AG-02RC-S-12-0096.doc

DOC document 498 KB Posted

Attached to
R1-IMAT, Nez Perce National Forest Federal contract opportunity
Solicitation number
AG-02RC-S-12-0096
Issued by
Department of Agriculture Forest Service R1-Northern Region

About this file

Solicitation package Little Slate Creek Culvert Replacement - see page 1 SF 18 for items to return for quote.

View the file

Other files for this federal contract opportunity

Other files attached to R1-IMAT, Nez Perce National Forest, newest first.
File Type Posted
SF30.doc DOC document
Slate NFSR 221 - MP 43.5 Culvert_FINAL PLANS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION RFQ thru FAC 2005-58A – 4/18/2012

AG-02RC-S-12-0096

Little Slate Creek Culvert Replacement

Salmon River RD, Nez Perce National Forest

REQUEST FOR QUOTATION

PAGE OF PAGES

(THIS IS NOT AN ORDER)
THIS RFQ
X
IS
IS NOT A HUB ZONE SET- ASIDE
1
76
1. REQUEST NO.
2. DATE ISSUED
3. REQUISITION/PURCHASE REQUEST NO.
4. CERT. FOR NAT.DEF.
RATING
AG-02RC-S-12-0096
06/01/12

UNDER BDSA REG. 2

AND/OR DMS REG. 1

5a. ISSUED BY
6. DELIVER BY (Date)

USDA – Forest Service

R1 IMAT Nez Perce-Clearwater National Forest 104 Airport Road Grangeville, ID 83530 See Contract Time

5b. FOR INFORMATION CALL (NO COLLECT CALLS)
7. DELIVERY

FOB DESTINATION

NAME
TELEPHONE NUMBER
X
OTHER (See Schedule)
AREA CODE
NUMBER
9. DESTINATION
Debbie Gerfen
208
983-4001
a. NAME OF CONSIGNEE
8. TO:
Section C - Location & Description
a. NAME
b. COMPANY
b. STREET ADDRESS
c. STREET ADDRESS
c. CITY
d. CITY
e. STATE
f. ZIP CODE
d. STATE
e. ZIP CODE
10. PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS (Date)
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5a. This request does not commit the Government to pay any costs incurred in the preparation of the
07/02/12 4:00 pm PT
submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NO.
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(a)
(b)
(c)
(d)
(e)
(f)

LittleSlate Creek Culvert Replacement, Salmon River Ranger District, Nez Perce National Forest, Idaho County, Idaho.

PLEASE PLACE YOUR QUOTE IN SECTION B- SCHEDULE OF ITEMS

FURNISHING QUOTATION: Complete Standard Form 18, Section B, Section K, Technical Proposal, and Requirements of Section L as your quote. Return to the address shown in Block 5a. Please place “Solicitation No. AG-02RC-S-12-0096” on the envelope.

a. 10 CALENDAR DAYS (%)
b. 20 CALENDAR DAYS
c. 30 CALENDAR DAYS
d. CALENDAR DAYS

12. DISCOUNT FOR PROMPT PAYMENT

(%)
(%)
NUMBER
PERCENTAGE
NOTE: Additional provisions and representations
X
are

are not attached.

13. NAME AND ADDRESS OF QUOTER
14. SIGNATURE OF PERSON AUTHORIZED TO
15. DATE OF
a. NAME OF QUOTER
SIGN QUOTATION
QUOTATION

DUNS NO. _____________ TIN NO.___________________

b. STREET ADDRESS
16. SIGNER
a. NAME (Type or print)
b. TELEPHONE

c. COUNTY

AREA CODE

d. CITY
e. STATE
f. ZIP CODE
c. TITLE (Type or Print)
NUMBER

NSN 7540-01-152-8084

Previous edition not usable

18-121
STANDARD FORM 18 (Rev. 6-95)

Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES

Little Slate Creek Culvert Replacement Salmon River Ranger District

Nez Perce National Forest

Idaho County, Idaho

B-1 SCHEDULE OF ITEMS

Pay Item Number
Description
Method of

Meas.

Pay Unit
Total

Quantities

Unit Price
Amount
15101
Mobilization
LSQ
LS
1
$__________
$__________
15201
Construction staking
LSQ
LS
1
$__________
$__________
15713
Soil Erosion & Pollution Control
LSQ
LS
1
$__________
$__________
20102
Clearing and grubbing
LSQ
LS
1
$__________
$__________
20301
Removal of existing 36" corrugated steel culvert
LSQ
Ea.
1
$__________
$__________
20806
Structure Excavation
LSQ
LS
1
$__________
$__________
25101A
Placed riprap, class 1 machine placed (commercial source)
DQ
CY
45
$__________
$__________
25101B
Placed riprap, class 4 machine placed (commercial source)
DQ
CY
55
$__________
$__________
25150
Grade control structure, rock weir
DQ
Ea.
7
$__________
$__________
25151
Fish rest stop rock
DQ
Ea.
30
$__________
$__________
27201
Geocell foundation stabilization
AQ
SY
100
$__________
$__________
30801
Crushed aggregate, surfacing, compaction method 1 (government source)
DQ
CY
100
$__________
$__________
553A01
Precast concrete member, culvert footing
LSQ
LS
1
$__________
$__________
60304
9' span, 4'-8 1/2" rise, structural plate arch, 0.111" thickness
LSQ
LF
98
$__________
$__________
62201A
Equipment rental, hydraulic excavator with thumb
AQ
Hour
8
$__________
$__________
62201B
Equipment rental, large dump truck
AQ
Hour
8
$__________
$__________
62503
Seeding, dry method
DQ
LS
1
$__________
$__________
63501
Temporary traffic control
LSQ
LS
1
$__________
$__________

Total (All Items) $______________________________

* Designated Method of Measurement: DQ=Design Quantity; AQ= Actual Quantity; LSQ=Lump Sum Quantity VQ=Vehicle Quantity

B-2 - NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted. The above pay items are contract quantities unless noted.

B- 3 Quote on all items. Only quotes to the nearest cent will be accepted.

B- 4 Written Acceptance Any contract resulting from this solicitation will require written acceptance within 10 days of receipt by the Contractor.

B- 5 Basis of Award

One award will be made. Offer of award will be made to the Quoter whose quote, as determined by the Contracting Officer, provides the best value to the Government, considering but not limited to, such factors as price, past performance, and capability to accomplish this type of work. The Technical Proposal will be used as part of this evaluation.

Use the following for your Technical Proposal:

Technical Proposal

1. Record of past performance of the firm, supervisor, and employees: List and briefly describe previous contracts of a similar nature completed within the last 5 years, and supply names and current phone numbers of those contacts.

2. Production Schedule (work plan): Address who, what, where, when and how you plan to do the work, from beginning to end as stated in the Statement of Work and Specifications. Include both overall time frame and time frames for each phase of construction as required. Include erosion control measures and safety for employees and traffic. Briefly summarize any proposed changes to the plans or specifications that would prove beneficial from a cost or technical standpoint and provide at least equal performance and appearance.

3. Experience and qualifications of the supervisor, lead employees, and proposed subcontractors: For each, list relevant licenses, certifications and experience in the type of work to be done under this contract. If none, list similar projects where experience could be applied to this kind of job and briefly explain how the experience relates to the type of work to be done under this contract.

PART I - THE SCHEDULE

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C-1 - PROJECT DESCRIPTION AND LOCATION

Description of Work: The intent of the contract is to remove and replace an existing corrugated steel pipe at a tributary to Little Slate Creek.

This project includes removing and disposing an existing culvert, structure excavation, backfilling, compacting, furnishing and installing a structural plate arch culvert, furnishing and installing precast footings, riprap placement, and hauling and placing roadway surfacing. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

(b) Project Location Little Slate Creek at Road No. 221, MP 43.5 in the Nez Perce National Forest. The structure is located in the Salmon River Ranger District in Section 10, T. 25 N., R. 3 E., Idaho County, Idaho.

(c) Price Range The Government’s estimate for this project is between $100,000 and $250,000.

(d) Pre-Bid Tour None

(e) Pre-Bid Conference None

(f) Start Work The count of contract time shall begin on the date of award and the work shall proceed in accordance with the Contractor’s approved work schedule.

(g) Period of Performance (See Part I, Section F, Clause 52.212-3)

(h) Government-Furnished Property None (Also see Section I, FAR 52.245-4)

C-2 - DRAWINGS (entitled “Tributary to Little Slate Creek Culvert Replacement”) The following drawings are a part of this solicitation and any resulting contract:

TITLE OR NUMBER
SHEETS
TITLE SHEET
1
SUMMARY OF QUANTITIES & GENERAL NOTES
2
ROAD TYPICAL SECTION & LAYOUT POINTS
3
ROAD PLAN & PROFILE
4
STREAM DIVERSION PLAN
5
CULVERT GENERAL LAYOUT
6
FOUNDATION DETAILS
7
PRECAST FOOTING DETAILS
8
STREAM DETAILS
9
ROAD CROSS SECTIONS
XS1-XS3

C-3 - STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS FP-03 U.S. Customary Units (U.S. DEPARTMENT OF TRANSPORTATION, Federal Highway Administration) (2003)

Standard Specifications for Construction of Roads & Bridges on Federal Highway Projects (FP-03) are included by reference only. The requirements contained in these Standard Specifications are hereby made a part of this solicitation and any resultant contract.

Copies of the Standard Specifications for Construction of Roads & Bridges on Federal Highway Projects (FP-03) are available in PDF format on the Western Federal Lands Highway Division website at www.wfl.fha.dot.gov/design/specs/fp03.htm.

C-4 - SUPPLEMENTAL PROJECT SPECIFICATIONS

The Supplemental Project Specifications listed in the Supplemental Specification List are applicable to this contract and are physically included in this section (C).

NOTE THAT THE SPECIFICATION LIST INCLUDES THE MAJOR SPECIFICATIONS APPLICABLE TO THIS PROJECT. OTHER SPECIFICATIONS REFERRED TO WITHIN THESE SPECIFICATIONS (EVEN THOUGH NOT SPECIFICALLY LISTED HEREIN) ARE ALSO FULLY APPLICABLE TO THIS REQUEST FOR PROPOSALS AND ANY RESULTANT CONTRACT.

SUPPLEMENTAL SPECIFICATION LIST

Tributary to Little Slate Creek Culvert Replacement Nez Perce National Forest

SPEC. No.
SPECIFICATION TITLE
FSSS 101
Terms, Format, and Definitions
FSSS 102
Bid, Award, and Execution of Contract
FSSS 103
Scope of Work
FSSS 104
Control of Work
FSSS 105
Control of Materials
FSSS 106
Acceptance of Work
FSSS 107
Legal Relations and Responsibility to the Public
FSSS 108
Prosecution and Progress
FSSS 109
Measurement & Payment
FSSS 151
Mobilization
FSSS 152
Construction Survey and Staking
FSSS 153
Contractor Quality Control
FSSS 155
Schedules for Construction Contracts
FSSS 156
Public Traffic
FSSS 157
Soil Erosion Control
FSSS 203
Removal of Structures and Obstructions
FSSS 208
Structure Excavation and Backfill for Selected Major Structures
FSSS 251
Riprap
FSSS 272
Geocell
FSSS 308
Minor Crushed Aggregate
FSSS 553A
Precast Concrete Structures
FSSS 603
Structural Plate Structures
FSSS 622
Rental Equipment
FSSS 625
Turf Establishment
FSSS 725
Miscellaneous Material

Table of Contents 8Table of Contents

Preface 101 - Terms, Format, and Definitions

101.01 Meaning of Terms

101.03 Abbreviations.

101.04 Definitions.

102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract 103 - Scope of Work 104 - Control of Work Deletions

104.06 Use of Roads by Contractor

105 - Control of Material

105.02 Material Sources

105.05 Use of Material Found in the Work.

106 - Acceptance of Work

106.07 Delete

107 - Legal Relations and Responsibility to the Public

107.02 Protection and Restoration of Property and Landscape.

107.05 Responsibility for Damage Claims.

107.06 Contractor’s Responsibility for Work.

107.09 Legal Relationship of the Parties.

107.10 Environmental Protection.

108 - Prosecution and Progress 108 Delete.

109 - Measurement and Payment 109 Deletions

109.02 Measurement Terms and Definitions.

151 - Mobilization 152 – Construction Survey and Staking 152.01(a) Personnel.

153 – Contractor Quality Control

153.07. Project Submittals

155 - Schedules for Construction Contracts 155 Delete.

156 - Public Traffic

156.03 Accommodating Traffic During Work.

156.08 Traffic and Safety Supervisor.

157 - Soil Erosion Control

157.02 Materials

157.03 General.

157.08 Water Crossings.

203 - Removal of Structures and Obstructions

203.05 Disposing of Material.

208 - Structure Excavation and Backfill for Selected Major Structures

208.04 General.

251 - Riprap

251.01 Description

251.04(a) Grade Control Structure (Rock Weir) 251.04(b) Fish Rest Stop Rock

251.07 Acceptance

272 - Geocell 308 - Minor Crushed Aggregate 553A – Precast Concrete Structures 603 - Structural Plate Structures

603.03 General.

603.05 Acceptance.

622 - Rental Equipment

622.02 Rental Equipment

625 – Turf Establishment

625.03 General.

625.04 Preparing Seedbed.

625.05 Watering

625.06 Fertilizing.

625.07 Seeding.

625.08 Mulching.

625.09 Protecting and Caring for Seeded Areas.

625.11 Measurement

725 - Miscellaneous Material

725.40 High-Strength Nonshrink Grout

725.41 Mortar

Preface Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

101 - Terms, Format, and Definitions

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp
Milepost
ppm
Part Per Million

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

103 - Scope of Work

103.01 Intent of Contract. Delete this subsection and replace with the following:

Tributary to Little Slate Creek 221-43.5

The intent of the contract is to remove and replace an existing corrugated steel pipe at a tributary to Little Slate Creek at Road No. 221, MP 43.5 in the Nez Perce National Forest. The structure is located in the Salmon River Ranger District in Section 10, T. 25 N., R. 3 E., Idaho County, Idaho.

This project includes removing and disposing an existing culvert, structure excavation, backfilling, compacting, furnishing and installing a structural plate arch culvert, furnishing and installing precast footings, riprap placement, and hauling and placing roadway surfacing. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

Delete the remaining subsections in this Section.

104 - Control of Work

Deletions

Delete Sections 104.02, and 104.04.

Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material

105.02 Material Sources

Add the following before the first paragraph.

Sources have been designated for this project as follows:

Riprap Source – Contractor Furnished – There is no Government source for riprap on this project.

Crushed Aggregate Source – Government Furnished – A Government source for crushed aggregate surfacing is located at the Adams Creek pit located in Section 26, T27N, R3E on Forest Road 221.

Waste Site – Government Furnished – A waste site for unsuitable or excess material, if necessary, will be identified by the CO within 1 mile of the project site. All other materials designated for removal and disposal must be disposed of away from Forest Lands.

Add the following to section (b) Contractor-located sources.

Prior to any pit development or use of materials, the Contractor shall provide to the CO a State certification that the pit site is free of noxious weed as listed on the "All States Noxious Weeds List”.

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

106 - Acceptance of Work

106.07 Delete

Delete subsection 106.07.

107 - Legal Relations and Responsibility to the Public

107.02 Protection and Restoration of Property and Landscape.

Add the following:

Work within the wetted perimeter of streams will be allowed only as specified in the approved 124 permit.

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

· Exact time and location of spill including a description of the area involved.

· Containment procedures.

· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 - Prosecution and Progress

108 Delete.

Delete Section 108 in its entirety.

109 - Measurement and Payment 109 Deletions Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

(q) Actual Quantity (AQ). Actual quantities are determined from measurements of completed work.

151 - Mobilization

151.01 Description

Add the following at the end of the last sentence:

Work also includes cleaning of all equipment used at the project site. Clean all construction equipment prior to entry on the project site. Remove all dirt, plant parts and material that may carry noxious weed seeds into the area. Only construction equipment inspected by the Forest Service will be allowed to operate within the project area. The contractor must provide a minimum of 24 hours notification prior to inspection. All inspections shall be conducted off Forest Service lands. Treat subsequent move-ins of equipment the same as the initial move-in. Clean truck beds and dump boxes hauling to the project site prior to entering the work area.

152 – Construction Survey and Staking 152.01(a) Personnel.

Add the following:

Conduct all construction staking under the direction of a licensed professional engineer or land surveyor who is closely associated and familiar with construction staking.

153 – Contractor Quality Control Add the following.

153.07. Project Submittals

At a minimum the contractor shall provide project submittals as shown on the below Submittal Log. Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.

Submittal Log

Log No.
Incidental to

Pay Item(s)

Description of Submittal
Type of Submittal
Requirement found in Specification No.

/Drawings Additional Specification References

1
151
Weed Free Material Source Certification
Material

Certification FSSS 105.02(b)

2
151
Hazardous Spill Plan
Plan
FSSS 107.10
3
151
Contractor Quality Control Plan
Plan
153.02
552.09
4
151
Traffic Control Plan
Plan
FSSS 156.03
5
157
Soil Erosion and Pollution Control Plan
Plan
FSSS 157.03
6
208
Material Moisture/Density Testing
Test Results
Table 208-1
106
7
208
Structural Backfill Compaction Testing
Test Results
208.11, 208.12
106
8
251
Riprap
Material

Certification

251.07
106, 705, Drawings
9
272
Geocell Abutment Stabilization
Material

Certification

272.06
106,

FSSS 736, Drawings

10
272
Geocell: Course Granular Backfill
Material

Certification

272.06
106,

FSSS 703.03, Drawings

11
272
Geocell: Geotextile – Type II
Material

Certification

272.06
106, 714, Drawings
12
553A
Precast Concrete Structures
Shop Drawing
FSSS 553A.03
104, 552, 553, 554
13
553A
Precast Concrete Structures: Testing
Test Results
FSSS 553A.06
106, 554, 562
14
553, 553A
Reinforcing Steel
Order List
554.03
553, 553A, 709, Drawings
15
553
Miscellaneous Material: Grout
Material

Certification

FSSS 725.40
553, Drawings
16
553
Miscellaneous Material: Grout
Product

Approval

FSSS 725.40
553, Drawings
17
553
Reinforcing Steel and Wire Rope
Material

Certification

709.01
553, Drawings
18
603
Structural Plate Structures
Material

Certification

603.04
106, Drawings
19
622
Equipment Rental
Equipment

Approval

FSSS 622.02

20
625
Fertilizer & Mulch
Material

Certification

625.10
106,

FSSS 625, 713

155 - Schedules for Construction Contracts 155 Delete.

Delete Section 155 in its entirety.

156 - Public Traffic

156.03 Accommodating Traffic During Work.

Delete the first paragraph and replace with the following:

Accommodate traffic according to the requirements set forth below, MUTCD, and Section 635 of FP-03. Submit a traffic control plan for acceptance at least 7 days before intended use.

Add the following project specific requirements:

The contractor will be allowed to close through traffic on Forest Road No. 221 during construction under the schedule specified in the contract documents.

Give the CO at least 21 days advance written notice prior to any road closure period to allow public notice of the closure by the Forest Service.

As a part of the sign plan for the culvert replacement, the Contractor will be required to furnish and install advance road closed signs at the junction of Road 221 and Road 394 both north and south of the project or as directed by the CO.

Delete the following from the last sentence of the last paragraph:

according to Subsection 106.07(b)

156.08 Traffic and Safety Supervisor.

Delete this subsection in its entirety.

157 - Soil Erosion Control

157.02 Materials

Add the following:

Provide bales, wattles, logs and rolls from a certified noxious weed free source.

157.03 General.

Delete the first two paragraphs and replace with the following:

Submit an Erosion Control Plan detailing permanent and temporary control measures to minimize erosion and sedimentation during and after construction in accordance with the plans and storm water permits. Do not modify the type, size, or location of any control or practice without approval. Submit the erosion control plan proposal at least 7 days before operations begin to the CO for approval.

Reflect in the Erosion Control Plan special concerns and measures necessary to protect resources and government improvements. Include:

(a) The construction activities and sequence of implementation relating to specific erosion control measures.

(b) The location and type of permanent controls to be implemented during construction.

(c) The location and type of temporary controls to be implemented during construction.

(d) For work in stream channels with running water a detailed dewatering plan.

(e) For work in stream channels without flowing water describe level of ground and vegetative disturbance and measures to reduce potential sediment delivery.

(f) Description of the monitoring plan.

Add the following to the third paragraph:

Upon completion of construction at the site, remove all temporary erosion control devices, dewatering materials and equipment from Government property.

157.08 Water Crossings.

Add the following:

At any channel crossing where there is running water, dewater by rerouting water flow around the site before and during excavation and embankment operations.

203 - Removal of Structures and Obstructions

203.05 Disposing of Material.

Modify this subsection as follows:

(a) Remove from project. Add the following:

All materials designated for removal become the property of the Contractor and are to be disposed of by removing off of Forest Service Lands in accordance with all local, state and federal requirements.

(b) Burn. Delete this section.

(c) Bury. Delete this section.

Add the following:

(e) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes or scatter as directed by the CO to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets. All slash material not suitable for embankment slopes shall be disposed off Forest Service Lands in accordance with all local, state and federal requirements or as approved by the CO.

208 - Structure Excavation and Backfill for Selected Major Structures

208.04 General.

Add the following:

Use all suitable material in the construction of the roadway embankment and for structural backfill. Field drain and dry excessively wet material that is otherwise suitable for embankment before placement. Place and shape unsuitable or excess material at designated sites shown on the drawings or as directed by the CO.

251 – Riprap

251.01 Description

Delete the first sentence and add the following:

This work consists of furnishing, hauling, and placing of riprap for bank protection, slope protection, drainage structures, rock weirs, erosion control, and other features shown on the plans.

Add the following:

251.04(a) Grade Control Structure (Rock Weir) Furnish riprap in accordance with FSSS 105 and as shown on the drawings. Place or rearrange individual rocks by mechanical methods to obtain a shape as shown on the drawings.

Fill all voids left during placement of grade control structures adjacent to concrete footings or corrugate pipes with excess structural excavation material.

All grade control structure locations must be approved by the CO prior to excavation or placement of rock.

251.04(b) Fish Rest Stop Rock Furnish sound, durable rock that is native to the vicinity of the work or is similar in texture and color to the native rock and has been proven satisfactory for the intended use.

Furnish rocks according to dimensions as shown on the plans.

251.07 Acceptance

Delete the fourth sentence and add the following:

Structure excavation and backfill will be evaluated under Section 208.

272 - Geocell

Description

272.01

This work consists of constructing geocell abutment stabilization at each abutment using a cellular confinement system such as Presto Geoweb Cellular Confinement System or Webtec TerraCell in accordance with the plans and manufacturers recommendations.

Materials

272.02 Requirements. Ensure that material conforms to specifications in the following subsections:

Granular Backfill Type (a)

703.03

Geotextile, Type II (A, B, C)

714.01

Geocell

Construction Requirements

272.03 General. Perform the work specified in Section 208 or 209. Use ditches, grading or similar methods to prevent surface runoff that may occur during inclement weather from ponding in the foundation excavation.

272.04 Storage and Handling of Material. During shipment and storage, wrap geotextile materials in heavy-duty protective covering. Protect the material from mud, soil, dust, debris and sunlight prior to installation.

272.05 Geotextile Installation. Place the geotextile according to Section 207. Have the surface approved by the CO prior to placing geotextile.

Sew or overlap adjacent strips a minimum of 12” at joints. Insert securing pins through both strips of overlapped geotextile at minimum intervals of 3 feet, but no closer than 2 inches to each edge, to prevent the geotextile from being displaced.

Have the installed geotextile approved by the CO prior to setting the geocells.

272.06 Geocell Installation. Furnish the CO with product literature and certification as required in Section 106.03 for review and approval 7 days prior to installation. When requested by the CO, furnish a sample of the geocell from each lot for verification testing.

Place the geocell sections directly on the prepared subgrade. Expand the geocell sections into position at the grades and lines as shown on the plans. Hold the expanded geocell sections with suitable “stretcher frames”, steel stakes driven inside selected outer cell walls, or other similar methods as allowed by the manufacturer prior to filling. Ensure that the individual cells have expanded to the minimum dimensions required by the manufacturer. If necessary field cut sections as per the manufacturer’s recommendations to the lines shown on the plans.

Connect geocell panels in accordance with the manufacturer’s recommendations.

272.07 Infill Placement. Furnish the CO with the manufacturer’s specific recommendations for backfilling 7 days prior to placement of the geocells.

Place coarse granular backfill meeting Subsection 703.03 into the expanded cells with equipment appropriate for the site conditions such as a backhoe or a front-end loader. Do not drop infill material more than 3 feet to avoid damage or displacement of the cell walls.

Overfill the geocell cells and level to a minimum of 2 inches above the top of the cell walls. A front-end loader may be used to place the infill provided that it only traffics above geocell sections that have been filled and covered with the minimum 2 inches of additional material. Compact the infill material with a vibratory plate compacter. Operate compaction equipment over the full width of the geocell. Make at least three complete passes or until visible deformation of the infill ceases. Grade the surface to be ½ inch above the top of the cells. Ensure that the cell walls are not exposed after fine grading is completed.

Use the geocell manufacturer’s specific recommendations for backfilling if they are more stringent than stated above.

272.08 Acceptance. Geotextile will be evaluated under Subsections 106.02 and 714.01.

Material for geocell will be evaluated under Subsections 106.2 and 106.03.

Granular backfill material will be evaluated under Section 106.02 and 106.04.

Measurement

272.09 Method. Measure the items listed in the bid schedule according to Subsection 109.02 and the following.

Measure geocell by the square yard in place, exclusive of wastage.

Payment

272.10 Basis. The accepted quantities will be paid for at the contract price per unit of measurement for the Section 272 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

The cost for furnishing and placing the granular backfill required in Sections 207, 208, and 209 for geocell infill is incidental to this pay item and no separate payment will be made.

The cost for furnishing and placing geotextile for the geocell installation is incidental to this pay item and no separate payment will be made.

308 - Minor Crushed Aggregate Delete section 308 in its entirety and replace with the following:

Description

308.01 This work consists of placing Government furnished aggregate or furnishing and placing crushed aggregate for bedding, backfill and roadway aggregate course.

Material

308.02 Conform to the following Subsections:

Crushed aggregate

703.06

Water

725.01

Construction Requirements

308.03 Preparing Surface. Prepare the roadway surface on which aggregate course is placed as shown on the plans.

308.04 Placing Crushed Aggregate.

(a) Roadway aggregate. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for compaction. Spread and shape the mixture on the prepared surface in a uniform layer.

Do not place the mixture in a layer exceeding 6 inches in compacted thickness. When more than one layer is necessary, compact each layer according to Subsection 308.05(a) before placing the next layer.

(b) Bedding and backfill aggregate. Place and shape the mixture in layers that, when compacted, do not exceed 6 inches in depth.

308.05 Compacting and Finishing Crushed Aggregate.

(a) Roadway aggregate. Adjust the moisture content of the material to a level suitable for compaction. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases. Make at least three complete passes.

Blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface.

Ensure that the thickness and width of the compacted aggregate conform to the dimensions SHOWN ON THE DRAWINGS, and that measurements on the compacted aggregate meet the following criteria:

(a) The maximum variation from the compacted specified thickness is ½ inch.

(b) The compacted thickness is not consistently above or below the specified thickness and the average thickness of 4 random measurements for any ½ mile of road segment is within + ¼ inch of the specified thickness.

(c) The maximum variation from the specified width will not exceed +12 inches at any point.

(d) The compacted width is not consistently above the specified width and the average of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width.

(b) Bedding and backfill aggregate. Compact in 6 inch lifts by using a Forest Service approved mechanical compactor until no visible deformation is observed over the entire area of aggregate.

308.06 Acceptance. Crushed aggregate will be evaluated under Subsections 106.02 and 106.03. Furnish a production certification including gradation and quality properties for each source.

Construction of roadway aggregate courses will be evaluated under Subsections 106.02 and 106.04. Compaction will be evaluated under Section 106.04.

Placement of bedding and backfill aggregate will be evaluated under Subsection 106.02 and Section 209.

Preparation of the surfaces on which crushed aggregate is placed will be evaluated under Section 303 and 209 as applicable.

Measurement

308.07 Measure the Section 308 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

Measure crushed aggregate by the cubic yard in-place on the road.

Measure width horizontally to include the top of aggregate width including designed widenings.

Measure the length horizontally along the centerline of the roadway.

Payment

308.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 308 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

553A – Precast Concrete Structures

Description

553A.01 Work. Construct precast concrete members. In addition, manufacture, test materials for, transport, store, and install all precast concrete portions except piling, and perform all necessary grouting, welding, or other connections. Furnish precast concrete members complete and in place, including all concrete reinforcing steel and incidentals connected therewith.

Materials

553A.02 Requirements. Provide materials that meet the requirements specified in the following subsections:

High-Strength Nonshrink Grout ……………………………… 725.40

Mortar ………………………………………………………… 725.40

Reinforcing Steel ……………………………………………… 709.01

Sealants, Fillers, Seals, & Sleeves …………………………….. 712.01

Structural Concrete ……………………………………………. 552

Structural Steel ………………………………………………… 717.01

Provide precast concrete members of the size, shape, strength, air content, and finish that are SHOWN ON THE DRAWINGS. Precast concrete members must be manufactured by a plant with the following certifications:

Precast/Prestressed Concrete Institute (PCI)

Bridge 1, Precast Bridge Products (no prestressed reinforcing)

Commercial 1, Precast Concrete Products (no prestressed reinforcing)

National Precast Concrete Association (NPCA)

Precast

Submit a copy of the transmittal letter of the latest PCI or NPCA inspection/certification with the shop drawings.

In lieu of PCI/NPCA certification, Contractor shall retain a professional engineer to provide quality assurance for the work by inspecting and certifying in writing the concrete members are constructed in accordance to the specification and shall include but not limited to:

a) Shop drawing review.

b) Concrete member dimensions.

c) Concrete mix design.

d) Aggregate sources and test results.

e) Steel reinforcing placement.

f) Concrete curing and strength test results.

g) Concrete material certifications.

h) Placement mixing, delivery and sampling.

Certification of the above shall be received by the CO prior to shipment and installation at the job site.

Perform all sampling, testing, and inspection necessary to ensure quality control of the component materials and the concrete. Sample and test for quality control and acceptance testing in accordance with the AASHTO or ASTM test methods prescribed in Section 552.

Maintain adequate records of all inspections and tests. Keep records that indicate the nature and number of observations made, the number and type of deficiencies found, the quantities approved and rejected, and the nature of any corrective action taken.

Construction 553A.03 Performance. Construct precast concrete structural members in accordance with the following sections and subsections, as applicable:

Reinforcing Steel ………………………………………………... 554

Storing, Transporting, & Erecting ………………………………. 553.08

Structural Concrete ……………………………………………… 552

Submit four sets of shop drawings to the CO for approval, including the concrete mix design for each class of concrete proposed for use, a minimum of 21 days before fabrication of the precast member(s).

553A.04 Casting Yard. The precasting of concrete structural members may only be done at a casting yard selected by the Contractor.

553A.05 Handling, Transporting, & Erecting. Provide additional reinforcement, as needed, to meet the requirements of handling, transporting, and erecting precast members.

553A.06 Acceptance. Reinforcing steel, anchor devices, elastomeric bearings, and material for concrete and grout will be evaluated under Subsection 106.03. Furnish production certifications for hydraulic cement, and reinforcing steel.

Concrete for precast concrete members will be evaluated under Subsections 106.02, 106.03, and 106.04.

Construction of precast concrete members will be evaluated under Subsections 106.02 and 106.04.

Reinforcing steel will be evaluated under Section 554.

Falsework and forms will be evaluated under Section 562.

Measurement

553A.07 Measure the Section 553A items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

Do not measure reinforcing steel, concrete, anchorages, plates, nuts, and other material contained within or attached to the unit for precast concrete structural members.

Payment

553A.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 553A pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

603 - Structural Plate Structures

603.03 General.

Delete the first sentence and add the following:

Excavation and backfill will be evaluated under Section 208.

603.05 Acceptance.

Delete the third sentence and add the following:

Excavation and backfill will be evaluated under Section 208.

622 - Rental Equipment

622.02 Rental Equipment

Delete the first two sentences of the first paragraph and add the following:

Provide equipment of the type listed in the Schedule of Items. Provide equipment of at least the minimum size needed to efficiently perform the work. Submit the model number of the equipment to the CO for approval before delivery to the project site. Equipment shall be no more than 15 years old and shall be reasonably free of leaks and other mechanical deficiencies.

Measurement

622.04

Add the following:

The Government reserves the right to reduce or eliminate entirely the work under this item with no adjustment in contract unit price.

625 – Turf Establishment

625.03 General.

Delete the first sentence and add the following:

Apply turf establishment to portions of slopes, ditches, waste areas, and other disturbed areas within 14 days after being constructed to template lines unless otherwise specified in writing by the C.O.

625.04 Preparing Seedbed.

Delete the second sentence of the first paragraph.

Delete the third paragraph.

625.05 Watering

Delete the entire paragraph.

625.06 Fertilizing.

Delete the entire subsection and add the following.

Apply fertilizer having a chemical analysis as listed in (c) below by the following methods. Apply seed and fertilizer in one application.

(a) Dry Method. Apply the fertilizer with approved power driven seeders, drills, fertilizer spreaders or other mechanical equipment. Hand operated methods are satisfactory on areas inaccessible to mechanical equipment.

(b) Hydraulic method. Use hydraulic-type equipment capable of providing a uniform application using water as the carrying agent. Add fertilizer to the slurry and mix before adding seed.

(c) Chemical analysis. Apply fertilizer at the rate of 100 pounds per acre. Apply fertilizer having the following chemical analysis.

Nutrient Percent

Nitrogen, N

Phosphorus, P2O5

Potassium, K

Fertilizer having a different chemical analysis may be used if approved in advance by the CO.

625.07 Seeding.

Delete the first sentence and add the following.

Apply seed mix shown in (c) below by the following methods.

(a) Dry method.

Delete the third sentence.

Add the following after subsection (b).

(c) Seed Mix. In terms of pure live seed, furnish and apply the following kinds and amounts of seed. Obtain the pounds of seed to furnish per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.

Example:

5 lbs Pure Live Seed/Acre = 6.55 lbs Commercial Seed/Acre

0.90 X 0.85 (Purity = 90% and Germination = 85%)

Kind of Seed Quantity of Pure Live Seed

(Lbs/Acre)

1. Annual Rye

2. Nez Purs Idaho Fescue

3. Garnet Mountain Brome

Total

625.08 Mulching.

(b) Hydraulic method.

Delete the first sentence and add the following.

Apply mulch in a separate application from the seed or in a single application with the seed using hydraulic-type equipment according to Subsection 625.07(b).

625.09 Protecting and Caring for Seeded Areas.

Delete the first sentence and add the following.

Protect and care for seeded areas until final acceptance.

625.11 Measurement

Delete the second paragraph and add the following.

Measure seeding, fertilizing, and mulching by the acre on the ground surface or by lump sum.

725 - Miscellaneous Material

Add the following section:

725.40 High-Strength Nonshrink Grout

Furnish grout that is packaged and ready for use with the addition of water at the construction site. Ensure that each bag is stamped to show the last date on which it may be used. Use grout that consists of a hydraulic cementitious system, graded and processed natural fine aggregate, and additional technical components such that the product meets the following conditions:

(a) Free of inorganic accelerators, including chlorides.

(b) Free of oxidizing catalysts.

(c) Free of gas-producing agents.

(d) When mixed to 130 percent flow on flow table (ASTM C 230 at 10 drops), it does not reduce in linear dimension when tested in accordance with ASTM C157. Take measurements at 72 hours and 7 days.

(e) Produces no bleeding for the first 2 hours after mixing when mixed to 130 percent flow on flow table (ASTM C 230 at 10 drops), as tested in accordance with ASTM C232.

(f) Has a minimum strength as follows when tested in accordance with ASTM C 109:

(1) After 72 hours, 25 MPa (3500 psi).

(2) At 7 days, 40 MPa (6000 psi).

(3) After 28 days, 50 MPa (7200 psi).

Provide performance characteristics at 115 to 120 percent flow on flow table (ASTM C 230 at 10 drops).

(g) It must be designed, as stated by the manufacturer, to be mixed, placed, and cured at atmospheric temperatures of 5O C to 30O C (40O F to 85O F). Submit products proposed for use for approval by the CO and accompany them with manufacturer’s submittals substantiating all requirements in this subsection, including graphs or charts showing the time, temperature, and humidity requirements for curing to achieve the specified grout strengths; and recommendations for storage, mixing, application, and curing procedures.

As specified as grout on the contract plans, the following products meet the above requirements.

1. MASTERFLOW 928 GROUT, manufactured by Chemrex.

2. CRYSTEX GROUT, manufactured by L&M Construction Chemicals, Inc.

3. CEMENT ALL, manufactured by CTS Cement Manufacturing Co.

4. SURE-GRIP HIGH PERFORMANCE GROUT manufactured by Dayton Superior.

725.41 Mortar

Furnish mortar that is packaged and ready for use with the addition of water at the construction site. Ensure that each bag is stamped to show the latest date on which it may be used. Use mortar that consists of a cementitious system made up of:

(a) Natural aggregate, 3/8” maximum size, that meets the requirements specified in ASTM C 33 except for grading. Accomplish grading by blending sieve sizes to obtain the optimum density.

(b) Metallic aggregate free from nonferrous material, soluble alkaline compounds, and visible rust.

(c) Water reducers, workability agents, air-entraining agents, and catalysts.

Blend the materials to minimize bleeding, increase workability, resist exposure to freeze-thaw cycles and deicing salts, and prevent shrinkage within and at the perimeter of the patch, keyway, or other area to be filled.

Ensure that the minimum compressive strength of the mortar, as tested by ASTM C 109 for a 3” slump, is:

· 24-hour...........................................................................................35MPa (5000 psi)

· 7-day...............................................................................................60 MPa (8500 psi)

· 28-day.............................................................................................70 MPa (10,000 psi)

Ensure that the durability of the products when tested at 300 cycles, ASTM C 666, procedure A is:

Submerged in: DF (%)

Water 98

5% CaCl2 solution 95

5% NaCL solution 85

Ensure that the scaling resistance has a rating of 3, Moderate Scaling, after 50 cycles when tested in accordance with ASTM C 672.

Provide certification from the manufacturer that the product is compatible for work that is 1” or more in depth and more than 1” in width; and where the mixing, placing, and curing temperatures may range from 5O C to 30O C (40O F to 85O F).

Submit products proposed for use to the CO for approval, and accompany them with the manufacturer’s submittals substantiating all requirements in this section, including (1) graphs or charts showing the time, temperature, humidity, and curing requirements to achieve mortar…