This document is a First Article Requirements Form (AFMC IMT 260) for a federal contract opportunity. The key details are:

The contract is for 1 unit of an F-16 Fuel Cell (NSN 1560012240803WF) as a first article. The first article must be manufactured at the same facilities as the production quantity and will serve as a manufacturing standard. Contractor testing and a test report are required, with the Government having 90 days to approve or disapprove the first article after receipt. The first article is due within 270 calendar days of contract award. The first article may be waived if the offeror has previously provided satisfactory production quantities of the same or similar article to the Air Force within the last 36 months. The contracting office is the Air Force Sustainment Center, and the item is export controlled.

View the file

Other files

File Type Posted
DDFORM_1423-1.pdf PDF
Item_Description.pdf PDF
Packaging_SOW.pdf PDF
IUID.pdf PDF
AFMC807_Quality_Assurance_Inspection_Requirements.pdf PDF
DD1653_Transportation_Data.pdf PDF
MANUFACTURING QUALIFICATION REQUIREMENTS Section C.pdf PDF
AFMC158_Packaging_Requirements.pdf PDF
Solicitation FA821225Q0001.pdf PDF
Engineering_Data_List.pdf PDF
SPI.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRST ARTICLE REQUIREMENTS 1. DATE

20 JUL 2023(AFMCI 23-110, AFMCDAFI 20-102, and FAR, Subpart 9.3) (additional instructions on page 3)

2. PR / MIPR NUMBER 3. CAGE / REFERENCE NUMBER

81755 / 16VB004002-7

4. NSN

1560012240803WF

5. FIRST ARTICLE QUANTITY

THE FIRST ARTICLE IS 1 UNIT(S) OF LOT / ITEM 1

AND WILL BE: X PART OF PRODUCTION QUANTITY IN ADDITION TO PRODUCTION QUANTITY

6. ARTICLES

WILL X WILL NOT SERVE AS A MANUFACTURING STANDARD

7. LONG LEAD TIME ITEMS

REQUIRED X NOT REQUIRED

(See FAR 52.209-3 OR -4, alternate II)

8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 OR -4 Alternate I)

X REQUIRED NOT REQUIRED

"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."

9. TEST / INSPECTION REQUIREMENTS

A.

X

CONTRACTOR TESTING

GOVERNMENT TESTING

Performance or other characteristics which the First Articles must meet are

Conformance with drawings, mylars, and engineering instructions

B. The detailed technical requirements for First Article approval tests are contained in drawings, mylars, and engineering instructions

(Cite Spec and Para number)

C. TEST PLAN REQUIRED

(3) Number of days for government approval / disapproval days.

(1) DD Form 1423 ELIN

(2) Delivery due calendar days from date of contract.

D. Contractor's notification to ACO and

(Requesting Activity) of test time and location due days prior to start of testing.

E. X TEST REPORT REQUIRED

(3) Forwarded to

Deliver concurrent with FA asset

(4) Government written notice of approval / disapproval due

(2) Due

(1) DD Form 1423 ELIN days after receipt of contractor's report.90 calendar days from date contract.

AFMC IMT 260, 20230316, V-5,

Version 8Generated by PRPS using Jasper Reports on 25 Sep 2024

PREVIOUS EDITION IS OBSOLETE

Prescribed by: AFMCI23-110

F. FIRST ARTICLE DELIVERY

(1) Due within 270 calendar days from date contract.

(2) Notify 30 calendar days prior to shipment.

(3) Delivered to government at

See Block 12

(Set Forth Consignee and Address)

(4) Government written notice of approval / disapproval within 90 days after receipt of first article package.

G. Estimated cost of government testing / inspection evaluation.

$10,000.0000

10. DISPOSITION OF FIRST ARTICLES

X Approved First Articles will be forwarded to

Supply

(insert quantity) First Articles will be expended in testing. Residual components of disapproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.

First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.

X Disapproved First Articles will be returned to the contractor

X will be retained by MXDEB pending disposition instructions from the contractor.

X On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).

a. Approved First Articles will be returned to the contractor for shipment with production item.

b. Disposition of disapproved First Articles will remain the same as marked above.

Other Disposition:

11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL

a. X Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the Government, DoD, X Air Force.

b. X Offerors currently in production of the same or similar article for a Government, DoD, X Air Force contract and who have received First Article approval under the existing contract.

c. X Offerors who have previously furnished production quantities of the same or similar articles to the Government, DoD, X Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.

d. X Provided not more than 36 months have elapsed since completion of the contract.

e. First Article testing will not be waived.

f. See Remarks in block 12 below.

NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED ARTICLE:

A. PROCURING OFFICE B. CONTRACT NUMBER C. DATE OF CONTRACT D. SPECIFICATION NUMBER AND REVISION

AFMC IMT 260, 20230316, V-5,

Version 8Generated by PRPS using Jasper Reports on 25 Sep 2024

12. REMARKS

Slaughter, George PNAME: 06 JUL 2023DATE:

Deliver to:

809 MXSS/MXDEB

Bldg 849 Attn: Non-Accountable Bay Hill AFB, UT 84056-5713 Mark for First Article Do Not Post

First article will be waived for the OEM, Lockheed Martin, cage 81755. First article testing is necessary for this part due to critical dimensions. This part is structurally significant in a critical safety item and must therefore meet the drawing specs to ensure proper fit and function.

13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR APPROVING

(Name, Organization, Phone)

Slaughter, George P

416 SCMS/GUEAA

801-586-5444

586-5444

14. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR CONDUCTING

TEST (Name, Organization, Phone)

First Article Lab

809 MXSS/MXDEB

X

X

AFMC IMT 260, 20230316, V-5,

Version 8Generated by PRPS using Jasper Reports on 25 Sep 2024

File details come from the government source that posted it. Updated .