AF151-168: Strip Solutions to Optimize the Stripping of Plating and Thermal Spray Coatings

PROJECTED CMMC LEVEL REQUIREMENT:

N/A

TECHNOLOGY AREAS:

Materials

MODERNIZATION PRIORITIES:

KEYWORDS:

strip plasma coatings, nickel plating, chrome plating, silver plating

ADDITIONAL INFORMATION

OBJECTIVE:

Research, develop, and validate stripping solutions used at Tinker AFB, Okla., to establish operating limits of solutions and stripping procedures that result in the best stripping rate.

DESCRIPTION:

Stripping solutions are used at Tinker AFB to remove coatings such as nickel plating, chrome plating, silver plating, and numerous types of thermal spray coatings. Research of these solutions is required to further optimize the stripping rate of these solutions to decrease flow days and increase life of part through minimizing part time in solution. Contaminants in stripping solutions are inevitable throughout the use of the solution, but they can greatly affect the stripping efficiency of the stripping solutions over time. More information is needed on these saturation limits to determine when it is cost effective to continue running and when it is cost effective to replace the solution. Research effort needs to be performed to provide innovative solution to address the above that result in reduced time to remove coating material in strip processes while optimizing all inputs that contribute to the best process. Solution should address any appropriate environmental reductions and insure no health concerns will be an issue.

PHASE I:

Research and develop concept of the innovative technical approach and report on how the approach will be applied to satisfy the Topic requirement. Final Phase I report should document concept and include a Phase II methodology development plan if selected for a Phase II contract.

PHASE II:

Continue the research and development of technology concept presented during Phase I for a prototype demonstration in an AFSC Complex facility and demonstrate the commercial viability of the approach.

PHASE III DUAL USE APPLICATIONS:

Dual application for both military and commercial aviation maintenance depots.

REFERENCES:

Technical Order 2-1-1-11.1.

Process Order 86-005.2.

TECHNICAL POINT OF CONTACT (TPOC):