IDAWY ACQUISITION SERVICE CENTER INSTRUCTIONAL COVER SHEET

ISSUING OFFICE:

U.S. DEPARTMENT OF AGRICULTURE

FOREST SERVICE

IDAWY ACQUISITION SERVICE CENTER

1405 HOLLIPARK DR.

IDAHO FALLS, ID 83401

FAX (208) 557-5829

SOLICITATION NO.: AG-02NV-S-15-0064

QUOTES ARE SOLICITED FOR: ST. ANTHONY BUNKHOUSE FOUNDATIONS FOR THE CARIBOU-TARGHEE

NATIONAL FOREST

SET-ASIDE: SMALL BUSINESS SET-ASIDE

IMPORTANT – NOTICE TO QUOTER:

AT A MINIMUM, QUOTER SHALL SUBMIT THE FOLLOWING DOCUMENTS AS THEIR RESPONSE TO THIS

SOLICITATION:

1.SF-18 Request For Quotation (Complete, date, and sign)

2.Section B – Schedule of Items (Page 2). (Complete Unit Price and Amount)

3.Section K – Representations and Certifications (Pages 30-34). (Complete the Representations and Certifications electronically via the System for Award Management (SAM) website at www.sam.gov)

4.Section J – Experience Questionnaire (Pages 28-29)

5.Section M – Technical Proposal

6. Acknowledgement of Amendment (If Any)

IT IS REQUIRED THAT YOU WRITE THE SOLICITATION NUMBER ON THE OUTSIDE OF YOUR

ENVELOPE.

Return to: IDAWY Acquisition Service Center

1405 Hollipark Drive

Idaho Falls, ID 83401

IT IS REQUIRED THAT ALL CONTRACTOR’S BE REGISTERED IN THE SYSTEM FOR AWARD MANAGEMENT DATABASE

PRIOR TO AWARD UNDER THIS SOLICITATION. SEE CLAUSE 52.204-7 SYSTEM FOR AWARD MANAGEMENT FOR

DETAILS ON HOW TO APPLY.

IT IS THE OFFERORS RESPONSIBILITY TO WATCH FOR ANY AND ALL AMENDMENTS TO THE SOLICITATION, WHICH

SHALL BE ISSUED ELECTRONICALLY THROUGH FEDBIZOPS.

AG-02NV-S-15-0064 St. Anthony Bunkhouse Foundations

Caribou-Targhee National Forest

REQUEST FOR QUOTATION PAGE OF PAGES

(THIS IS NOT AN ORDER) THIS RFQ X IS IS NOT A SMALL BUSINESS SET- ASIDE 1 41

1. REQUEST NO. 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT.DEF. RATING

AG-02NV-S-15-0064 6/22/2015

AND/OR DMS REG. 1

5a. ISSUED BY 6. DELIVER BY (Date)

IDAWY Service Center, 1405 Hollipark Dr., Idaho Falls, Id 83401 See Contract Time

5b. FOR INFORMATION CALL (NO COLLECT CALLS) 7. DELIVERY FOB DESTINATION NAME TELEPHONE NUMBER X OTHER (See Schedule)

AREA CODE NUMBER 9. DESTINATION

KELLIE SHAW 208 557-5766 a. NAME OF CONSIGNEE

8. TO: Section C - Location & Description

a. NAME b. COMPANY b. STREET ADDRESS

c. STREET ADDRESS c. CITY

d. CITY e. STATE f. ZIP CODE d. STATE e. ZIP CODE

10. PLEASE FURNISH QUOTATIONS TO THE

ISSUING OFFICE IN BLOCK 5A ON OR

BEFORE CLOSE OF BUSINESS

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5A.

This request does not commit the Government to pay any costs incurred in the preparation of the

July 22, 2015 no later than

3:00 p.m. MST submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

(a) (b) (c) (d) (e) (f) St. Anthony Bunkhouse Foundation Project , Caribou-Targhee National Forest, Fremont County, Idaho.

Price Range - Between $25,000 - $100,000

PLEASE PLACE YOUR QUOTE IN SECTION B- SCHEDULE OF ITEMS

This requirement is being procured as a fixed-price Simplified Acquisition.

Quotes received after the exact time specified for receipt of quotes will not be considered.

FACSMILE (FAX) WILL NOT BE ACCEPTED.

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS c. 30 CALENDAR DAYS d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations X are are not attached.

13. NAME AND ADDRESS OF QUOTER 14. SIGNATURE OF PERSON AUTHORIZED TO 15. DATE OF

a. NAME OF QUOTER SIGN QUOTATION QUOTATION

DUNS # _________________ CAGE CODE ____________

b. STREET ADDRESS 16. SIGNER

a. NAME (Type or print) b. TELEPHONE

c. COUNTY AREA CODE

d. CITY e. STATE f. ZIP CODE c. TITLE (Type or Print) NUMBER

NSN 7540-01-152-8084

Previous edition not usable

18-121 STANDARD FORM 18 (Rev. 6-95) Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

PART I--THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES

ST. ANTHONY BUNKHOUSE FOUNDATIONS PROJECT

Fremont County, Idaho

This solicitation and any resulting contract is a firm-fixed price type of contract, which under the definition in FAR 16.202-1, “this type of contract provides for a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract. This contract type places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss.”

Quoter’s shall submit a quote for all Base Items and all Optional Items in the Schedule of Items.

Failure to comply with the instructions may render your quote nonresponsive and ineligible for contract award.

Prices on the Schedule shall reflect Contractor’s full cost for materials, labor, supervision, overhead costs, and incidental items.

B- 1 - Schedule of Items

Pay

Item

Item Description MM* Estimated

Quantity

Pay

Unit

Unit

Price

Amount

010250 Construction Staking LSQ 1 LS $________ $________

011900 Mobilization LSQ 1 LS $________ $________

312100 Foundation Excavation &

Backfill

AQ 2 EA $________ $________

033000 Bunkhouse Foundation AQ 2 EA $________ $________

TOTAL AMOUNT QUOTED (All Items) $________

* Designated Method of Measurement:

DQ - Designed Quantities, AQ - Actual Quantities, LSQ - Lump Sum Quantities, SQ - Staked Quantities

B- 2: Quote on all items. Only quotes to the nearest cent will be accepted.

B- 3 - Note: Payment for bond premiums in accordance with FAR Clause 52.232-5, Payment Under

Fixed-Price Construction Contracts, shall not be in addition to the contract price.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C- 1 - Project Description and Location

(a) Description of Work.

This project consists of constructing a permanent foundation for a 4 bedroom-modular bunkhouse building. This project also consists of completing required earthwork and finish grading to construct a level pad for the building.

(b) Project Location.

The project is located on the Caribou-Targhee National Forest, 499 N. 2400 E. St. Anthony, Fremont

County, Idaho at an elevation of approximately 4977 feet. It is located in the SE1/4 of Section 1, T7N, R40E (latitude 43o57’18"N, longitude 111o40'45"E). The project may be accessed from The Teton

Highway.

(c) Site Visit. (See Section L, FAR Clause 52.236-27)

(d) Start Work.

It is estimated that work will begin August 15, 2015.

(e) Period of Performance. (See Section F, FAR Clause 52.211-10.)

C- 2 - Government-Furnished Property

The Government will provide the following items of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the “Government Property” FAR clause contained elsewhere in the contract. The following items will be government furnished:

None

C- 3 – Inspection of Worksite

The Contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

C- 4 – Recycling and Disposal of Refuse

With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all refuse, excess or waste materials resulting from construction operations shall become the property of the Contractor and shall be recycled and/or disposed of. All disposals shall be in accordance with federal, state, and local laws and regulations. No disposal, viewing or sale of materials and/or equipment shall be allowed on Government property.

C- 5 – Safety

During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for

Construction. Smoking will not be permitted in any building or structure.

C- 6 – Site Information and Limitations

Construction sites will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access with fencing.

C-7 – Temporary Facilities

(a) STAGING AREA: The Contracting Officer Representative shall arrange the location for exterior stockpiling of materials. The Government will provide adequate staging area as close to the job site as practicable. The Contractor shall be responsible for protecting materials stockpiled against adverse weather, damage, theft, and other risks of loss. The Government assumes no responsibility for material or equipment left in the storage area. No overnight camping will be allowed on the project site.

(b) SANITARY FACILITIES: Toilet facilities will not be provided by the Government at job sites. The

Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.

Toilet facilities shall be provided at a rate of one stool for every 10 workers assigned or working on site with a minimum of one required.

(c) WATER AND ELECTRICITY: Water and utilities are not available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.

C- 8 – Existing Utilities

The Contractor shall field verify all utility locations before digging or trenching. This shall include, but not be limited to, the use of sonic, electronic or magnetic detection devices, by noting pull box and utility box locations at the surface, use of locator services, and by potholing. Contractor shall be responsible for repairing any utilities damaged during construction at no additional cost to the Government.

C- 9 – Traffic Control and Construction Signing

No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Idaho Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the

Schedule of Items.

C-10 - Submittals

(a) Definition: Submittals - Product literature, catalog cuts, product samples, shop drawings, as-built drawings, Quality Control Plans, and other documents submitted to the Contracting Officer for information or for review and approval when required.

(b) Submittals shall be presented in two copies unless indicated otherwise. The Contracting Officer will return one copy of the submittal to the Contractor, whether approved or rejected.

(c) Salient characteristics of the materials proposed for use shall be clearly identified in the submittal. The

Project Site Superintendent shall certify that he has reviewed the submittal and has determined that the submittal is in full compliance with the requirements of the Contract. Illegible, incomplete, or uncertified submittals may be rejected.

(d) Submittals shall be approved by the Contracting Officer prior to any work being performed on the contract or materials being delivered to the job site.

(e) Review of submittals, and corrections or comments made during the review, does not relieve the

Contractor from compliance with the requirements of this Contract.

(f) Allow 14 calendar days for government review of submittals. Review time shall commence upon receipt of a satisfactory submittal certified by the Project/Site Superintendent containing all information required to completely and thoroughly evaluate the submittal. Time shall start anew for each submittal and any required resubmissions.

C-11 – Hazardous Material Identification

Submit Material Safety Data Sheets (MSDS) for any materials defined as hazardous under the most current revision of Federal Standard 313. Two copies of each MSDS shall be submitted to the Contracting

Officer no later than the delivery date of the product.

C-12 - As-Built Drawings

When Shop Drawings are required by the specifications, the Contractor shall maintain at the job site one set of contract drawings marked in red to show any deviations which are found to exist or have been made from the contract drawings. Upon completion of the work, the marked set of drawings shall be delivered to the Contracting Officer. Request for final payment will not be approved until the marked drawings are delivered to the Contracting Officer.

C-13 - AGAR 452.211-73 Attachments To Statement Of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

NOTE: Offeror’s are cautioned to carefully review these Project Specifications prior to submission of offers. All specifications contained in Section J are binding on the parties signing the contract.

SECTION E--INSPECTION AND ACCEPTANCE

E- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

E- 2 – Pre-Final and Final Inspection

a. Pre-final Inspection: The Government may, at its own discretion, conduct a pre-final inspection prior to the contractor requesting a final inspection. Any discrepancies noted shall be corrected prior to final inspection.

b. Final Inspection: When the work is ready for final inspection, the Contractor shall submit a written request for the final inspection to the duly assigned Contracting Officer’s Representative at least seven (7) days prior to the desired final inspection date. The final inspection will be performed with the Contractor by the appropriate Government personnel. If any discrepancies are noted, they shall be handled in accordance with 52.246-12.

http://www.arnet.gov/far/

SECTION F--DELIVERIES OR PERFORMANCE

F- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

52.242-14 Suspension of Work (APR 1984)

F- 2 - FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 calendar days after the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ and the

Agriculture Acquisition Regulations may be accessed at www.usda.gov/da/procure/agar/subchaph.html#11.

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.236-72 Use of Premises (NOV 1996)

H- 2 - Use of Premises

The Contractor shall comply with the regulations governing the operation of premises which are occupied and shall perform the contract in such a manner as not to interrupt or interfere with the conduct of

Government business.

H- 3 - Incidental Payment Items

The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

H- 4 - Conformity With Drawings and Specifications

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

H- 5 - Samples, Tests, Cited Specifications

Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.

H- 6 - Barricades, Warning Signs, and Other Devices

The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and

Highways, published by the Federal Highway Administration and applicable safety codes.

Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.

H- 7 - Contract Administration

(a) CONTRACTING OFFICER means a person with the authority to enter into, administer and/or terminate contracts and make related determinations and findings. The Contracting Officer signs all contractual documents, approves and signs all modifications to contracts, processes and approves payment requests, reviews and makes final decisions on contractual discrepancies, and administers the contract.

The Contracting Officer is the only authorized individual to make changes to a contract.

(b) CONTRACTING OFFICER'S REPRESENTATIVE. The Contracting Officer will designate a representative, hereinafter referred to as the Contracting Officer's Representative (COR) or, alternatively, as the Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing and a copy of the designation will be furnished to the Contractor before or at the pre-work conference. The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term "Contracting Officer" as used throughout the contract shall be interpreted to include the Contracting Officer's designated representative(s) acting within the limits of their delegation of authority.

(c) CONTRACTOR'S REPRESENTATIVE. Any representative of the Contractor shall be designated in writing. The designation shall clearly indicate the name and limitations of authority, if any, of the representative.

H- 8 – Work Schedule

A Work Schedule shall define the overall time required to perform the identified work. Each major task, including beginning time and ending time, shall be identified within the schedule. Notify the Contracting

Officer whenever there are significant departures from the approved Work Schedule. Submit any requests to modify the Work Schedule, in writing to the Contracting Officer with an explanation for the deviation.

H- 9 - Subcontract Data

The Contractor shall submit an executed Statement and Acknowledgment Standard Form 1413, to the

Contracting Officer for every subcontractor (including every subcontractor of the second or lower tier) that will be performing work at the construction site. This shall be submitted before the subcontractor begins work. This form provides an acknowledgment by the subcontractor that mandatory "flowdown" contract clauses have been included in their contract in accordance with FAR Clause 52.222-11.

Completing this form creates no contractual relationship between subcontractors and the Government.

H-10 - Site Superintendent

It shall be the responsibility of the Contractor to provide a responsible site superintendent to represent the

Contractor in the field in all matters under this contract including, but not limited to construction, day-to-day coordination of activities, control over employees and subcontractors, and coordination with local

Government personnel. The site superintendent shall be designated in writing. They shall be available on site in person to respond to any and all problems during normal working hours. The site superintendent shall be responsible for on-site Quality Control.

Site superintendent shall maintain on site a file containing the following project documents.

Executed Copy of the Contract

Contract Drawings

Contract Specifications

Quality Control Plan – (up to date)

As-Built Drawing – (up to date) if required

Work Orders

Modifications

This file shall be maintained and available to the Contracting Officer upon request. If the Site

Superintendent is replaced, the existing Superintendent shall review all documents and ongoing issues with the new Superintendent.

H-11 - Designation of Contracting Officer Representative

Prior to the commencement of work, the COR will be designated. The COR is responsible for administering the performance of the work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by the Contracting Officer prior to the completion of this contract.

H-12 – Washing Equipment

All equipment used on the site shall be cleaned and inspected off National Forest land prior to its arrival on the site. The equipment must be 1) free of all mud, seeds, plants, and plant fragments; and 2) free of oil, fuel, or toxic leaks that would wash off into the water. The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

Notify the Contracting Officer 48 hours in advance of mobilizing equipment to the site to arrange an inspection.

H-13 – Fuel Storage

A written Hazardous Spill Plan may be required for projects which involve fuel storage and refueling actions. The plan shall contain a description of the specific hazardous materials, procedures, and spill containment that will be used, including inventory, storage, and handling. All vehicles carrying fuel will have specific equipment and materials needed to contain or clean up any incidental spills at the project site. Equipment and materials will be specific to each project site, and can include spill kits appropriately sized for specific quantities of fuel, shovels, absorbent pads, straw bales, containment structures and liners, and/or booms. Storing and refueling areas will be located in staging areas away from streams in areas where a spill would not have the potential to reach live water. Containment structures may be necessary if prevention of spilled material from reaching live water cannot be assured.

Should quantities of stored fuel for a project exceed 660 gallons in a single tank; or exceed 1320 gallons for all storage combined; contractors and agency operators will be required to have a standard EPA written Spill Prevention Control and Containment (SPCC) Plan onsite, which describes measures to prevent or reduce impacts from potential spills from fuel, hydraulic fluid, etc. (40 CFR 112, Oil Pollution

Act relating to SPCC Plans).

Storage of fuel and other toxicants within Riparian Conservation Areas (RCA – within 300 feet of live streams) is prohibited. Refueling of equipment may be done within the RCA only at locations approved by the Contracting Officer (CO). Centrifugal pumps used for removing water from structure excavation shall sit in a secondary spill container with sufficient capacity to contain the quantity of fuel in the pump fuel tank. A Spill Prevention & Containment Plan is required and shall be submitted to the CO for approval prior to beginning construction. A spill containment kit shall be available on site that is to accommodate potential spills from the equipment used during construction.

H-14 - Prework Conference

Prior to commencement of work, the Contracting Officer will arrange a meeting with the Contractor to discuss the contract terms and work performance requirements. Also at this meeting such things as work progress schedule and fire prevention and suppression plans shall be developed and established in writing.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

52.204-10 Reporting Executive Compensation and First Tier Subcontract Awards (JUL 2013)

52.204-18 Commercial and Government Entity Code Maintenance (NOV 2014)

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (AUG 2013)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporation (DEC 2014)

52.219-6 Notice of Total Small Business Set-Aside (NOV 2011)

52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013)

52.222-3 Convict Labor (JUN 2003)

52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2014)

52.222-6 Construction Wage Rate Requirements (MAY 2014)

52.222-7 Withholding of Funds (MAY 2014)

52.222-8 Payrolls and Basic Records (MAY 2014)

52.222-9 Apprentices and Trainees (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (MAY 2014)

52.222-12 Contract Termination - Debarment (MAY 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related Act Regulations

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988)

52.222-15 Certification of Eligibility (MAY 2014)

52.222-20 Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000

(MAY 2014)

52.222-21 Prohibition of Segregated Facilities (FEB 1999)

52.222-26 Equal Opportunity (MAR 2007)

52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)

52.222-36 Equal Opportunity for Workers with Disabilities (JUL 2014)

52.222-50 Combating Trafficking in Persons (MAR 2015)

52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts

(SEP 2013)

52.223-3 Hazardous Material Identification and Material Safety Data (JAN 1997) Alternate I (JUL

1995)

52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011)

52.223-6 Drug-Free Workplace (MAY 2001)

52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts

(MAY 2008)

52.223-18 Contractor Policy to Ban Text Messaging While Driving (AUG 2011) http://www.usda.gov/procurement/policy/agar.html

52.224-1 Privacy Act Notification (APR 1984)

52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)

52.228-2 Additional Bond Security (OCT 1997)

52.228-11 Pledges of Assets (JAN 2012)

52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014)

52.228-14 Irrevocable Letter of Credit (NOV 2014)

52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014)

52.232-23 Assignment of Claims (MAY 2014)

52.232-27 Prompt Payment for Construction Contracts (MAY 2014)

52.232-33 Payment of Electronic Funds Transfer – System for Award Management (JUL 2013)

52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)

52.233-1 Disputes (MAY 2014) Alternate I (DEC 1991)

52.233-3 Protest After Award (SEP 2006)

52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)

52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)

52.236-5 Material and Workmanship (APR 1984)

52.236-6 Superintendence by the Contractor (APR 1984)

52.236-8 Other Contracts (APR 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984)

52.236-11 Use and Possession Prior to Completion (APR 1984)

52.236-12 Cleaning Up (APR 1984)

52.236-13 Accident Prevention (NOV 1991)

52.236-14 Availability and Use of Utility Services (APR 1984)

52.236-15 Schedules for Construction Contracts (APR 1984)

52.236-17 Layout of Work (APR 1984)

52.236-21 Specifications and Drawings for Construction (FEB 1997)

52.242-13 Bankruptcy (JUL 1995)

52.243-5 Changes and Changed Conditions (APR 1984)

52.244-6 Subcontracts for Commercial Items (MAR 2015)

52.245-1 Government Property (APR 2012) ALT I (APR 2012)

52.245-9 Use and Charges (APR 2012)

52.246-21 Warranty of Construction (MAR 1994)

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (APR 1984)

52.249-10 Default (Fixed-Price Construction) (APR 1984)

52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.224-70 Confidentiality of Information (FEB 1988)

452.236-73 Archeological or Historic Sites (FEB 1988)

452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)

452.236-76 Samples and Certificates (FEB 1988)

452.236-77 Emergency Response (NOV 1996)

I- 2 – FAR 52.204-12 Data Universal Numbering System Number Maintenance (DEC 2012)

(a) Definition. “Data Universal Numbering System (DUNS) number,” as used in this clause, means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities, which is used as the identification number for Federal contractors.

(b) The Contractor shall ensure that the DUNS number is maintained with Dun & Bradstreet throughout the life of the contract. The Contractor shall communicate any change to the DUNS number to the

Contracting Officer within 30 days after the change, so an appropriate modification can be issued to update the data on the contract. A change in the DUNS number does not necessarily require a novation be accomplished. Dun & Bradstreet may be contacted—

(1) Via the internet at http://fedgov.dnb.com/webform or if the Contractor does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or

(2) If located outside the United States, by contacting the local Dun and Bradstreet office.

I- 3 – FAR 52.204-13 System for Award Management Maintenance (JUL 2013)

(a) Definitions. As used in this clause—

“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and

Bradstreet, Inc. (D&B) to identify unique business entities, which is used as the identification number for

Federal contractors.

“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts

(see the FAR at subpart 32.11) for the same concern.

“Registered in the System for Award Management (SAM) database” means that—

(1) The Contractor has entered all mandatory information, including the DUNS number or the

DUNS+4 number, the Contractor and Government Entity (CAGE) code, as well as data required by the

Federal Funding Accountability and Transparency Act of 2006 (see Subpart 4.14), into the SAM database;

(2) The Contractor has completed the Core, Assertions, Representations and Certifications, and

Points of Contact sections of the registration in the SAM database;

(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer

Identification Number (TIN) with the Internal Revenue Service (IRS). The Contractor will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and

(4) The Government has marked the record “Active”.

“System for Award Management (SAM)” means the primary Government repository for prospective

Federal awardee and Federal awardee information and the centralized Government system for certain contracting, grants, and other assistance-related processes. It includes— http://fedgov.dnb.com/webform

(1) Data collected from prospective Federal awardees required for the conduct of business with the

Government;

(2) Prospective contractor-submitted annual representations and certifications in accordance with

FAR Subpart 4.14; and

(3) Identification of those parties excluded from receiving Federal contracts, certain subcontracts, and certain types of Federal financial and non-financial assistance and benefits.

(b) The Contractor is responsible for the accuracy and completeness of the data within the SAM database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the SAM database after the initial registration, the Contractor is required to review and update on an annual basis, from the date of initial registration or subsequent updates, its information in the SAM database to ensure it is current, accurate and complete. Updating information in the SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(c) (1)

(i) If a Contractor has legally changed its business name, doing business as name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in subpart 42.12, the Contractor shall provide the responsible

Contracting Officer a minimum of one business day's written notification of its intention to—

(A) Change the name in the SAM database;

(B) Comply with the requirements of subpart 42.12 of the FAR; and

(C) Agree in writing to the timeline and procedures specified by the responsible

Contracting Officer. The Contractor shall provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (c)(1)(i) of this clause, or fails to perform the agreement at paragraph (c)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.

(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the SAM record to reflect an assignee for the purpose of assignment of claims (see FAR subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the SAM. Information provided to the Contractor’s SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the EFT clause of this contract.

(3) The Contractor shall ensure that the DUNS number is maintained with Dun & Bradstreet throughout the life of the contract. The Contractor shall communicate any change to the DUNS number to the Contracting Officer within 30 days after the change, so an appropriate modification can be issued to update the data on the contract. A change in the DUNS number does not necessarily require a novation be accomplished. Dun & Bradstreet may be contacted

(i) Via the internet at http://fedgov.dnb.com/webform or if the contractor does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United

States; or

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office.

(d) Contractors may obtain additional information on registration and annual confirmation requirements at https://www.acquisition.gov.

I- 4 - AGAR 452.209-71 Assurance Regarding Felony Conviction Or Tax Delinquent Status For

Corporate Applicants (FEB 2012) Alt I (FEB 2012)

(a) This award is subject to the provisions contained in the Consolidated Appropriations Act, 2012 (P.L.

No. 112-74), Division E, Sections 433 and 434 regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –

(1) does not have a tax delinquency, meaning that it is not subject to any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and

(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered suspension or debarment of the awardee, or such officer or agent, based on these convictions and/or tax delinquencies and determined that suspension or debarment is not necessary to protect the interests of the Government.

(b) If the awardee fails to comply with these provisions, the Forest Service may terminate this contract for default and may recover any funds the awardee has received in violation of sections 433 or 434.

I- 5 - FAR 52.225-9 Buy American Act-Construction Materials (MAY 2014)

(a) Definitions. As used in this clause—

“Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the

Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy

American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)).

The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

http://uscode.house.gov/ https://acquisition.gov/far/current/html/Subpart%2012_5.html#wp1077123

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

NONE

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than

6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United

States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the

Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description Unit of Measure Quantity Price (Dollars)*

Item 1:

Foreign construction material _______ _______ _______

Domestic construction material _______ _______ _______

Item 2: _______ _______ _______

Foreign construction material _______ _______ _______

Domestic construction material

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

I- 6 - FAR 52.228-13 Alternative Payment Protections (JUL 2000)

(a) The Contractor shall submit one of the following payment protections:

(1) Payment Bond

(2) Irrevocable Letter of Credit (ILC)

(3) Money orders, drafts, cashier’s checks, or certified checks.

(b) The amount of the payment protection shall be 100 percent of the contract price.

(c) The submission of the payment protection is required within 10 days of contract award.

(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.

(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the

Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.

(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.

I- 7 - AGAR 452.228-70 Alternative Forms of Security (NOV 1996)

If furnished as security, money orders, drafts, cashier's checks, or certified checks shall be drawn payable to: USDA Forest Service.

I- 8 – FAR 52.232-40 Providing Accelerated Payment to Small Business Subcontractors (DEC 2013)

(a) Upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract, to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, after receipt of a proper invoice and all other required documentation from the small business subcontractor.

(b) The acceleration of payments under this clause does not provide any new rights under the Prompt

Payment Act.

(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial items.

I- 9 – FAR 52.236-7 Permits and Responsibilities (NOV 1991)

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor's fault or negligence. The

Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may…