HighCorralSol.doc
DOC document 845 KB Posted
- Solicitation number
- AG-02RC-S-13-0077
About this file
High Corral Road Decommissioning Solicitation Package refer to page 2 for instruction on submitting quote. Map drawings and State of Idaho Worker's Comp form are uploaded as seperate documents
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PreSolitMap.pdf | ||
| workercomp.doc | DOC document | |
| Drawings_Signed_p1-8.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS |
| 1. REQUISITION NUMBER |
| PAGE 1 OF |
| OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30 |
| 86 |
| 2. CONTRACT NO. |
| 3. AWARD/EFFECTIVE |
| 4. ORDER NUMBER |
| 5. SOLICITATION NUMBER |
| 6. SOLICITATION ISSUE |
| DATE |
| AG-02RC-S-13-0077 |
| DATE |
06/18/13
| a. NAME |
| b. TELEPHONE NUMBER(No collect |
| 8. OFFER DUE DATE/ |
| 7. FOR SOLICITATION |
| Debbie Gerfen |
| calls) 208 983-4001 |
| LOCAL TIME |
INFORMATION CALL:
07/18/13 4:00 p.m.
| 9. ISSUED BY CODE |
| 10. THIS ACQUISITON IS FORMCHECKBOX |
UNRESTRICTED OR FORMCHECKBOX
SET ASIDE: _________% FOR
USDA – R1 IMAT
Nez Perce-Clearwater NF
FORMCHECKBOX
SMALL BUSINESS FORMCHECKBOX
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
X HUBZONE SMALL SMALL BUSINESS PROGRAM
104 Airport Road Grangeville, ID 83530
BUSINESS
FORMCHECKBOX
EDWOSB NAICS: 115310
FORMCHECKBOX
SERVICE-DISABLED
VETERAN-OWNED SIZE STANDARD: $7.0 Mill
SMALL BUSINESS FORMCHECKBOX
8(A)
11. DELIVERY FOR FOB DESTINATION UNLESS BLOCK IS MARKED
SEE SCHEDULE
| 12. DISCOUNT TERMS |
| FORMCHECKBOX |
13a. THIS CONTRACT IS A RATED
ORDER UNDER DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
x RFQ FORMCHECKBOX
IFB FORMCHECKBOX
RFP
15. DELIVER TO CODE
See Delivery Schedule
16. ADMINISTERED BY CODE
Same as Block 9
17a. CONTRACTOR/ CODE FACILITY
OFFEROR ADDRESS CODE
DUNS No: ___________________________________________ Tax Identification No.: __________________________________
Email Address: ________________________________________
18a. PAYMENT WILL BE MADE BY CODE
Submit invoice to COR for the work performed. Invoice will be reviewed and approved or rejected by the COR within 7 days of receipt of the invoice. Rejected invoices must be corrected and resubmitted. COR will forward the approved invoice to the CO who will submit to:
USDA, OCFO, COD, APB
P.O. Box 60075
New Orleans, LA 70160
TELEPHONE N0.
FORMCHECKBOX
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW
| OFFER |
| IS CHECKED |
FORMCHECKBOX
SEE ADDENDUM
| 19. |
| 20. |
| 21. |
| 22. |
| 23. |
| 24. |
| ITEM N0. |
| SCHEDULE OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| High Corral Road Decommissioning |
Nez Perce-Clearwater National Forest
Moose Creek Ranger District
Idaho County, Idaho
PLEASE PLACE YOUR QUOTE IN
SCHEDULE OF ITEMS, page(s) 3
FURNISHING QUOTATION:
See submission Criteria – Page 2, Place Solicitation Number on the front of your bid envelope.
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
FORMCHECKBOX
| 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA |
| FORMCHECKBOX |
| ARE |
| FORMCHECKBOX |
ARE NOT ATTACHED
FORMCHECKBOX
| 27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA |
| FORMCHECKBOX |
| ARE |
| FORMCHECKBOX |
ARE NOT ATTACHED
| 28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ |
| FORMCHECKBOX |
29. AWARD OF CONTRACT: REF. OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
| DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY |
| DATED .. YOUR OFFER ON SOLICITATION |
| ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED |
| (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE |
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS: ____________________
| 30a. SIGNATURE OF OFFEROR/CONTRACTOR |
| 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) |
| 30b. NAME AND TITLE OF SIGNER (Type or print) |
| 30c. DATE SIGNED |
| 31b. NAME OF CONTRACTING OFFICER (Type or print) |
| 31c. DATE SIGNED |
AUTHORIZED FOR LOCAL REPRODUCTION
STANDARD FORM 1449 (REV.2/2012)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA ‑ FAR (48 CFR) 53.212
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
23.
| Submission Criteria |
Items Required:
*Signed & Dated Standard Form 1449
*Signed & Dated Amendments (If Any Posted During Solicitation Period)
*Completed Schedule of Items
*Completed Provision 52.212-3 Offeror Certs & Reps
*AGAR 452.209 – 70, Alternate I (February 2012)
* Completed State of ID Cert. of Verification of Workers’ Comp. Insurance
*Technical Proposal – 1 Copy (See FAR 52.212-2, Evaluation – Commercial Items)
NOTE TO QUOTERS: Technical proposals are required for the evaluation of quotes.
DUNS:_____________________
Submission Methods:
1. Hard Copy Mail or Personal Delivery To:
Nez Perce National Forest S.O.
ATTN: Contracting
104 Airport Road
Grangeville, ID 83530
2. FAX 208-983-4098
**It is the responsibility of the Contractor to confirm timely receipt of their quotation by contacting Debbie Gerfen at (208) 983-4001. Electronic submittals are prohibited.
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED
FORMCHECKBOX
INSPECTED
FORMCHECKBOX
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ___________________________________
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
| 33. SHIP NUMBER |
| 34. VOUCHER NUMBER |
| 35. AMOUNT VERIFIED |
CORRECT FOR
| 36. PAYMENT |
| 37. CHECK NUMBER |
PARTIAL FINAL
FORMCHECKBOX
COMPLETE FORMCHECKBOX
PARTIAL FORMCHECKBOX
FINAL
| 38. S/R ACCOUNT NUMBER |
| 39. S/R VOUCHER NUMBER |
| 40. PAID BY |
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
42a. RECEIVED BY (Print)
| 41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER |
| 41c. DATE |
42b. RECEIVED AT (Location)
| 42c. DATE REC’D (YY/MM/DD) |
| 42d. TOTAL CONTAINERS |
STANDARD FORM 1449 (REV. 2/2012) BACK
SERVICES AND PRICES
Schedule of Items
HIGH CORRAL ROAD DECOMMISSIONING
Moose Creek Ranger District Nez Perce-Clearwater National Forests Idaho County, Idaho
B - SCHEDULE OF ITEMS
ITEM
NO.
DESCRIPTION
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
15101
Mobilization
Lump Sum
21103A
Roadway Obliteration, Method I
Mile
11.03
TOTAL BID PRICE ( ALL ITEMS ) $_____________________
62201
Hydraulic Excavator with Thumb*
Hour
XX
$_____XX___
*Contractor shall give a price per hour under Item 62201A Hydraulic Excavator with Thumb for additional work above the estimated quantities that is encountered during the contract performance. The Government does not guarantee any additional quantities will be purchased and in no event shall the Government order more than 8 hours of equipment rental under this item.
HUBZone Set-Aside. This acquisition has been set-aside for HUBZone Concerns (see FAR 52.219-3, Notice of Total HUBZone Set-Aside in Section I). Quoter must be a certified HUBZone Concern with the U.S. Small Business Administration. For information regarding the on-line application process, go to the following website at https://eweb1sp.sba.gov/hubzone/internet/index.cfm. This process can take 90 days or more to complete.
The Government contemplates award of a firm, fixed price contract resulting from this solicitation.
PROJECT DESCRIPTION AND LOCATION
Scope of Contract. This project is one of the implementation projects of the Collaborative Forest Landscape Restoration Project (CFLRP). The goal of the CFLRP project is to utilize collaborative, science based ecosystem restoration techniques to improve watershed function while encouraging ecological, economic and social sustainability with an emphasis on providing local employment opportunities. This contract requires road decommissioning, vegetation mastication and related work in compliance with its terms, specifications, and provisions. This includes furnishing labor, equipment, supervision, transportation, operating supplies, and incidentals
a. Description of Work. The High Corral Road Decommissioning project consists of decommissioning approximately 10-14 miles of road. Road decommissioning treatments range from drainage structure removal to strong outslopes and complete recontouring. Roadways will be decompacted as described in worklists. All fill material in draws will be removed and stream channels restored to natural grade and dimensions. All disturbed areas will be seeded. In addition, native forbs and shrubs will be transplanted from areas adjacent to the road. Grade control structures will be constructed in newly reconstructed stream channels.
b. Project Location. The project is located southeast of Kooskia, Idaho. From Kooskia travel south on Highway 13 for 11 miles to the junction of the Sally Ann Road. Turn left and travel 3.5 miles east to Clearwater, Idaho. Turn left on Main St and follow for 1 mile, then turn right onto Road 650. Follow road 650 to the FS boundary and the junction of Forest Road 1106. This is the beginning of the project area.
c. Pre-Bid Tour. No pre-bid tour.
d. Start Work. It is estimated that work will begin on July 29, 2013. The contractor shall give 14 days notice prior to starting any work. Contractor must have 75% or 8.0 miles decommissioned no later than October 31, 2013. All work must be completed by August 1, 2014.
e. Period of performance. (See page 12, FAR Clause 52.211-10)
FOREST SERVICE SPECIFICATIONS
Forest Service specifications are included as APPENDIX A of this solicitation.
DRAWINGS (Entitled “HIGH CORRAL ROAD DECOMMISSIONING”)
The following drawings are a part of this solicitation and any resulting contract:
| Title |
| Page of Pages |
| Title Sheet |
| 1 of 8 |
| Summary of Estimated Quantities |
| 2-3 of 8 |
| Road Decommissioning Details |
| 4-5 of 8 |
| Location Map |
| 6-8 of 8 |
| Road Decommissioning Work Lists (All Roads) |
| 1-32 of 32 |
CONTRACT ADMINISTRATION DATA
CONTRACTING OFFICER'S REPRESENTATIVE
The Contracting Officer will designate a representative, hereinafter referred to as the Contracting Officer's Representative (COR) or, alternatively, as the Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing and a copy of the designation will be furnished to the Contractor before or at the prework conference. The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term "Contracting Officer" as used throughout the Specifications, shall be interpreted to include the Contracting Officer's designated representative(s) acting within the limits of their delegation of authority.
FAR 52.236-4 Physical Data (APR 1984)
Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the plans and in the specifications are the result of site investigations by Forest Service specialists making physical determination based on surface observations.
(b) Weather Conditions. Normal snow conditions indicate a work season from approximately June 15 to October 15.
(c) Transportation Facilities. The project is located southeast of Kooskia, Idaho. From Kooskia travel south on Highway 13 for 11 miles to the junction of the Sally Ann Road. Turn left and travel 3.5 miles east to Clearwater, Idaho. Turn left on Main St and follow for 1 mile, then turn right onto Road 650. Follow road 650 to the FS boundry and the junction of Forest Road 1106. This is the beginning of the project area.
(d) Access roads and roads to be decommissioned may be overgrown and need to be cleared to gain access before use. Contractor is responsible for clearing and maintaining access roads during the project.
SPECIAL CONTRACT REQUIREMENTS
BARRICADES, WARNING SIGNS, AND OTHER DEVICES
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
…As a minimum, it is anticipated that the following type and number of signs will be required:
| Location |
| Designation |
| Quantity |
| At the beginning of each road being worked on. |
| ROAD CLOSED |
| 1 |
LANDSCAPE PRESERVATION
(a) Do not remove, deface, injure, or destroy trees, shrubs, lawn, or natural features not designated for treatment. This does not include access roads. Confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Retrieve material which falls outside of these limits and dispose of, or incorporate in the work.
Preserve the scenic and natural environment along this construction project.
(b) Do not allow objectionable material to enter any stream, river, lake, or other body of water. Retrieve material which falls in these areas and dispose of, or incorporate in the work, and repair damage to vegetation or structures outside the project limits.
(c) Do not operate equipment or otherwise disturb the natural vegetation and soil beyond the construction limits.
ENVIRONMENTAL PROTECTION
Prevention of Oil Spills.
The contractor is required to have a spill plan. The plan will contain a description of the specific hazardous materials, procedures, and spill containment that will be used, including inventory, storage, and handling.
All vehicles carrying fuel will have specific equipment and materials needed to contain or clean up any incidental spills at the project site.
All pumps and generators used in or near streams will have appropriate spill containment structures and/or absorbent pads in place during use.
When storage facilities for oil or oil products are on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or any other body of water. If a spill of petroleum product should occur in water, immediately notify the Contracting Officer and appropriate state agencies.
Fuel and service all equipment only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Meet all applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.
Contractor shall ensure that all personnel involved in handling and packaging the hazardous waste are trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures, and spills. Provide handling and personal protective equipment appropriate to ensure safe handling of the hazardous waste according to 29 CFR 1910.120). Notify the Forest Service of all hazardous material that may be brought onto the National Forest.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. The contractor must clean up spills or leaks in a manner that complies with Federal, state, and local laws and regulations and to the satisfaction of the CO. When necessary provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
Equipment Fuel/Oil Leakage.
All equipment used for instream work will be cleaned of external oil, grease, dirt and mud; and leaks repaired; prior to arriving at the project site. All equipment will be inspected by the Contracting Officer’s Representative before unloading at site. Any leaks or accumulations of grease will be corrected before entering streams or areas that drain directly to streams or wetlands.
Equipment used for in-stream or riparian work (including chainsaws and other hand power tools) will be fueled and serviced in an area approved by the CO. When not in use, vehicles will be stored in the designated staging area. The staging area should be in an area that will not deliver fuel, oil, etc. to streams.
Contractor is required to have a Spill Kit or equivalent that contains oil-absorbing floating booms, and other equipment such as pads and absorbent “peanuts” appropriate for the size of the stream, available on-site during all phases of construction. For small streams with few pools or slack water, booms may not be effective. Use pads and straw bales to anchor booms if necessary. Booms will be placed in a location that facilitates an immediate response to potential petroleum leakage.
NOXIOUS WEED CONTROL
In order to prevent the potential spread of noxious weeds into work areas, Contractor shall be required to use weed-free equipment.
The following is considered proof of weed-free equipment:
The Contractor will be required to clean all construction equipment prior to entry on to national forest land. This cleaning shall remove all dirt and plant parts and material that could carry noxious weed seeds into the work area. Only clean construction equipment inspected by the Forest Service will be allowed to operate within the work area. All subsequent move-ins of construction equipment shall be treated in the same manner as initial move-in. "Construction equipment" does not include pickup trucks and personal vehicles.
Straw/Hay Bales shall be certified as “Weed Free”. The source field shall be inspected and certified by the county extension agent from the county that the straw/hay is grown. Each shipment onto the forest shall be accompanied by a certification tag stating that it is weed free. The contractor shall furnish the forest service with a statement of certification.
FIRE CONTROL (FS 236-1)
(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.
(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or his employees, the Contractor when requested by the Contracting Officer shall place his employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.
Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area. An equitable adjustment in contract time may be made for this period.
(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract.
(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.
(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with a 4 BC or higher rating.
One - shovel, round point #0 lady or equal.
One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.
One - water container (at least 1-gallon capacity), not required with stationary equipment.
(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.
(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:
One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.
One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.
Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.
(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.
(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.
(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site when all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.
(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.
(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.
All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.
(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.
(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.
When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:
(i) All high fire risk operations could be terminated at 1300 local time.
(ii) All burning could be stopped, including debris burning fires.
(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.
(12) Pump and Trailer. NOT USED
(13) Burning. Before starting any open burning, the Contractor shall comply with the following:
(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.
(ii) Submit a burning permit from the District Ranger.
(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.
(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.
(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.
(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his discretion, prohibit all open burning for definite periods within specific areas of the National Forest.
CONTRACT CLAUSES
FAR 52.212-4 Contract Terms and Conditions - Commercial Items (FEB 2012)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights--
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Government-wide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to the Contract Disputes Act of 1978, as amended (41 U.S.C. 601-613). Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice. (1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized,) to the address designated in the contract to receive invoices. An invoice must include--
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, contract line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to be notified in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer - Central Contractor Registration, or 52.232-34, Payment by Electronic Funds Transfer - Other Than Central Contractor Registration), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected contract line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in Section 611 of the Contract Disputes Act of 1978 (Public Law 95-563), which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. 3701, et seq., Contract Work Hours and Safety Standards Act; 41 U.S.C. 51-58, Anti-Kickback Act of 1986; 41 U.S.C. 265 and 10 U.S.C. 2409 relating to whistleblower protections; Section 1553 of the American Recovery and Reinvestment Act of 2009 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. 423 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, and Compliance with Laws Unique to Government Contracts paragraphs of this clause.
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments.
(9) The specification.
(t) Central Contractor Registration (CCR). (This is now SAM – www.sam.gov)
(1) Unless exempted by an addendum to this contract, the Contractor is responsible during performance and through final payment of any contract for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(2)
(i) If a Contractor has legally changed its business name, "doing business as" name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in FAR Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to (A) change the name in the CCR database; (B) comply with the requirements of Subpart 42.12; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (t)(2)(i) of this clause, or fails to perform the agreement at paragraph (t)(2)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the "Suspension of Payment" paragraph of the electronic funds transfer (EFT) clause of this contract.
(3) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor's CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the "Suspension of payment" paragraph of the EFT clause of this contract.
(4) Offerors and Contractors may obtain information on registration and annual confirmation requirements via CCR accessed through http://www.acquisition.gov or by calling 1-888-227-2423 or 269-961-5757.
FAR 52.212-4 Addendum to - Contract Terms (FEB 2012) 52.242-14 Suspension of Work (APR 1984)
52.236-2
Differing Site Condition (APR 1984)
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed (b) prosecute the work diligently, and (c) 75% or 8.0 miles shall be completed by October 31, 2013. Complete the entire work ready for use not later than August 1, 2014. The time stated for completion shall include final cleanup of the premises.
FAR 52.211-18 Variation in Estimated Quantity (APR 1984)
Add the following:
Adjustment of contract prices as described in this section shall not apply to Section 622, Rental Equipment, Items: 62201A, Hydraulic Excavator with Thumb. All work under these items will be approved by the government prior to starting with no adjustment in contract unit price.
AGAR 452.209-71 Assurance Regarding Felony Conviction or Tax Delinquent Status for Corporate Applicants (FEB 2012) Alternate I (FEB 2012)
(a) This award is subject to the provisions contained in sections 433 and 434 of the Consolidated Appropriations Act, 2012 (P.L. No. 112-74), Division E, as amended and/or subsequently enacted, regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –
(1) does not have a tax delinquency, meaning that it is not subject to any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and
(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered suspension or debarment of the awardee, or such officer or agent, based on these convictions and/or tax delinquencies and determined that suspension or debarment is not necessary to protect the interests of the Government.
(b) If the awardee fails to comply with these provisions, the Forest Service may terminate this contract for default and may recover any funds the awardee has received in violation of sections 433 or 434, amended and/or subsequently enacted.
AGAR 452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful quoter is required. It will be scheduled and held within 30 days of the commencement of work. The conference will be held at Nez Perce National Forest Supervisor’s Office, 104 Airport Road, Grangeville, ID 83530.
FAR 52.232-99 Providing Accelerated Payment to Small Business Subcontractors (DEVIATION) (AUG 2012)
This clause implements the temporary policy provided by OMB Policy Memorandum M-12-16, Providing Prompt Payment to Small Business Subcontractors, dated July 11, 2012.
(a) Upon receipt of accelerated payments from the Government, the contractor is required to make accelerated payments to small business subcontractors to the maximum extent practicable after receipt of a proper invoice and all proper documentation from the small business subcontractor.
(b) Include the substance of this clause, including this paragraph (b), in all subcontracts with small business concerns.
(c) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.
AGAR 452.237-74 Key Personnel (FEB 1988)
(a) The Contractor shall assign to this contract the key personnel identified in the accepted technical proposal.
(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel FAR 52.236-7 Permits and Responsibilities (NOV 1991)
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor's fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
AGAR 452.211-74 Period of Performance (FEB 1988) AGAR 452.211-75 Effective Period of the Contract (FEB 1988) The effective period of this contract is from contract award through August 1, 2014.
Idaho Workers Compensation Law
(a) Prior to award of any contract subject to Idaho Workers' Compensation Laws, the contractor must provide a completed State of Idaho Certificate of Verification of Workers’ Compensation Insurance form to the Government. This form will be submitted to the Idaho Industrial Commission by the Government in order to assure that the contractor in line for award has the required worker’s compensation coverage or is exempt from the requirement for coverage.
(b) A copy of the State of Idaho Certificate of Verification of Workers' Compensation Insurance form has been provided for use in Section J and shall be completed and submitted as part of the quotation.
(c) This certificate of verification shall be fully executed by the contractor and signed by the Industrial Commission Compliance Officer prior to issuance of the Notice to Proceed.
Contractor Workforce Certification
Upon the request of the Contracting Officer, the Contractor…