Appendix_A_FSSS_NZ_Toilet_Repairs.pdf

PDF 145 KB Posted

Attached to
North Zone Toilet Repairs Federal contract opportunity
Solicitation number
AG-02RC-S-16-0095
Issued by
Department of Agriculture Forest Service R1-Northern Region

About this file

Appendix A

View the file

Other files for this federal contract opportunity

Other files attached to North Zone Toilet Repairs, newest first.
File Type Posted
Drawings_NZ_Toilet_Repairs.pdf PDF
Nez_Perce-Clearwater_NF_Nort_Zone_Toilet_Repairs_(AG-02RC-S-16-0095).doc DOC document
Location_Map_to_NZ_Toilets.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NORTH ZONE TOILET REPAIRS

CONTRACT SPECIFICATIONS

NORTH ZONE TOILET REPAIRS

CONTRACT SPECIFICATIONS

TABLE OF CONTENTS

NO. SPECIFICATION TITLE SHEETS

01010 SUMMARY OF WORK 1-3

01025 DEFINITION OF BID ITEMS / MEASURE AND PAYMENT 1-6

01140 WORK RESTRICTIONS 1

01330 SUBMITTAL PROCEDURES 1-2

01430 QUALITY CONTROL REQUIREMENTS 1

01510 MOBILIZATION 1

02222 STRUCTURAL EXCAVATION /BACKFILL&COMPACTION 1-2

02232 AGGREGATE BASE COURSE 1-2

02245 GRADING 1-2

07190 WATER PROOFING MEMBRANE 1

13901 REMOVING AND REPLACING CONCRETE VAULT TOILET 1-2

01010 - 1

SUMMARY OF WORK

SECTION 01010

SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Work for this project consists of removing and disposing sewage from vaults, off Forest in a legal manner; removing the toilet structure; excavating and removing toilet vault; removing and disposing existing vault liners, off Forest in a legal manner;

applying a water proofing membrane to inside surface of the vaults; resettting the vaults and raising the elevation of the vaults using crushed aggregate fill at the base;

resetting the toilet structures; and then building an crushed aggregate ADA ramp to the toilets. Also included will be to remove and replace the concrete approach pads.

The trail head toilet at the Giant White Pine Campground will not be raised 1 foot like all the other toilets in the contract. The toilets close proximity to the parking area will not allow for an ADA ramp if the toilet were to be raised.

Seeding and mulching will be completed once the ground is reshaped and all excess excavation has been removed from project area.

1.2 LOCATION

A. Giant White Pine Campground: Latah County: Palouse RD (T42N R3W Sec 11) (current structures installed in 2001) The campground lies along State Highway 6 at Milepost 19.

Hidden Creek Campground: Clearwater County: North Fork RD (T40N R10E Sec 3) (current structures installed in 1999), This campground sits between Forest Road 250, approximately 13 miles North of the Kelly Forks Work Center, accessed either through the nearest towns of Pierce Idaho or Superior Montana.

Clarke Mtn Campground: Clearwater County: North Fork RD (T38N R7E Sec 34) (current structure installed in 2001). The site is located along Forest Road 250, approximately 23 miles NE of Pierce Idaho, east of French Mountain saddle.

1.3 GENERAL SITE CONDITIONS AND WEATHER

A. The elevation of the site is approximately 2,000 feet above mean sea level. The construction site experiences heavy snowfall and extremely cold temperatures, with snow on the ground typically from mid-November through April.

B. In-depth water table surveys have not been performed; however, if water is encountered during excavation, the Contractor shall perform adequate dewatering to keep the excavation free from water and dispose of the water without damage to property.

01010 - 2

1.4 USE OF PREMISES

A. General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. The project site area will be limited to the general areal in the toilet vicinity and not the campground as a whole.

Contractor's use of premises is limited only by the Government's right to perform work or to retain other contractors on portions of Project.

B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and employees.

C. Confine storage of materials to areas as approved by the CO.

D. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.

E. Preservation of Natural Features: Confines all operations to work limits of the project.

Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

1. Provide temporary barriers to protect existing trees and plants and root zones.

2. Do not remove, injure, or destroy trees or other plants without prior approval.

Consult with CO and remove agreed-on roots and branches that interfere with construction.

3. Do not fasten ropes, cables, or guys to existing trees.

4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

1.5 CAMPING

A. With approval by the North Fork and Palouse Ranger Districts, National Forest Service lands may be used by the Contractor for camping purposes. The camping site must be agreed to in advanced and a camping permit will be issued for the anticipated duration of the work in that area.

1.6 CONSTRUCTION SEQUENCE

A. There is no specified construction sequence or season for this project.

B. Depending on conditions, normal fire restrictions may apply to activities associated with this project.

1.7 FIELD VERIFICATION

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

01010 - 3

END OF SECTION 01100

01025-1

DEFINITION OF BID ITEMS &

MEASUREMENT AND PAYMENT

SECTION 01025

DEFINITION OF BID ITEMS

AND

MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general; what is and what is not included in a bid item; the limits or cut-off points where one bid item ends and another begins; and method of measurements and basis of payment for work items listed in the Bid Item Schedule.

B. Work:

1. Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it, and carrying out all duties and obligations imposed by the contract on the Contractor.

C. Payment:

1. For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications, as shown on the drawings, and as staked in the field.

2. Measurement and payment for contract work shall be made only for and under those pay items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.

1.2 DETERMINATION OF QUANTITIES

A. The contractor shall perform, or cause to be performed, all measurement of quantities of materials incorporated into the work processes that are to be measured under the provisions of the contract.

B. Quantity Measurements:

1. The Contractor shall make all measurements for computation of quantities for all work items except those specified for payment by Contract Quantity (CQ) or Lump Sum Quantity (LSQ).

2. The contractor shall compute the quantities for periodic progress payments; the Contracting Officer shall compute the quantities for the final payment based on measurements taken by the Contractor.

3. All Contractor measurements are subject to verification.

4. The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities.

01025-2

MEASUREMENT AND PAYMENT

5. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.

C. The following measurements and calculations are used to determine contract quantities.

1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

2. The average end area method shall be used to compute volumes of excavation or embankment. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three dimensional methods.

3. Structures shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed. Pipes shall be measured along center of invert.

5. For aggregates measured for payment, the cubic yards shall be measure in place and compacted using the average end area method.

6. For standard manufactured items--such as fence, wire, plates, rolled shapes, pipe conduits--identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

1.3 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

B. Cubic Yard: A measurement computed by one of the following methods:

1. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

2. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

3. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

C. Each: One complete unit, which may consist of one or more parts.

01025-3

MEASUREMENT AND PAYMENT

D. Linear Foot: Linear feet measured horizontally.

1.4 DEFINITION OF BID ITEMS

A. Definition of Bid Item No. 01510 MOBILIZATION

1. Description: Mobilization includes moving personnel, equipment, material, and incidentals to the project sites and performing all work necessary before beginning work at the project sites. Mobilization also includes the obtaining of permits, insurance, and bonds.

2. Measurement and payment: Measurement will be made on a lump sum basis.

There are three project sites, therefore up to 50% of the mobilization is eligible for payment upon mobilizing to the first project site. The remaining mobilization will be split into 25% increments and paid accordingly upon mobilization to the other two sites.

B. Definition Bid Item No. 02222 STRUCUTRAL EXCAVATION

1. Description: Structural excavation will include any necessary excavation in order to remove the concrete vaults for bid item 13901. This bid item will also include any necessary backfill/embankment once the vaults are replace in order to provide a nice even graded surface around the vault prior to placing the 5/8 minus aggregate in bid item 02232A.

2. Measurements and Payment: Structural excavation will be paid on a lump sum basis. There are 7 vaults toilets that will be raised, therefore, 1/7 of the lump sum structural excavation contract price will be eligible for payment upon the completion of each toilet.

C. Definition Bid Item No. 02232 AGGREGATE BASE UNDER VAULT

1. Description: This bid item will include placing and compacting 5/8” to ¾ minus crushed aggregate in the excavated area under the vault prior to replacing the concrete vault according to bid item 13901. The intent is to raise each concrete vault toilet’s elevation 12” above the original elevation upon completion of the project. It is estimated that a 12” compacted lift of aggregate will be required to accomplish this.

2. Measurements and Payment: This bid item will be measure based on contract quantities per cubic yard. There are 7 vaults toilets that will be raised, therefore, it is estimated that approximately 5 cubic yards per toilet will be required.

Payment will be eligible upon completion of work.

01025-4

MEASUREMENT AND PAYMENT

D. Definition Bid Item No. 02232A 5/8” AGGREGATE AROUND THE TOILET

WITH ADA RAMP

1. Description: This bid item will include placing and compacting 5/8” minus aggregate around the base of the toilet, placing and compacting a 5/8” minus aggregate base for the concrete approach pad, and placing and compacting 5/8” minus aggregate to build the ADA ramp per the Contract Drawings.

2. Measurements and Payment: This bid item will be measure based on contract quantities per cubic yard. There are 7 vaults toilets that will be raised, therefore, it is estimated that approximately 14 cubic yards per toilet will be required.

Payment will be eligible upon completion of work.

E. Definition Bid Item No. 03306 RELOACTING EXISTING CONCRETE PADS

1. Description: This bid item will include removing the existing concrete approach pads for each toilet and replacing them according to the Contract Drawings. In lieu of removing and replacing the existing concrete pad the contractor may demolish the existing pads, removing them off Forest in a legal manner, and then reconstruct the concrete approach pads according to the Construction Drawings.

2. Measurements and Payment: This bid item will be paid on a lump sum basis.

There are 7 vaults toilets that will be raised, therefore, 1/7 of the lump sum Relocating Existing Concrete Pads contract price will be eligible for payment upon the completion of each toilet.

F. Definition Bid Item No. 06260 SEEDING

1. Description: This bid item will include seeding all the disturbed grass areas, not covered by crushed aggregate under bid item 02232A, after the completion of all other bid items for each toilet. The seed mix will be provided by the USFS.

2. Measurements and Payment: This bid item will be paid on a lump sum basis.

There are 8 vaults toilets, therefore, 1/8 of the lump sum structural excavation contract price will be eligible for payment upon the completion of each toilet.

G. Definition Bid Item No. 07190 WATER PROOFING MEMBRANE

1. Description: This bid item will include applying two coats of MasterSeal HLM 5000, or equal, to the interior floor and all interior sides of the existing concrete

01025-5

MEASUREMENT AND PAYMENT

vaults. All preparation of concrete surfaces and any other necessary work required for the successful application of the MasterSeal HLM 5000, or equal, will be incidental to this bid item. Other manufacturer’s products may be required for the surface preparation and application of the MasterSeal HLM 5000, or equal, and will be incidental to this bid item.

2. Measurements and Payment: Measurement for this bid item will be based on Contract Quantities per square foot of Sonoshield HLM 5000, or equal, applied.

One measured square foot of Sonoshield HLM 5000, or equal, applied will include both coats applied. There are 8 vaults toilets, therefore, it is estimated that there will be 275 square feet of applied.

Measurements and Payment: This bid item will be paid on a lump sum basis.

There are 8 vaults toilets, therefore, 1/8 of the lump sum structural excavation

H. Definition Bid Item No. 13901 REMOVING AND RESETTING CONCRETE

VAULT TOILET

1. Description: This bid item will include all necessary sewage pumping of the concrete vault toilets. Sewage shall be remove off Forest in a legal manner.

Also included in this bid item is removing and resetting the concrete toilet structure, and removing and resetting the concrete toilet vault. Also included will be to provide and maintain at least two self-contained toilet units at each site while the campground toilets are out of service. Finally this bid item will include removing the existing vault liners and disposing them off Forest in a legal manner.

2. Measurements and Payment: This bid item will be paid on a lump sum basis.

There are 8 vaults toilets, therefore, 1/8 of the lump sum concrete vault toilet

PART 2 - METHOD OF MEASUREMENT

2.1 GENERAL

01025-6

MEASUREMENT AND PAYMENT

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

B. CONTARCT QUANTITIES (CQ)

1. These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

C. ACTUAL QUANTITIES (AQ)

1. These estimated quantities which are determined from actual measurements of completed work.

D. LUMP SUM QUANTITIES (LSQ)

1. These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

PART 3 - EARTHWORK TOLERANCES

3.1 GENERAL

A. Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed trail sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

END OF SECTION 01025

01140 - 1

WORK RESTRICTIONS

SECTION 01140

WORK RESTRICTIONS

PART 1-GENERAL

1.1 USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to the area around the vault toilet and any other immediately adjacent area needed to park equipment or store materials.

2. Government Occupancy: All reasonable accommodations will be made not to interfere with the occupancy of the campground outside of the immediate area of the vault toi-lets.

3. Driveways and Entrances: At the end of each work day or whenever possible keep campground roads and entrances serving camp sites clear and available to the public, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

END OF SECTION 01140

01330 - 1

SUBMITTAL PROCEDURES

SECTION 01330

SUBMITTAL PROCEDURES

PART 1- GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. CO reserves the right to withhold action on a submittal requiring coordina-tion with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for resub-mittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 10 days for initial review of each submittal. Allow addi-tional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial sub-mittal.

3. Allow 10 days for processing each resubmittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

PART 2 – PRODUCTS

2.1 SUBMITTALS

A. General: Prepare and submit submittals required by individual Specification Sections.

1. Number of Copies: Submit two copies of each submittal, unless otherwise indi-cated. CO will return one copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of con-struction and type of product or equipment.

01330 - 2

SUBMITTAL PROCEDURES

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are ap-plicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

PART 3 – EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Contract shall sign and date each submittal signify-ing their approval before submitting to CO.

END OF SECTION 01330

01400 - 1

QUALITY REQUIREMENTS

SECTION 01430

QUALITY CONTROL REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for quality control.

1.2 DEFINITIONS

A. Quality-Control: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that completed construction complies with require-ments. Services do not include contract enforcement activities performed by CO.

1.3 SUBMITTALS

A. Quality Control Plan: Prior to the start of work the contractor shall submit a quality control plan. This quality control plan shall include the method and frequency as to how the contractor will perform internal quality control during the construction period.

Also, included in the quality control plan is how deficiencies will be recognized and corrected.

1.4 QUALITY CONTROL

A. Contractor Responsibilities: Unless otherwise indicated, provide quality control for all work performed under the contract.

PART 3 – EXECUTION

3.1 REPAIR AND PROTECTION

A. Repair and protection are Contractor's responsibility.

END OF SECTION 01400

MOBILIZATION 01510-1

SECTION 01510

MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. Measurement will be made on a lump sum basis. There are three project sites, therefore up to 50% of the mobilization is eligible for payment upon mobilizing to the first project site. The remaining mobilization will be split into 25% increments and paid accordingly upon mobilization to the other two sites.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01510

June 2016

02222-1

SECTION 02222

STRUCTURAL EXCAVATION, BACKFILL AND COMPACTION

PART 1 - GENERAL

1.1 SUMMARY

A. Includes structure excavation, special fills, backfill, and compaction.

1.2 PROTECTION

A. Protect excavations from accumulation of water. If clay soil becomes saturated, compact after it has dried as specified herein.

B. Protect excavations from freezing. If frost action occurs, compact ground after thawing as specified herein.

C. Provide shoring and bracing as necessary to protect structures employees, and the public.

PART 2 – PRODUCTS

2.1 BACKFILL AND FILLS

A. Use the excavated material as specified below:

1. Remove rocks over 8 inches in maximum dimension, ice or frozen earth, muck, debris, and earth with high void content.

2. Remove rocks over 4 inches in maximum dimension for backfill placed within

12 inches of foundation.

3. Materials removed in stripping shall not be used for backfill.

2.2 GRAVEL FILLS

A. Clean pit-run gravel uniformly graded with less than 5% minus #200 material, 2 inches maximum size, free of deleterious materials.

PART 3 – EXECUTION

3.1 EXCAVATION

A. Perform to the lines, grades, and elevations indicated. Extend excavation a sufficient distance from walls and footings to allow for safety, placing and removal of forms, installation of services, and for inspection. Provide proper depth with allowance made for gravel fills formed voids and concrete flatwork.

02222-2

1. Bottoms for piers, footings, and foundation walls shall be level, clean, true to size, and clear of loose materials.

2. Pier excavations shall be drilled or otherwise accurately formed.

3. If excavations for foundations are carried below the specified levels, extend the foundation to the excavated level.

3.2 BACKFILLING

A. Place and compact fills and backfills adjacent to structures in such a manner as to prevent wedging action or eccentric lodging upon or against the structures.

1. Remove forms, and clean the excavation of trash and debris prior to backfilling.

2. Do not place backfill against any concrete footings or wall without prior permission of the Contracting Officer (CO) and in no case less than 7 days after completion of the wall or footings.

3. Place backfill in horizontal layers not more than 12 inches thick with the proper moisture content for the required degree of compaction. Flooding or puddling not allowed. Compact each layer as specified. Backfill layer thickness under concrete flatwork limited to 6 inches maximum.

4. Heavy equipment for spreading and compacting backfill shall not be operated closer to a wall than a distance equal to the height of the backfill above the top of the footing.

5. Provide for anticipated settlement and shrinkage of the backfill and for the finished grades required, including topsoil grading.

6. Prepare subgrades for gravel fill areas level and free from soft spots. Place and compact earthfill where required to raise subgrade. Place gravel to the lines and grades shown. Compact the gravel sub-base as specified until a smooth, uniform use surface is obtained.

3.3 COMPACTION

A. Compact each layer with a jumping jack or plate compacter. Provide three passes or until visual displacement has ceased, whichever is more.

END OF SECTION 02222

02232-1

AGGREGATE BASE COURSE

SECTION 02232

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of furnishing and placing aggregate, and filler if required, on a prepared subgrade.

1.2 SUBMITTALS

A. Provide the CO the aggregate gradation results for the 5/8” minus aggregate for bid item 02232A and for the aggregate for bid item 02232, for their approval prior to delivering material to the project site.

B. Provide the CO a weed free certification for the aggregate source.

PART 2 - PRODUCTS

2.1 AGGREGATE

A. Clean, hard, durable fragments or particles of crushed stone, crushed slag, or crushed or natural gravel. Materials that break up due to freeze-thaw or wet-dry cycling shall not be used.

PART 3 – EXECUTION

3.1 PLACING

A. If the required compacted depth of the aggregate base course exceeds six inches, place course in two or more layers of approximately equal thickness. The maximum compacted thickness of any one layer will not exceed six inches.

3.2 COMPACTION

A. Compact each layer with a jumping jack or plate compactor, provide three passes or until visual displacement has ceased, whichever is more. If necessary contractor shall provide adequate moisture for optimal compaction.

3.3 SURFACE FINISHING

A. Use a plate compactor for the final compacting of top surface base course. Water surface and evenly spread loose stones before final compacting. Make minimum of three complete passes. Correct soft spots developed during compacting.

02232-2

B. Compacted base course surface shall be smooth and free from waves and other irregularities. Unsatisfactory portions of base course shall be torn up, reworked, relaid, and rerolled, at no additional expense to Government.

3.4 TOLERANCES

A. Surface: Contractor will test finished surface of the base course with a 10-foot straightedge or other device. The variation between any two contacts with the surface shall not exceed one-half inch. Any areas not complying with these tolerances shall be reworked to obtain conformity.

B. Width: Plan dimension, plus or minus two inches.

C. Thickness: Plan dimension, plus or minus one-half inch.

3.5 MAINTENANCE

A. Maintain base course in a satisfactory condition until surfaced or until final acceptance.

END OF SECTION 02232

02245 - 1

GRADING

SECTION 02245

PART 1 - GENERAL

1.1 SUMMARY

A. Includes topsoil stripping, rock removal, cutting, filling, compaction and rough grading.

1.2 PROTECTION

A. During grading operations, and before stopping work for the day, blade unfinished areas being graded to provide a well-drained surface so water cannot collect in pools and puddles. Protect newly graded areas from traffic and erosion.

1.3 REFERENCES

A. Standard Moisture Density Test, AASHTO T-99, Method C or D.

PART 2 – PRODUCTS

2.1 FILLS AND EMBANKMENTS

A. Use excavated material, including rock up to 12 inches, in largest dimension. Material removed in stripping shall not be used. Material used must be clean and free from vegetation, pieces of timber, muck, and other foreign material.

1. Rocks over 6 inches in largest dimension not permitted in the top 2 feet of fill.

Rocks over 4 inches in largest dimension not permitted in the top 6 inches of fill.

2. No frozen material permitted in the fill.

2.2 TOPSOIL

A. Use material stripped from the cleared area. Remove large roots and stones over 2 inches in maximum dimension.

PART 3 – EXECUTION

3.1 TOPSOIL STRIPPING

A. Strip to a depth of 5 inches within the grading and excavation limits.

B. Remove without contamination with subsoil and stockpile on the site as directed by the Contracting Officer (CO).

3.2 CUTS, FILLS, AND EMBANKMENTS

A. Locations, lines, and grades as indicated on the drawings.

02245 - 2

B. Cohesive soils that have become hard or lumpy, or that have been piled and have become dry, shall be broken up and properly conditioned for moisture content for moisture content immediately before use in filling.

C. Surfaces on which compacted fill is to be placed shall be wetted or dried as may be required to obtain the compaction specified.

3.3 ROUGH GRADING

A. Uniformly smooth grade excavated and filled sections and adjacent transition areas.

B. Grade to 4 inches below finish grade elevation for all areas to be topsoiled.

C. Grade finished surface for other areas reasonably smooth, compacted, and free from irregular surface changes.

END OF SECTION 02245

07190 - 1

WATER PROOFING MEMBRANE

SECTION 07190

WATER PROOFING MEMBRANE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes water proofing membrane coatings for the following vertical and nontraffic horizontal surfaces:

1. Concrete (unpainted).

1.2 SUBMITTALS

A. Product Data: For Water Proofing Membrane coating and surface preparation.

B. Product test reports.

1.3 QUALITY ASSURANCE

A. Installer Qualifications: Follow manufacturer’s recomendation.

PART 2 - PRODUCTS

2.1 WATER PROOFING MEMBRANE

A. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following:

a. BASF.; MasterSeal HLM 5000, or equal.

B. Store and handle product according to the manufacturer’s recommendations.

PART 3 - EXECUTION

3.1 APPLICATION

A. Preparation: Prepare all surfaces for application according to the manufacturer’s rec-ommendations. Other product may be required. Use other surface preparation prod-ucts in accordance with the manufacturer’s recommendations.

B. Follow the manufacturer’s recommendation for providing a water proofing membrane for a wastewater storage vault. At a minimum provide to coats at the manufacturer’s recommended application rate.

END OF SECTION 07190

13901 - 1

REMOVING AND RESETTING CONCRETE TOILET AND VAULT

SECTION 13901

REMOVING AND RESETTING THE CONCRETE TOILET AND VAULT

PART 1 - GENERAL

1.1 SUMMARY

A. This section applies to the removing and replacing of eight (8) prefabricated concrete toilets.

1.2 SUBMITTALS

A. Lifting Plan: Prior to the beginning of work submit a lifting plan for each toilet building structure and vault that lift the concrete structures according to the original manufacture instruction. Provide the lifting points, necessary rigging, and minimum crane size necessary to perform the work. Also, provide brief description on how the safety of the contractor, contractor employee’s, FS employees, and the general public will be maintained during the lifting of the concrete structures.

B. Joint Sealing Plan: Prior to replacing the toilet structure submit the manufactures recommendations for proving a water tight seal between the top of the concrete vaults and the bottom of the concrete toilet structures. At a minimum the plan should include all product information and how the products are properly applied to ensure a water tight seal.

PART 2 – PRODUCTS

2.1 TEMPORARY REST ROOM FACILITIES

A. The Contractor shall provide at least two self-contained toilet units for each site while the campground toilets are out of service. The self-contained toilet units shall single-occupant units of chemical, aerated recirculation, or combustion type; vented; fully enclosed with a glass-fiber-reinforced polyester shell or similar nonabsorbent material.

2.2 SEWAGE PUMPING

A. Prior to removal of the concrete vaults the contractor shall obtain the service of a licensed and bonded sewage pumping/disposal company to pump the toilet vaults and remove all sewage off the Forest in a legal manner.

2.3 EXCAVATION, BEDDING MATERIALS AND BACKFILL

A. See specification 02223 “Structural Excavation” and 02232 “Aggregate Base Course” for excavation, bedding and backfill materials; and preparation for the vault and floor slab.

2.4 LIFT IN THE CONCRETE TOILET AND VAULT STRUCUTRE

13901 - 2

REMOVING AND RESETTING CONCRETE TOILET AND VAULT

A. The Contractor shall provide all necessary equipment to remove and replace the precast concrete toilets and panels at the designated site. Existing lifting logs, threaded anchors, etc., installed by the manufacturer shall be used by the Contractor to remove and replace the concrete toilet structures and concrete vaults.

B. It is the Contractor’s responsibility to remove and replace the concrete vaults and toilet structures in a safe manner. The safety of the contractor, contractor’s employees, FS employees, and the general public are the sole responsibility of the contract.

C. Any damaged incurred to the existing concrete toilet structures or concrete vaults is the responsibility of the contractor and shall be repair back to the original condition at the contractor’s expense.

2.5 REMOVAL OF EXISTING VAULT LINERS

A. The contractor shall remove the existing vault liners from each toilet off Forest in a legal manner. The CO may request documentation to certify that the existing vault liners were transported to and appropriate waste facility.

2.6 JOINT FILLERS AND CAULKING.

A. Provide a water tight seal between the top of the vault and the bottom of the toilet structure according to the original toilet manufactures recommendations.

END OF SECTION 13901

NORTH ZONE TOILET REPAIRS TC
NORTH ZONE TOILET REPAIRS
01010 -Summary of Work
1.
1.1 summary
A. Work for this project consists of removing and disposing sewage from vaults, off Forest in a legal manner; removing the toilet structure; excavating and removing toilet vault; removing and disposing existing vault liners, off Forest in a legal mann...
The trail head toilet at the Giant White Pine Campground will not be raised 1 foot like all the other toilets in the contract. The toilets close proximity to the parking area will not allow for an ADA ramp if the toilet were to be raised.
1.2 location
A. Giant White Pine Campground: Latah County: Palouse RD (T42N R3W Sec 11)
1.3 GENERAL SITE CONDITIONS AND WEATHER
A. The elevation of the site is approximately 2,000 feet above mean sea level. The construction site experiences heavy snowfall and extremely cold temperatures, with snow on the ground typically from mid-November through April.
B. In-depth water table surveys have not been performed; however, if water is encountered during excavation, the Contractor shall perform adequate dewatering to keep the excavation free from water and dispose of the water without damage to property.
1.4 USE OF PREMISES
A. General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. The project site area will be limited to the general areal in the toilet vicinity and not the campground a...
B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and employees.
C. Confine storage of materials to areas as approved by the CO.
D. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.
E. Preservation of Natural Features: Confines all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and plants and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with CO and remove agreed-on roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
1.5 camping
A. With approval by the North Fork and Palouse Ranger Districts, National Forest Service lands may be used by the Contractor for camping purposes. The camping site must be agreed to in advanced and a camping permit will be issued for the anticipated ...
1.6 construction sequence
A. There is no specified construction sequence or season for this project.
B. Depending on conditions, normal fire restrictions may apply to activities associated with this project.
1.7 Field verification
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
2.
3.
01025_Measurement and Payment
1.1 summary
A. The intent of this section is to explain, in general; what is and what is not included in a bid item; the limits or cut-off points where one bid item ends and another begins; and method of measurements and basis of payment for work items listed in ...
B. Work:
1. Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it, and carrying out all duties and obligations imposed by the contract on the Contractor.
C. Payment:
1. For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications, as shown on the drawings, and as staked in the field.
2. Measurement and payment for contract work shall be made only for and under those pay items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.
1.2 DETERMINATION OF QUANTITIES
A. The contractor shall perform, or cause to be performed, all measurement of quantities of materials incorporated into the work processes that are to be measured under the provisions of the contract.
B. Quantity Measurements:
1. The Contractor shall make all measurements for computation of quantities for all work items except those specified for payment by Contract Quantity (CQ) or Lump Sum Quantity (LSQ).
2. The contractor shall compute the quantities for periodic progress payments; the Contracting Officer shall compute the quantities for the final payment based on measurements taken by the Contractor.
3. All Contractor measurements are subject to verification.
4. The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities.
5. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.
C. The following measurements and calculations are used to determine contract quantities.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control ...
2. The average end area method shall be used to compute volumes of excavation or embankment. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehic...
3. Structures shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed. Pipes shall be measured along center of...
5. For aggregates measured for payment, the cubic yards shall be measure in place and compacted using the average end area method.
6. For standard manufactured items--such as fence, wire, plates, rolled shapes, pipe conduits--identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlle...
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
B. Cubic Yard: A measurement computed by one of the following methods:
1. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
2. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
3. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required wh...
C. Each: One complete unit, which may consist of one or more parts.
D. Linear Foot: Linear feet measured horizontally.
1.4 deFINItion of bid items
A. Definition of Bid Item No. 01510 MOBILIZATION
1. Description: Mobilization includes moving personnel, equipment, material, and incidentals to the project sites and performing all work necessary before beginning work at the project sites. Mobilization also includes the obtaining of permits, insur...
2. Measurement and payment: Measurement will be made on a lump sum basis. There are three project sites, therefore up to 50% of the mobilization is eligible for payment upon mobilizing to the first project site. The remaining mobilization will be sp...
B. Definition Bid Item No. 02222 STRUCUTRAL EXCAVATION
1. Description: Structural excavation will include any necessary excavation in order to remove the concrete vaults for bid item 13901. This bid item will also include any necessary backfill/embankment once the vaults are replace in order to provide a...
2. Measurements and Payment: Structural excavation will be paid on a lump sum basis. There are 7 vaults toilets that will be raised, therefore, 1/7 of the lump sum structural excavation contract price will be eligible for payment upon the completion ...
C. Definition Bid Item No. 02232 AGGREGATE BASE UNDER VAULT
1. Description: This bid item will include placing and compacting 5/8” to ¾ minus crushed aggregate in the excavated area under the vault prior to replacing the concrete vault according to bid item 13901. The intent is to raise each concrete vault to...
2. Measurements and Payment: This bid item will be measure based on contract quantities per cubic yard. There are 7 vaults toilets that will be raised, therefore, it is estimated that approximately 5 cubic yards per toilet will be required. Payment ...
D. Definition Bid Item No. 02232A 5/8” AGGREGATE AROUND THE TOILET WITH ADA RAMP
1. Description: This bid item will include placing and compacting 5/8” minus aggregate around the base of the toilet, placing and compacting a 5/8” minus aggregate base for the concrete approach pad, and placing and compacting 5/8” minus aggregate to ...
2. Measurements and Payment: This bid item will be measure based on contract quantities per cubic yard. There are 7 vaults toilets that will be raised, therefore, it is estimated that approximately 14 cubic yards per toilet will be required. Payment...
E. Definition Bid Item No. 03306 RELOACTING EXISTING CONCRETE PADS
1. Description: This bid item will include removing the existing concrete approach pads for each toilet and replacing them according to the Contract Drawings. In lieu of removing and replacing the existing concrete pad the contractor may demolish the...
2. Measurements and Payment: This bid item will be paid on a lump sum basis. There are 7 vaults toilets that will be raised, therefore, 1/7 of the lump sum Relocating Existing Concrete Pads contract price will be eligible for payment upon the complet...
F. Definition Bid Item No. 06260 SEEDING
1. Description: This bid item will include seeding all the disturbed grass areas, not covered by crushed aggregate under bid item 02232A, after the completion of all other bid items for each toilet. The seed mix will be provided by the USFS.
2. Measurements and Payment: This bid item will be paid on a lump sum basis. There are 8 vaults toilets, therefore, 1/8 of the lump sum structural excavation contract price will be eligible for payment upon the completion of each toilet.
G. Definition Bid Item No. 07190 WATER PROOFING MEMBRANE
1. Description: This bid item will include applying two coats of MasterSeal HLM 5000, or equal, to the interior floor and all interior sides of the existing concrete vaults. All preparation of concrete surfaces and any other necessary work required f...
2. Measurements and Payment: Measurement for this bid item will be based on Contract Quantities per square foot of Sonoshield HLM 5000, or equal, applied. One measured square foot of Sonoshield HLM 5000, or equal, applied will include both coats appl...
Measurements and Payment: This bid item will be paid on a lump sum basis. There are 8 vaults toilets, therefore, 1/8 of the lump sum structural excavation contract price will be eligible for payment upon the completion of each toilet.
H. Definition Bid Item No. 13901 REMOVING AND RESETTING CONCRETE VAULT TOILET
1. Description: This bid item will include all necessary sewage pumping of the concrete vault toilets. Sewage shall be remove off Forest in a legal manner. Also included in this bid item is removing and resetting the concrete toilet structure, and r...
2. Measurements and Payment: This bid item will be paid on a lump sum basis. There are 8 vaults toilets, therefore, 1/8 of the lump sum concrete vault toilet contract price will be eligible for payment upon the completion of each toilet.
2.
2.1 GENERAL
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
B. CONTARCT QUANTITIES (CQ)
1. These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey informa...
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, dra...
C. ACTUAL QUANTITIES (AQ)
1. These estimated quantities which are determined from actual measurements of completed work.
D. LUMP SUM QUANTITIES (LSQ)
1. These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
3.
3.1 GENERAL
A. Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed trail sections and to balance earthwo...
01140_Work Restrictions
1.
1.1 USE OF PREMISES
A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to the area around the vault toilet and any other immediately adjacent area needed to park equipment or store materials.
2. Government Occupancy: All reasonable accommodations will be made not to interfere with the occupancy of the campground outside of the immediate area of the vault toilets.
3. Driveways and Entrances: At the end of each work day or whenever possible keep campground roads and entrances serving camp sites clear and available to the public, Government employees, and emergency vehicles at all times. Do not use these areas ...
2.
3.
01330_Submittal Procedures
1.
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.