
16 42 16 7 2 No. 10
20 48 20 8 3 No. 10
24 60 24 10 3 No. 10
36 72 36 14 4 No. 10
48 96 48 18 6 No. 10
725 - Miscellaneous Material
Add the following section:
725.40 High-Strength Nonshrink Grout
Furnish grout that is packaged and ready for use with the addition of water at the construction site. Ensure that each bag is stamped to show the last date on which it may be used. Use grout that consists of a hydraulic cementitious system, graded and processed natural fine aggregate, and additional technical components such that the product meets the following conditions:
(a) Free of inorganic accelerators, including chlorides.
(b) Free of oxidizing catalysts.
(c) Free of gas-producing agents.
(d) When mixed to 130 percent flow on flow table (ASTM C 230 at 10 drops), it does not reduce in linear dimension when tested in accordance with ASTM C157.
Take measurements at 72 hours and 7 days.
(e) Produces no bleeding for the first 2 hours after mixing when mixed to 130 percent flow on flow table (ASTM C 230 at 10 drops), as tested in accordance with
ASTM C232.
(f) Has a minimum strength as follows when tested in accordance with ASTM C 109:
(1) After 72 hours, 25 MPa (3500 psi).
(2) At 7 days, 40 MPa (6000 psi).
(3) After 28 days, 50 MPa (7200 psi).
Provide performance characteristics at 115 to 120 percent flow on flow table (ASTM C 230 at 10 drops).
(g) It must be designed, as stated by the manufacturer, to be mixed, placed, and cured at atmospheric temperatures of 5O C to 30O C (40O F to 85O F). Submit products proposed for use for approval by the CO and accompany them with manufacturer’s submittals substantiating all requirements in this subsection, including graphs or charts showing the time, temperature, and humidity requirements for curing to achieve the specified grout strengths; and recommendations for storage, mixing, application, and curing procedures.
As specified as grout on the contract plans, the following products meet the above requirements.
1. MASTERFLOW 928 GROUT, manufactured by Chemrex.
2. CRYSTEX GROUT, manufactured by L&M Construction Chemicals, Inc.
3. CEMENT ALL, manufactured by CTS Cement Manufacturing Co.
4. SURE-GRIP HIGH PERFORMANCE GROUT manufactured by Dayton Superior.
725.41 Mortar
Furnish mortar that is packaged and ready for use with the addition of water at the construction site. Ensure that each bag is stamped to show the latest date on which it may be used. Use mortar that consists of a cementitious system made up of:
(a) Natural aggregate, 3/8” maximum size, that meets the requirements specified in ASTM C 33 except for grading. Accomplish grading by blending sieve sizes to obtain the optimum density.
(b) Metallic aggregate free from nonferrous material, soluble alkaline compounds, and visible rust.
(c) Water reducers, workability agents, air-entraining agents, and catalysts.
Blend the materials to minimize bleeding, increase workability, resist exposure to freeze-thaw cycles and deicing salts, and prevent shrinkage within and at the perimeter of the patch, keyway, or other area to be filled.
Ensure that the minimum compressive strength of the mortar, as tested by ASTM C 109 for a 3” slump, is:
24-hour...........................................................................................35MPa (5000 psi) 7-day...............................................................................................60 MPa (8500 psi) 28-day.............................................................................................70 MPa (10,000 psi)
Ensure that the durability of the products when tested at 300 cycles, ASTM C 666, procedure A is:
Submerged in: DF (%)
Water 98
5% CaCl2 solution 95
5% NaCL solution 85
Ensure that the scaling resistance has a rating of 3, Moderate Scaling, after 50 cycles when tested in accordance with ASTM C 672.
Provide certification from the manufacturer that the product is compatible for work that is 1” or more in depth and more than 1” in width; and where the mixing, placing, and curing temperatures may range from 5O C to 30O C (40O F to 85O F).
Submit products proposed for use to the CO for approval, and accompany them with the manufacturer’s submittals substantiating all requirements in this section, including (1) graphs or charts showing the time, temperature, humidity, and curing requirements to achieve mortar strengths equal to the adjacent concrete; and (2) complete recommendations for storage, mixing, application, and curing procedures.
As specified as mortar on the contract plans, the following products meet the above requirements.
1. EMACO T425 or T430, manufactured by Chemrex.
2. RAPID SET DOT REPAIR MIX manufactured by CTS Cement Manufacturing Co.
3. SURE-GRIP HIGH PERFORMANCE GROUT (when extended with pea gravel) manufactured by Dayton Superior .
736 - Geocell
736.01 Geocell.
Furnish geocell material consisting of sheet strips fabricated from high-density polyethylene (H.D.P.E.), connected in series at off-set, full-depth ultrasonic seams aligned perpendicular to the longitudinal axis of the strips. When expanded, the interconnected strips form the walls of a flexible, three-dimensional cellular confinement structure into which the specified infill material is placed.
736.02 Requirements. Furnish geocells consisting of polyethylene material treated to resist ultraviolet degradation and conforming to the requirements shown in table 736-1.
Table 736-1 – requirements for geocells.
Density ASTM D 1505 0.935 to 0.965 g/cm3 (58.4 to 60.2 pounds per cubic foot).
Environmental Stress Crack Resistance
ASTM D 1693 3000 hour
Strip Sheet Thickness
ASTM D 5199 1.27 mm (50 mil), minus 5 percent, plus 10 percent.
Determine thickness in the flat before any surface texturing or other surface disruption.
Short-term peel strength
U.S. Army Corps of Engineers Technical Report GL-86-19, Appendix A
2000 N (450 pound) minimum for 203 mm (8.0 inch) depth cell
Seam Hang Strength 101.6 mm (4”) weld joint supporting load of 72.5 kg (160 pounds) or
101.6 mm (4”) weld joint supporting load of 72.5 kg (160 pounds) while undergoing temperature change from 23O C to 54O C (74O F to 130O F) on 1 hour cycles.
30 days minimum
7 days minimum
| Deadman & Pete King Cover Page |
| Deadman & Pete King FSSS1 |
File details come from the government source that posted it. Updated .