SF_30.doc
DOC document 55 KB Posted
- Solicitation number
- AG-02RC-S-14-0146
About this file
Amendment to solicitation Clarifies measurement and payment of base gravel. Addis specification for Facility Drainage Piping. Adds clauses for bid guarantee performance and payments bonds. If bid is over 150 000 bid guarantee and performance bonds will be required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Specifications-StampedWOcostest.pdf | ||
| gacpondsol.doc | DOC document | |
| FinalGACplans_Signed.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
| 1. CONTRACT ID CODE |
| PAGE OF PAGES |
| 1 |
| ? |
| 2. AMENDMENT/MODIFICATION NO. |
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE REQ. NO. |
| 5. PROJECT NO. (If applicable) |
| 1 |
| 09/08/2014 |
| 705989 |
| 6. ISSUED BY |
| CODE |
| 7. ADMINISTERED BY (If other than Item 6) |
| CODE |
Nez Perce-Clearwater National Forest 104 Airport Road
Grangeville, ID 83530
| 8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) |
| (X) |
| 9A. AMENDMENT OF SOLICITATION NO. |
| X |
| Ag-02RC-S-14-0146 |
9B. DATED (SEE ITEM 11)
08/08/2014
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
| CODE |
| FACILITY CODE |
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers X is extended, FORMCHECKBOX is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: 52.211.18 THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 1 and 2.
FORMCHECKBOX
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
FORMCHECKBOX
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
| x |
| D. OTHER (Specify type of modification and authority) |
Clarifies measurement and payment for base gravel, adds 221400 Facility Drainage Piping: Part 2.2 C, Piles and Fittings, and bid and performance bond clauses, extends bid closure date to 9/12/2014, 4 pm
E. IMPORTANT: Contractor FORMCHECKBOX is not, FORMCHECKBOX is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
1- Measurement and payment for base gravel shall be covered as mentioned under Specification 312316.16 Pond Area Excavation and Backfill. Disregard the measurement and payment of base gravel under 334713.13 HDPE liner section
2-Add Specification 221400 Facility Drainage Piping: Part 2.2 C, Pipes and Fittings: All pipe boot material and installation work to attach the proposed and existing pipes to the HDPE Liner as shown on Page 9 of the plans, including a pipe boot for the existing 4” plastic PVC shown on Page 4 of the plans entering the pond from the southwest corner, is incidental to Item 334713.13 HDPE Retention Pond Liner and Geotextile Fabric.
3-An offer guarantee (Bid Bond) IS REQUIRED if bid is over $150,000.00. Performance and Payment Bonds will be required of the successful offeror. (See Section I, FAR Clause 52.228-15.) No performance bond shall be required if the total awarded contract value is less than or equal to $150,000. (See Section I, FAR Clause 52.228-13.)
4-Adds clauses 52.228-1; 52.228-13; 52.228-14; 52.228-15; and 52.228-11;
| 15A. NAME AND TITLE OF SIGNER (Type or print) |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) |
Debbie A. Gerfen, CONTRACTING OFFICER
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
| /s/ Debbie A. Gerfen |
| 9/08/2014 |
(Signature of person authorized to sign)
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
| 30-105 |
| STANDARD FORM 30 (REV. 10-83) |
Prescribed by GSA
FAR (48 CFR) 53.243
File details come from the government source that posted it. Updated .