DE_FSSS_revision1.docx
DOCX document 126 KB Posted
- Attached to
- Idaho Panhandle NF, Devil's Elbow Repave Federal contract opportunity
- Solicitation number
- AG-02RC-S-11-0122
About this file
Special Project Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_pkg_1.doc | DOC document | |
| Devils_Elbow_Repave_revision1.pdf | ||
| SF24BidBondFillForm.pdf | ||
| DBWageDetermination.docx | DOCX document | |
| OwnerPastPerformanceSurvey.docx | DOCX document | |
| IdahoWCI.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
| Preface | 5 |
| 101 - Terms, Format, and Definitions | 6 |
| 101.01 Meaning of Terms | 6 |
| 101.03 Abbreviations. | 6 |
| 101.04 Definitions. | 6 |
| 102 - Bid, Award, and Execution of Contract | 9 |
| 102 Bid, Award, and Execution of Contract | 9 |
| 103 - Scope of Work | 10 |
| Deletions | 10 |
| 104 - Control of Work | 11 |
| Deletions | 11 |
| 104.06 Use of Roads by Contractor | 11 |
| 105 - Control of Material | 12 |
| 105.01 Source of Supply and Quality Requirements. | 12 |
| 105.02 Material Sources. | 12 |
| 105.02(a) Government-provided sources. | 12 |
| 105.05 Use of Material Found in the Work. | 12 |
| 106 - Acceptance of Work | 13 |
| 106.01 Conformity with Contract Requirements. | 13 |
| 106.07 Delete | 15 |
| 107 - Legal Relations and Responsibility to the Public | 16 |
| 107.05 Responsibility for Damage Claims. | 16 |
| 107.06 Contractor’s Responsibility for Work. | 16 |
| 107.09 Legal Relationship of the Parties. | 16 |
| 107.10 Environmental Protection. | 16 |
| 108 - Prosecution and Progress | 18 |
| 108 Delete. | 18 |
| 109 - Measurement and Payment | 19 |
| 109 Deletions | 19 |
| 109.02 Measurement Terms and Definitions. | 19 |
| 151 - Mobilization | 20 |
| 151.01 | 20 |
| 155 - Schedules for Construction Contracts | 22 |
| 155 Delete. | 22 |
| 156 - Public Traffic | 23 |
| 156.08 Traffic and Safety Supervisor. | 23 |
| 201 - Clearing and Grubbing | 24 |
| 201.01 Description | 24 |
| 201.04 Clearing. | 24 |
| 202 - Additional Clearing and Grubbing | 26 |
| 202.09 Measurement. | 26 |
| 203 - Removal of Structures and Obstructions | 27 |
| 203.01 Description. | 27 |
| 203.03 Salvaging Material | 27 |
| 203.04 Removing Material. | 27 |
| 203.05 Disposing of Material. | 27 |
| 204 - Excavation and Embankment | 29 |
| 204.01 | 29 |
| 204.02 Definitions | 29 |
| 204.03 | 30 |
| 204.04 Preparation for Roadway Excavation and Embankment Construction | 30 |
| 204.05 Reserved | 30 |
| 204.06 Roadway Excavation | 30 |
| 204.07 Subexcavation | 30 |
| 204.08 Borrow Excavation | 31 |
| 204.09 Preparing Foundation for Embankment Construction | 31 |
| 204.10 Embankment Construction | 31 |
| 204.11 Compaction | 32 |
| 204.12 Ditches | 33 |
| 204.13 Sloping, Shaping, and Finishing | 33 |
| 204.14 Disposal of Unsuitable or Excess Material | 34 |
| 204.15 Acceptance | 34 |
| 204.16 Measurement. | 35 |
| 204.17 Payment. | 36 |
| 324 - Minor Aggregate, Commercial Source | 40 |
| 324.01 Description | 40 |
| 324.02 Material | 40 |
| 324.03 General | 40 |
| 324.04 Mixing and Spreading | 40 |
| 324.05 Compacting | 41 |
| 324.06 Construction Tolerance. | 41 |
| 324.07 Maintenance | 42 |
| 324.08 Acceptance | 42 |
| 324.09 Measurement. | 42 |
| 324.10 Payment. | 42 |
| 403 - Hot Asphalt Concrete Pavement | 45 |
| 403.03 Composition of Mix (Job-Mix Formula) | 45 |
| 403.06 Surface Preparation. | 45 |
| 403.16 Pavement Smoothness. | 45 |
| 403.17 Acceptance | 45 |
| Table 403-1—Acceptance Sampling and Testing Requirements. | 46 |
| 412 - Asphalt Tack Coat | 47 |
| 412.07 Acceptance | 47 |
| 622 - Rental Equipment | 48 |
| 622.02 Rental Equipment | 48 |
| 625 - Turf Establishment | 50 |
| 626.03 General | 50 |
| 625.04 Preparing Seedbed. | 50 |
| 625.05 Watering | 50 |
| 625.06 Fertilizing. | 50 |
| 625.07 Seeding. | 51 |
| 625.08 Mulching. | 52 |
| 625.09 Protecting and Caring for Seeded Areas | 52 |
| 625.11 Measurement. | 52 |
| 633 - Permanent Traffic Control | 53 |
| 633.01 | 53 |
| 633.02 Material. | 53 |
| 633.03 General. | 53 |
| 633.05 Panels. | 53 |
| 634 - Permanent Pavement Marking | 54 |
| 634.03 General. | 54 |
| 634.04 Conventional Traffic Paint (Type A). | 54 |
| 635 - Temporary Traffic Control | 55 |
| 635.03 General. | 55 |
| 718 - Traffic Signing and Marking Material | 56 |
| 718.05 Aluminum Panels | 56 |
Devil’s Elbow Repave Project iii
Preface Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions 101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
| mp |
| Milepost |
| ppm |
| Part Per Million |
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005 102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work 103.00_nat_us_02_16_2005 Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work 104.00_nat_us_06_16_2006 Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_ipnf_08_12_2011 Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated on the Coeur d’Alene River Ranger District Motor Vehicle Use Map (MVUM) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material 105.00_01_us_10_13_2006
105.01 Source of Supply and Quality Requirements.
Add the following:
All materials incorporated into the project shall be certified noxious weed-free seed, either through visual inspection or commercial certification.
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a)_ipnf_08_12_2011 105.02(a) Government-provided sources.
Add the following:
An additional Government material source is located 13.1 miles from the Devil’s Elbow Campground on Road #2321.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work 106.01_ipnf_08_12_2011
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
Sampling and testing of materials will be completed by the Contractor.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(2) Sample transport;
(3) Test procedures;
(4) Testing laboratories;
(5) Reporting;
(6) Estimated time and costs; and
(7) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress 108.00_nat_us_02_16_2005 108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment 109.00_nat_us_02_17_2005 109 Deletions Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02 Measurement Terms and Definitions.
Delete paragraph (b) and replace with the following:
“(b) Contract quantity. The quantity to be paid is the quantity shown in the bid schedule. This quantity is based upon the original design data available prior to advertising the project. The contract quantity will be adjusted for authorized changes that affect the quantity or for errors made in computing this quantity that changes the original quantity by more than 15%. If there is evidence the quantity specified as a contract quantity is incorrect by more than 15%, submit calculations, drawings, or other evidence indicating why the quantity is in error and request, in writing, that the quantity be adjusted.”
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Delete paragraph (h) and replace with the following:
“(h) Lump sum quantity. Do not measure directly. The quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. The quantity is designated as “All” and will not be measured.
Add the following definition:
“(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
151 - Mobilization 151.00_01_us_10_11_2006 Delete Section 151 in its entirety and replace with the following.
Description
151.01 Add the following:
This work consists of washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands.
Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.
Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.
Notify the CO in writing at least 48 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.
Use methods of cleaning and locations for cleaning approved by the C.O.
For work at a commercial washing facility, use an approved facility.
New infestations of noxious weeds of concern to Forest Service and identified by either Contractor or Forest Service, on the Project Area or on the haul route, will be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.
Measurement
151.02 Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment for cleaning will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.
Measure mobilization according to Subsection 109.02.
Payment
151.03 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Progress payments for mobilization lump sum will be paid as follows:
(a) If applicable, bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.
Include all costs associated with the initial cleaning of equipment in the unit bid price for Mobilization. Cleaning for subsequent move-ins will not be paid for unless after a suspension ordered by the CO.
155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004 155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic 156.00_ipnf_08_12_2011 Delete Section 156 in its entirety and replace with the following:
156.03 General. The Devil’s Elbow Campground will be closed to public use for the duration of this contract, therefore existing roads do not need to remain open to all traffic other than construction traffic.
156.08_nat_us_02_24_2005
156.08 Traffic and Safety Supervisor.
Delete this subsection in its entirety.
201 - Clearing and Grubbing 201.01_nat_us_02_18_2005
201.01 Description
Replace with the following
This work consists of clearing and grubbing within clearing limits and other designated areas.
201.04_ipnf_08_12_2011
201.04 Clearing.
Delete paragraph (c) and replace with the following:
(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground. Within the camp site limits around spurs and pull-throughs, cut stumps flush with the ground.
Add the following:
(e) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs as near flush with the trunk as practicable.
(f) Remove brush from log decks. Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.
201.06_ipnf_08_12_2011
201.06 Disposal
Delete the first sentence of this paragraph and substitute the following:
Limb and deck logs 8 inches or greater into log lengths of 40 feet, or in tree lengths where practical, at a location approved by the CO, or otherwise designated. Limb and deck logs of 4 – 7 inches within the campground near the new spur sites. Deck logs according to 201.04 (f).
202 - Additional Clearing and Grubbing
202.09_ipnf_08_12_2011
202.09 Measurement.
Delete the second paragraph of this subsection and substitute the following:
Individual removal of trees is the number of trees of the various size designations removed. Measure tree diameters at a height of 12 inches above ground. Do not count trees less than 4 inches in diameter. Size designations are shown in Table 202-1.
Table 202-1. - Size designations for trees removed.
| Pay Item Designation |
| Size of Least Diameter at Height of 12 inches |
| Greater Than |
| Less Than |
| Small |
| 6 inches |
| 24 inches |
| Medium |
| 24 inches |
| 40 inches |
| Large |
| 40 inches |
| - |
203 - Removal of Structures and Obstructions 203.01_ipnf_08_12_2011
203.01 Description.
Delete and replace with the following:
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions, such as concrete bollards, wooden curbs, and barrier rocks.
203.03_ipnf_08_12_2011
203.03 Salvaging Material
Delete paragraphs two and three and add:
Stockpile salvaged material at a location approved by the CO. Logs 8” or above are to be decked in tree lengths at the group site location designated by the CO.
203.04_ipnf_08_12_2011
203.04 Removing Material.
Add the following:
Remove the existing pavement within the campground to the top layer of natural subgrade. Grind the existing pavement and use the resulting material as fill material for the embankment placement item.
203.05_ipnf_08_12_2011
203.05 Disposing of Material.
(a) Remove from project.
Delete the last two sentences and add the following:
Stumps are to are to be burned according to (b) of this section. Or, if they cannot be reduced adequately by burning, they are to be removed to the material source site on Road #2321 and stockpiled.
(b) Burn.
Delete the last sentence and add the following:
Deposit construction slash so that burning does not damage standing trees. Dispose of unburned material as directed by the CO.
203.08_nat_us_02_24_2005
203.08 Payment
Add the following:
Disposal of construction slash will be compensated under the designated pay item in Section 201.
204 - Excavation and Embankment 204.00_ipnf_08_12_2011
Replace Section 204 in its entirety with the following:
Description
204.01 This work consists of excavating material and constructing embankments. This includes furnishing, hauling, stockpiling, placing, disposing, sloping, shaping, compacting, and finishing earthen and rocky material.
204.02 Definitions.
(a) Excavation. Excavation consists of the following:
(1) Roadway excavation. All material excavated from within the right-of-way or easement areas, except subexcavation covered in (2) below and structure excavation covered in Sections 208 and 209. Roadway excavation includes all material encountered regardless of its nature or characteristics.
(2) Subexcavation. Material excavated from below subgrade elevation in cut sections or from below the original groundline in embankment sections. Subexcavation does not include the work required by Subsections 204.05, 204.06(b), and 204.06(c).
(3) Borrow excavation. Material used for embankment construction that is obtained from outside the roadway prism. Borrow excavation includes unclassified borrow, select borrow, and select topping.
(b) Embankment construction. Embankment construction consists of placing and compacting roadway or borrow excavation. This work includes:
(1) Preparing foundation for embankment;
(2) Constructing roadway embankments;
(3) Benching for side-hill embankments;
(4) Constructing dikes, ramps, mounds, and berms; and
(5) Backfilling subexcavated areas, holes, pits, and other depressions.
(c) Conserved topsoil. Excavated material conserved from the roadway excavation and embankment foundation areas that is suitable for growth of grass, cover crops, or native vegetation.
(d) Waste. Excess and unsuitable roadway excavation and subexcavation that cannot be used.
Material
204.03 Conform to the following Subsections:
| Backfill material | 704.03 |
| Select borrow | 704.07 |
| Select topping | 704.08 |
| Topping | 704.05 |
| Unclassified borrow | 704.06 |
| Water | 725.01 |
Construction Requirements
204.04 Preparation for Roadway Excavation and Embankment Construction. Clear the area of vegetation and obstructions according to Sections 201 and 203.
204.05 Reserved.
204.06 Roadway Excavation. Excavate as follows:
(a) General. Do not disturb material and vegetation outside the construction limits.
Incorporate only suitable material into embankments. Replace any shortage of suitable material caused by premature disposal of roadway excavation. Dispose of unsuitable or excess excavation material according to Subsection 204.14.
At the end of each day's operations, shape to drain and compact the work area to a uniform cross-section. Eliminate all ruts and low spots that could hold water.
Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.
(b) Pioneer Roads. Road pioneering, slash disposal, and grubbing of stumps may proceed concurrently with excavation. Conduct excavation and placement operations so material to be treated under Section 201 will not be incorporated into the roadway unless specified in the slash treatment method. Maintain drainage during pioneering operations.
Remove snow and ice in advance of the work and deposit beyond the roadway limits in a manner that will not waste material or generate sediment. Do not incorporate snow and ice into embankments. Place snow or ice in a manner to prevent resource damage.
204.07 Subexcavation. Excavate material to the limits designated by the CO. Take cross-sections according to Section 152. Prevent unsuitable material from becoming mixed with the backfill. Dispose of unsuitable material according to Subsection 204.14. Backfill the subexcavation with topping, or other suitable material. Compact the material according to Subsection 204.11.
204.08 Borrow Excavation. Use all suitable roadway excavation in embankment construction. Do not use borrow excavation when it results in excess roadway excavation. Deduct excess borrow excavation from the appropriate borrow excavation quantity.
Obtain borrow source acceptance according to Subsection 105.02. Develop and restore borrow sources according to Subsection 105.03. Do not excavate beyond the established limits. When applicable, shape the borrow source to permit accurate measurements when excavation is complete.
204.09 Preparing Foundation for Embankment Construction. Prepare foundation for embankment construction as follows:
(a) Embankment less than 4 feet high over natural ground. Remove topsoil and compact the ground surface according to Subsection 204.11.
(b) Embankments over an existing asphalt, concrete, or gravel road surface. Grind the existing asphalt layer to the top layer of natural subgrade, according to Section 203 and FSSS 203.04. Compact the surface according to Subsection 204.11.
204.10 Embankment Construction. Incorporate only suitable roadway excavation material into the embankment. When the supply of suitable roadway excavation is exhausted, furnish unclassified borrow to complete the embankment. Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline. Construct embankments as follows:
(a) General. At the end of each day's operations, shape to drain and compact the embankment surface to a uniform cross-section. Eliminate all ruts and low spots that could hold water.
During all stages of construction, route and distribute hauling and leveling equipment over the width and length of each layer of material.
(b) Embankment within the roadway prism. Place embankment material in horizontal layers not exceeding 12 inches in compacted thickness. Compact each layer according to Subsection 204.11 before placing the next layer.
Material composed predominately of boulders or rock fragments too large for 12inch layers may be placed in layers up to 24 inches thick. Incorporate oversize boulders or rock fragments into the 24-inch layer by reducing them in size or placing them individually according to (c) below. Place sufficient earth and smaller rocks to fill the voids. Compact each layer according to Subsection 204.11 before placing the next layer.
(c) Individual rock fragments and boulders. Place individual rock fragments and boulders greater than 24 inches in diameter as follows:
(1) Reduce rock to less than 48 inches in the largest dimension.
(2) Distribute rock within the embankment to prevent nesting.
(3) Place layers of embankment material around each rock to a depth not greater than that permitted by (b) above. Fill all the voids between rocks.
(4) Compact each layer according to Subsection 204.11 before placing the next layer.
204.11 Compaction. Compact the embankment using one of the following methods as specified:
(a) Compaction A. Use AASHTO T 27 to determine the amount of material retained on a Number 4 sieve. If there is more than 80 percent retained on the No. 4 sieve use procedure (1). If there is 50 to 80 percent retained on the No. 4 sieve use procedure (2). If there is less than 50 percent retained on the No. 4 sieve use procedure (3).
(1) Adjust the moisture content to a level suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Use compression-type rollers at speeds less than 6feet per second and vibratory rollers at speeds less than 3 feet per second. Compact each layer of material full width with one of the following and until there is no visible evidence of further consolidation.
(a) Four roller passes of a vibratory roller having a minimum dynamic force of 40,000 pounds impact per vibration and a minimum frequency of 1000 vibrations per minute.
(b) Eight roller passes of a 20-ton compression-type roller.
(c) Eight roller passes of a vibratory roller having a minimum dynamic force of 30,000 pounds impact per vibration and a minimum frequency of 1000 vibrations per minute.
Increase the compactive effort for layers deeper than 12 inches as follows:
For each additional 6 inches or fraction thereof, increase the number of roller passes in (a) above by four passes.
For each additional 6 inches or fraction thereof, increase the number of roller passes in (b) and (c) above, by eight passes.
(2) Use AASHTO T 99 to determine the optimum moisture content of the portion of the material passing a No. 4 sieve. Multiply this number by the percentage of material passing a No. 4 sieve, and add 2 percent to determine the optimum moisture content of the material. Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content.
Use compression-type rollers at speeds less than 6 feet per second and vibratory rollers at speeds less than 3 feet per second. Compact each layer of material full width according to (1) above.
(3) Classify the material according to AASHTO M 145. For material classified A-1 or A-2-4, determine the maximum density according to AASHTO T 180, method D. For other material classifications, determine the optimum moisture content and maximum density according to AASHTO T 99, method C.
Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A6 and A-7 to within 2 percent of the optimum moisture content.
Use compression-type or vibratory rollers. Compact each layer of material full width to at least 95 percent of the maximum density. Determine the in-place density and moisture content according to AASHTO T 310 or other approved test procedures. When required, use AASHTO T 224 to correct for coarse particles.
(b) Compaction B. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until there is no visible evidence of further consolidation or, if when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.
(c) Compaction C. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.
204.12 Ditches. Slope, grade, and shape ditches. Remove all projecting roots, stumps, rock, or similar matter. Maintain all ditches in an open condition and free from leaves, sticks, and other debris.
Form furrow ditches by plowing or using other acceptable methods to produce a continuous furrow. Place all excavated material on the downhill side so the bottom of the ditch is approximately 18 inches below the crest of the loose material. Clean the ditch using a hand shovel, ditcher, or other suitable method. Shape to provide drainage without overflow.
204.13 Sloping, Shaping, and Finishing. Complete slopes, ditches, culverts, riprap, and other underground minor structures before placing aggregate courses. Slope, shape, and finish as follows:
(a) Sloping. Leave all earth slopes with uniform roughened surfaces, except as described in (b) below, with no noticeable break as viewed from the road. Except in solid rock, round tops and bottoms of all slopes including the slopes of drainage ditches. Round material overlaying solid rock to the extent practical. Scale all rock slopes. Slope rounding is not required on tolerance class D though M roads.
If a slide or slipout occurs on a cut or embankment slope, remove or replace the material, and repair or restore all damage to the work. Bench or key the slope to stabilize the slide. Reshape the cut or embankment slope to an acceptable condition.
(b) Stepped slopes. Where required by the contract, construct steps on slopes of 1⅓V:1H to 1V:2H. Construct the steps approximately 18 inches high. Blend the steps into natural ground at the end of the cut. If the slope contains nonrippable rock outcrops, blend steps into the rock. Remove loose material found in transitional area. Except for removing large rocks that may fall, scaling stepped slopes is not required.
(c) Shaping. Shape the subgrade to a smooth surface and to the cross-section required. Shape slopes to gradually transition into slope adjustments without noticeable breaks. At the ends of cuts and at intersections of cuts and embankments, adjust slopes in the horizontal and vertical planes to blend into each other or into the natural ground.
(d) Finishing. Finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material. Finish roadbeds to the tolerance class shown in table 204-2.Ensure that the subgrade is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.
For surfaced roads, remove all material larger than 6 inches from the top 6 inches of the roadbed.
For unsurfaced roads, use one of the following methods to finish the roadbed:
(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.
(2) Method B. Use a vibratory grid roller or approved equal with a minimum weight of 10 tons. Roll at least 5 full-width passes or until there is no visible evidence of further consolidation.
(3) Method C. For roads designated as Construction Tolerance Class K, L, or M, finish the roadbed by spreading the excavation. Eliminate rock berms.
204.14 Disposal of Unsuitable or Excess Material. Dispose of unsuitable or excess material at designated sites or legally off of the project.
When there is a pay item for waste, shape and compact the waste material in its final location. Do not mix clearing or other material not subject to payment with the waste material.
204.15 Acceptance. See Table 204-1 for sampling and testing requirements.
Material for embankment and conserved topsoil will be evaluated under Subsections 106.02 and 106.04.
Excavation and embankment construction will be evaluated under Subsections 106.02 and 106.04.
Clearing and removal of obstructions will be evaluated under Sections 201 and 203.
Measurement
204.16 Measurement. Measure the Section 204 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.
(a) Roadway excavation. Measure roadway excavation in its original position as follows:
(1) Include the following volumes in roadway excavation:
(a) Roadway prism excavation;
(b) Rock material excavated and removed from below subgrade in cut sections;
(c) Unsuitable material below subgrade and unsuitable material beneath embankment areas when a pay item for subexcavation is not shown in the bid schedule;
(d) Ditches, except furrow ditches measured under a separate bid item;
(eTopsoil;
(f) Borrow material used in the work when a pay item for borrow is not shown in the bid schedule;
(g) Loose scattered rocks removed and placed as required within the roadway;
(h) Conserved material taken from stockpiles and used in Section 204 work; and
(i) Slide and slipout material not attributable to the Contractor's method of operation.
(2) Do not include the following in roadway excavation:
(a) Overburden and other spoil material from borrow sources;
(b) Overbreakage from the backslope in rock excavation;
(c) Water or other liquid material;
(d) Material used for purposes other than required;
(e) Roadbed material scarified in place and not removed;
(f) Material excavated when stepping cut slopes;
(g) Material excavated when rounding cut slopes;
(h) Preparing foundations for embankment construction;
(i) Material excavated when benching for embankments;
(j) Slide or slipout material attributable to the Contractor's method of operation;
(k) Conserved material taken from stockpiles constructed at the option of the Contractor; and
(l) Material excavated outside the established slope limits.
(3) When both roadway excavation and embankment construction pay items are shown in the bid schedule, measure the following as roadway excavation only:
(a) Unsuitable material below subgrade in cuts and unsuitable material beneath embankment areas when a pay item for subexcavation is not shown in the bid schedule;
(b) Slide and slipout material not attributable to the Contractor’s method of operations; and
(c) Drainage ditches, channel changes, and diversion ditches.
(b) Unclassified borrow, select borrow, and select topping. When measuring by the cubic yard measure in its original position. If borrow excavation is measured by the cubic yard in place, take initial cross-sections of the ground surface after stripping overburden. Upon completion of excavation and after the borrow source waste material is returned to the source, retake cross-sections before replacing the overburden.
Do not measure borrow excavation used in place of excess roadway excavation.
(c) Embankment construction. Measure embankment construction in its final position. Do not make deductions from the embankment construction quantity for the volume of minor structures.
(1) Include the following volumes in embankment construction:
(a) Roadway embankments;
(b) Material used to backfill subexcavated areas, holes, pits, and other depressions;
(c) Material used to restore obliterated roadbeds to original contours; and
(d) Material used for dikes, ramps, mounds, and berms.
(2) Do not include the following in embankment construction:
(a) Preparing foundations for embankment construction;
(b) Adjustments for subsidence or settlement of the embankment or of the foundation on which the embankment is placed; and
(c) Material used to round fill slopes.
(d) Rounding cut slopes. Measure rounding cut slopes horizontally along the centerline of the roadway if a pay item for slope rounding is included in the bid schedule. If a pay item for slope rounding is not included in the bid schedule slope rounding will be considered subsidiary to excavation.
(e) Waste. Measure waste by the cubic yard in its final position. Take initial cross-sections of the ground surface after stripping over burden. Upon completion of the waste placement, retake cross-sections before replacing overburden.
(f) Slope scaling. Measure slope scaling by the cubic yard in the hauling vehicle.
Payment
204.17 Payment. The accepted quantities will be paid at the contract price per unit of measurement for the Section 204 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Table 204-1 Sampling and Testing Requirements
| Reporting Time |
| Before using in work |
| “ |
| Before placing next layer |
| Before using in work |
| “ |
| “ |
| “ |
| Before placing next layer |
| (1) Minimum of 5 points per proctor |
Split Sample
| Yes, when requested |
| “ |
| — |
| Yes, when requested |
| “ |
| “ |
| “ |
| — |
| Point of Sampling |
| Processed material before incorporating in work |
| “ |
| In-place |
| Processed material before incorporating in work |
| “ |
| “ |
| “ |
| In-place |
Sampling Frequency
| 1 per soil type |
| 1 per soil type but not less than 1 per |
13,000 yd3
| 1 per 6000 yd2 but not less than 1 per layer |
| 1 per soil type but not less than 1 for each day of production |
| “ |
| “ |
| 1 per soil type but not less than 1 per |
13,000 yd3 1 per 6000 yd2 but not less than 1 per layer
| Test Methods Specifications |
| AASHTO M 145 |
| AASHTO T 180, method D(1) or T 99, method C(1) |
| AASHTO T 310 or other approved procedures |
| AASHTO M 145 |
| AASHTO T 27 |
& T 11
| AASHTO T 89 |
| AASHTO T 180, method D(1) or T 99, method C(1) |
| AASHTO T 310 or other approved procedures |
| Category |
| — |
| — |
| — |
| — |
| — |
| — |
| — |
| — |
| Characteristic |
| Classification |
| Moisture-density |
| Compaction |
| Classification |
| Gradation |
| Liquid limit |
| Moisture-density |
| Compaction |
| Type of Acceptance (Subsection) |
| Measured and tested for conformance (106.04) |
| Measured and tested for conformance (106.04) |
| Material or Product |
| Topping |
(704.05) & unclassified borrow (704.06) Select borrow (704.07 & Select topping (704.08)
Table 204-1 (continued)
| Reporting Time |
| Before using |
in work
| “ |
| Before placing next layer |
| Before placing next layer |
| (1) Minimum of 5 points per proctor. |
Split
| Yes, when requested |
| “ |
| — |
| — |
| Point of Sampling |
| Source of |
Material
| “ |
| In-place |
| In-place |
Sampling
| 1 per soil type |
| 1 per soil type but not |
less than 1 per 13,000 yd3 1 per 3500 yd2 but not less than 1 per layer 1 per 2500 yd2
| Test Methods Specifications |
| AASHTO M 145 |
| AASHTO T 180, |
method D(1) or T 99, method C(1) AASHTO T 310 or other approved procedures AASHTO T 310 or other approved procedures
| Category |
| — |
| — |
| — |
| — |
| Characteristic |
| Classification |
| Moisture- |
density
| Compaction |
| Compaction |
| Type of Acceptance (Subsection) |
| Measured and tested |
for conformance (106.04) Measured and tested for conformance (106.04)
| Material or Product |
| Earth embankment (204.11, |
Compaction A) Top of subgrade (204.11 Compaction A)
Table 204-2 Construction Tolerances
| Tolerance Class (a) |
| M |
| +2.0 |
| (c) |
| (c) |
| +20 |
| (a) Maximum allowable deviation from construction stakes and drawings. |
(b) Maximum allowable deviation from staked slope measured from slope stakes or hinge points.
(c) Unless otherwise shown the centerline alignment and subgrade elevation, as built, have no horizontal curves with a radius of less than 80 feet, and no vertical curves with a curve length of less than 80 feet when the algebraic difference in the grade change is less than 10 percent, or a curve length of less than 100 feet when the algebraic difference of the grade change is greater than or equal to 10 percent. The centerline grade is not to exceed 20 percent in 100 feet of length.
| L |
| +2.0 |
| +3.0 |
| +5.0 |
| +20 |
| K |
| +2.0 |
| +2.0 |
| +3.0 |
| +20 |
| J |
| +2.0 |
| +3.0 |
| +3.0 |
| +10 |
| I |
| +2.0 |
| +2.0 |
| +2.0 |
| +10 |
| H |
| +1.0 |
| +1.5 |
| +1.5 |
| +10 |
| G |
| +1.5 |
| +1.0 |
| +1.5 |
| +10 |
| F |
| +1.0 |
| +1.0 |
| +1.0 |
| +5 |
| E |
| +1.0 |
| +0.5 |
| +1.0 |
| +5 |
| D |
| +1.0 |
| +0.5 |
| +0.5 |
| +5 |
| C |
| +1.0 |
| +0.2 |
| +0.5 |
| +5 |
| B |
| +0.5 |
| +0.2 |
| +0.2 |
| +5 |
| A |
| +0.5 |
| +0.1 |
| +0.2 |
| +3 |
| Roadbed width (ft) |
| Subgrade elevation |
(ft)
| Centerline alignment (ft) |
| Slopes, excavation, and embankment |
(% slope(b))
324 - Minor Aggregate, Commercial Source 324.00_ipnf_08_12_2011 Section 324. – MINOR AGGREGATE COURSES – COMMERCIAL SOURCE
324.01 Description. This work consists of constructing one or more courses of aggregate on a prepared surface. Work includes producing aggregate by crushing methods.
324.02 Material. Conform to the following Subsections:
| Aggregate | 703.06 |
| Water | 725.01 |
Construction Requirements
324.03 General. Prepare the surface on which the aggregate course is placed according to Section 204 or 303 as applicable.
Request approval of the roadbed in writing before placing aggregate.
Develop, haul, and apply water in accordance to Section 170.
Submit aggregate gradations for approval by the CO.
After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at approved locations.
324.04 Mixing and Spreading. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with moisture content suitable for the specified compaction method. Spread and shape the mixture on the prepared surface in a uniform layer with no segregation of size, and to a loose depth that will provide the required compacted thickness. Place the mixture in a maximum compacted layer thickness of 4 inches.
When more than one layer is necessary, compact each layer according to Subsection 324.05 before placing the next layer. Route hauling and leveling equipment uniformly over the full width.
When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.
324.05 Compacting. Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
Compaction F. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 180,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .