AE SOW PNQS 24-2543 Int_Ext Refresh Bldg 842.pdf

PDF 114 KB Posted

Attached to
PNQS 24-2543 Int/Ext Refresh 842, Maxwell AFB (Sources Sought)
Solicitation number
PNQS242543
Issued by

About this file

This is an Architect-Engineer Statement of Work (SOW) for project PNQS 24-2543 requiring architectural-engineering services for interior and exterior refresh of Building 842 at Maxwell Air Force Base, Alabama. The scope includes refinishing the building's exterior, conducting a lead-based paint survey for the interior, designing interior refinishing, repairing west-facing hangar doors and a man door, repairing interior building unit wall finishes, and providing solutions for an overflowing HVAC drain pan in the Honor Guard compartment.

The A-E firm must complete all design work within 90 days of Notice to Proceed, with submittals required at 95% (70 days) and Ready to Advertise (RTA) stages (90 days). Deliverables include construction drawings, specifications, design analyses, cost estimates, submittal registers, and other documentation, with specific requirements for electronic formats (AutoCAD 2024, MS Word 2010, PDF) and physical copies. The A-E must provide Level 5 cost estimates as defined by the Whole Building Design Guide, use Master Format 2018 specifications, and comply with all applicable codes, standards and environmental requirements including DOD Green Procurement Program policies. The technical monitor for this project is Sandra Bredlow at Maxwell AFB Civil Engineering Squadron.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A/E-SOW

ARCHITECT-ENGINEER STATEMENT OF WORK

PNQS 24-2543 Int/Ext Refresh 842, Maxwell AFB

1.0 INTRODUCTION

Maxwell AFB 42CES/CEN has a requirement for a Subcontractor to provide Architectural-

Engineering services for:

PNQS 24-2543 Int/Ext Refresh 842, Maxwell AFB

1.1 The Service provider (Architect/Engineer) will perform all design work necessary to accomplish the work indicated herein and in accordance with Appendix A, Performance Requirements for

Architect-Engineering Services, except as modified herein. Provide all plant, labor, equipment and materials required to complete the project and deliver to Maxwell AFB complete project documents, including but not limited to: construction drawings, specifications, design analyses, cost estimates, construction submittal register, drawing list, specification list, bid schedules, product and material technical data sheets, and working sketches. For 65% drawing and specification submittals, the A-E shall deliver two sets of bound half-size drawings and one set of bound specifications along with drawings and specifications in electronic format stored on

CD. For 100% drawings and specifications submittals, the A-E shall deliver three sets of bound half-size drawings and three sets of bound specifications along with drawings and specifications in electronic format stored on CD. All RTA final construction drawings shall be delivered as three sets of bound half-size copies and in electronic format stored on CD. All

Mechanical Drawings shall be stamped by the Mechanical Engineer. Drawings shall be delivered in a useable electronic format as an AutoCAD “.dwg” file, 2020. All RTA final specifications shall be delivered three sets bound and in electronic format in both MSWord

2010 (.docx) and Adobe PDF format stored on CD. Design analyses shall be delivered in two bound sets at all junctures of the project time frame. Cost estimate and submittal register shall be delivered in two bound sets and in electronic format stored on CD with the all submittals.

1.2 All work is to be performed in accordance with this SOW (Statement of Work).

1.3 Consultants. The A-E will be required to have as an integral part of the firm, or shall be able to obtain the services of, registered professional engineers and registered Architects established in various disciplines to support the subject project. The use of consultants will be determined by the A-E with all coordination, control, payment and scheduling responsibilities belonging to the A-E. The A-E shall make the consultants aware of the scope of the work and shall be responsible for the accomplishment of the work in accordance with all related standards, regulations, instructions, directions, and adopted codes that are pertinent to Maxwell AFB, AL and as described under 3.0 herein.

Cost Estimates:

All cost estimates will be a ‘LEVEL 5’ cost estimate as defined by the Whole Building Design

Guide.

Cost Estimating | WBDG - Whole Building Design Guide https://www.wbdg.org/design-disciplines/cost-estimating

The purpose of this level of estimate is to develop probable costs in the preparation and submittal of bids for contract. This will be provided with 65%, 100%, and RTA submittal.

Include a complete and thorough "Scope of Estimate" statement that would state clearly such items assumptions, allowances, documents used for the estimate, and contingency amounts included.

https://www.wbdg.org/design-disciplines/cost-estimating

Specifications:

All specifications will be in the format of Master Format 2018.

Specifications will be in line with the specifications at the Whole Building Design Guide website. https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

SpecsIntact software is an automated system for preparing standardized facility construction specifications used worldwide by National Aeronautics and Space Administration (NASA), the

U.S. Naval Facilities Engineering Command (NAVFAC), and the U.S. Army Corps of

Engineers (USACE). The SpecsIntact software is government funded and does not require or provide an End Users Agreement (EULA) therefore, can be downloaded and installed on an unlimited number of computers free of charge.

This software produces the specifications that are available on WBDG site, except that they are editable and customizable. Information and software download is available at the link below.

https://www.wbdg.org/dod/specsintact/software?

1.4 The Service provider (Architect/Engineer) shall furnish and provide for the contracting officer the quality and quantity of service per Section 4 of this Statement of Work.

2.0 ACRONYMS/DEFINITIONS:

A-E = Architect/ Engineer

ASHRAE = American Society of Heating, Refrigerating and Air Conditioning Engineers

CHWP= Chilled Water Pump

CHWR= Chilled Water Return

CHWS= Chilled Water Supply

COE = Corps of Engineers

CWP= Condenser Water Pump

CWR= Condenser Water Return

CWS= Condenser Water Supply

DDC = Direct Digital Control

NTP = Notice to Proceed

SMACNA = Sheet Metal and Air Conditioning Contractors National Association

SOW = Statement of Work

VFD = Variable Frequency Drive

3.0 APPLICABLE SPECIFICATIONS/STANDARDS/RELATED STUDIES:

3.1 Applicable Publications, Laws and Regulations, and Instructions, ETC.:

3.1.2 Latest Edition of the following Codes & References

a. ASHRAE Std 62

b. ASHRAE Std 90.1

c. SMACNA Duct Construction Standards

d. American with Disabilities Act and Architectural Barriers Accessibility Guidelines

e. National Fire Protection Association Codes and Standards.

f. National Fire Protection Association 101, Life Safety Code

g. International Building Code

h. International Mechanical Code

i. International Fuel Gas Code

j. International Plumbing Code https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.wbdg.org/dod/specsintact/software

k. ASHRAE Handbook of Fundamentals; Handbook of HVAC Systems and Equipment;

Handbook of HVAC Applications; and Handbook of Refrigeration

l. National Electric Code

m. UFC, DOD Minimum Antiterrorism Standards for Buildings, UFC 4-010-01

4.0 TASK DESCRIPTION

4.1 Background Information & Location – this work will be located on Maxwell AFB building 842.

4.2 Description of Services: This description of services provides the A/E with a basis to develop the design intent as proposed. The SOW is not intended to be a complete and concise description of all the details required in the work effort. The determination of all applicable constraints on the project and the refinement of the intent as indicated in the

SOW are the responsibility of the A/E. AE must meet with the Project Manager to review the Scope of Work prior submitting proposal. Service provider (Architect/Engineer) must contact 42CES/CEN sandra.bredlow.ctr@us.af.mil, before scheduling a kick-off meeting for the project design.

The A/E is to design for, Refinishing the exterior of the facility. A Lead Based paint survey will need to be completed for the interior of this facility. Design the interior refinishing of the facility.

This is a Hangar that was built in 1931.

The west facing hangar doors need to be repaired.

A man door on the same side needs to be repaired so entry can be secured.

Inside the building are interior building units, see appendix B photo, the finish on those walls needs repair or a better solution.

The interior compartment that houses the Honor Guard has a HVAC unit on its roof, solutions for the HVAC drain pan overflowing is needed for this area.

STANDARD PROJECT REQUIREMENTS

*ALL FORMS AND SOW MUST BE INCLUDED IN BID PACKAGE AND WILL BE

FURNISHED BY SANDRA BREDLOW IN CE

1. 01000 General Requirements

2. AF Form 66

3. Spec Section 1305 Submittal Procedures

4. AF Form IMT 3000

5. Contractor's HAZMAT Questionnaire Form ESH-ESH-FM-002.

6. Contractor's Environmental Reporting Entry Form ESH-ESH-FM-003

7. Recycling and Landfill Report

8. 13279A Asbestos Protocol/13280 Asbestos Spec

9. Updated Signature Block

10. Cost Estimate Form

11. Project signage requirements and location of contractor trailer information

4.3 This description of services provides the A/E with a basis to develop the design intent as proposed. The SOW is not intended to be a complete and concise description of all the details required in the work effort. The determination of all applicable constraints on the project and the refinement of the intent as indicated in the SOW are the responsibility of the A/E.

4.4 Performance of Work

4.4.1 Performance Period. Complete design shall be completed within 90 days from NTP.

The definition of complete work shall mean that all design stages have been accomplished, all reviews required herein have been completed, all comments made by the user/42CES/CEN are incorporated into the construction documents, and all documents are ready for advertisement and the bidding process.

4.4.2 Schedules: The A-E shall provide a schedule that indicates the start of the performance period, the review milestones, and the completion date. If the contract is modified to adjust the completion date the A-E shall submit a revised schedule to Contract

Administrator within one day of the signed modification to the original delivery order clearly indicating the original performance period and the new completion date.

4.4.3 Submittal Milestones. The A-E shall submit the following design documents and supporting elements for the subject project in the following sequence. Note that all time elements are in reference to the date the purchase order is received by the A-E, which hereafter shall be referred to as NTP (Notice to Proceed):

A. 35% Design Charrette---------------------------------------------------- N/A

B. 65% Design Documentation-------------------------------------------N/A

C. 95% Design Documentation-------------------------------------------70 Days after NTP

D. RTA Design Documentation------------------------------------------90 Days after NTP

4.4.4. The design documents submitted by the A-E will be reviewed by various agencies located on Maxwell AFB to verify that Air Force requirements are reflected in the design.

The A-E shall be held responsible for ALL requirements particular to the project being designed. 42CES/CEN shall only act as a regulatory body specifically there to provide the

A-E with direction on relevant regulations, standards, codes, and public laws that impact the subject project. The A-E shall determine how all of these elements guide and control the resultant design.

4.5 REVIEW PROCESS.

4.5.2 Upon completion of the 65% milestone the A-E shall submit the design package in the quantities indicated to the agencies listed in paragraph 5.1. Drawings shall be half-scale. The review process shall take 10 working days after receipt of the package and will generate written documents stating 42CES/CEN / user’s observations, questions and comments. The review time indicated is concurrent with the performance period time line indicated in paragraph 4.4.3.

4.5.3 Upon completion of the 100% milestone the A-E shall submit the design package in scale. The review process shall take 10 working days after receipt of the package and will generate written documents stating 42CES/CEN / user’s observations, questions and comments. The review time indicated is concurrent with the performance period time line indicated in paragraph 4.4.3.

4.5.4 Upon completion of the RTA milestone, the A-E shall submit the design package in scale. The original specifications, drawing list, specification list, and Submittal Register shall be printed on one side of each page. All drawings, including CAD files, specifications and cost estimate shall be provided to 42CES/CEN on compact disks. Both

CD and shall be labeled with project name, no., submittal phase, date and A/E name. The

Construction Cost Estimate and Annotated Comments shall be submitted in separate bound copies with Title Cover Sheets.

4.5.5 Note: The A-E shall attach a letter to each RTA design level addressee above that indicates the project number and name, the using organization, the project location, and state that all comments be forwarded to Ms. Sandra Bredlow at the address indicated in #1 on the list within 5 working days from the date on the A-E’s letter.

4.5.6 Specifications. A sample format will be given to the A-E. There shall be no reference to the “owner”, “Architect”, “Engineer” etc. in specifications. The only entity authorized to obligate government funds and negotiate with a contractor is 42 Contracting

Squadron’s Contracting Officer and shall be used in place of all references to an individual, except where the term “Contractor” is used.

We are now required to use the Master format 2018. SpecsIntact is an automated

Specification Management System and is the latest generation of software for preparing facility construction specifications used worldwide by NASA, the Naval Facilities

Engineering Command (NAVFAC), U.S. Army Corps of Engineers (USACE) and Air

Force Civil Engineer Center. SpecsIntact utilizes Master guide specifications prepared by the Government agencies, which is at the hear of what makes the system unique.

SpecsIntact is a free download at https://specsintact.ksc.nasa.gov/Software/Software.sht

4.5.7 Specification References. Provide in both MS-word (.docx) and PDF format (PDF @

RTA only). All references to industry standards such as ASTM, ANSI, Fed Spec, etc. shall be dated. Only references specifically applicable to the subject project shall be included in the specifications.

4.5.8 Warranty & Guaranties. All items that carry a warranty longer than the one-year warranty provided for in the Federal Acquisition Regulations shall be covered by a warranty paragraph in the specifications that reflects the extended warranty period.

4.5.9 Proprietary References. Federal projects are required to provide open competition for all products that serve the intended function and fulfill the performance requirements stated in the construction documents. The A-E shall provide performance specifications whenever possible and use reference specifications when necessary. If the work requires the use of proprietary specifications the A-E shall provide 42CES/CEN with a Sole Source justification letter that explains why a particular product is the only one that can perform the intended function. When reference specifications are used provide the name and address of the manufacturer used as a basis for the design. Qualify the use of a single manufacture name by stating, “any reference to a specific manufacture is intended to set minimum standards, configuration, and appearance, and not to restrict competition of equal or better manufacturers and products. The A-E shall provide 42CES/CEN project manager with a cut sheet from the manufacture that describes all the salient features of the product being specified.

4.6 Green Procurement.

4.6.1. In order to comply with federally mandated environmental preference programs and

Department of Defense (DOD) “Green Procurement Program” (GPP) policy, Maxwell-

Gunter AFB requires the use of environmentally preferable products and services. These program elements include; recovered material products, energy and water efficient products, alternative fuels and fuel efficiency, bio-based products, non-ozone depleting substances, priority chemicals, and environmentally preferable products.

4.7 Asbestos. The A-E shall not specify asbestos containing materials in the work. In those instances that removal of asbestos containing materials is required a comprehensive specification meeting the requirements and conditions of the federal government will be required. A sample specification will be given to the A-E.

4.8 Drawing Notes. A sample title sheet will be given to the A-E. Ensure that the following is on the title sheet:

“ALL DRAWINGS ARE DIAGRAMMATIC AND ARE INTENDED TO QUANTIFY THE

MATERIALS SPECIFIED AND INDICATE THEIR INTENDED RELATIONSHIP TO EACH

OTHER. THE DRAWINGS ARE NOT TO BE SCALED. THE VARIOUS SCALES USED ON THE

DRAWINGS MAY NOT ALLOW FOR ALL FITTINGS, OFFSETS, AND ACCESSORIES THAT

MAY BE REQUIRED TO COMPLETE THE WORK. THE CONTRACTOR SHALL CAREFULLY

INVESTIGATE THE CONDITIONS THAT WOULD AFFECT THE WORK TO BE PERFORMED

AND SHALL ARRANGE SUCH WORK AS NECESSARY TO COMPLY WITH THE INTENT OF

THE CONSTRUCTION DOCUMENTS.”

4.9 Designs In Inch-Pound. This requires the use of inch-pound measurements in criteria, design, and specification documents for facility projects. When dual units are needed present International

System of Units (SI) designations first, followed by the inch-pound (IP) designation in parenthesis.

4.10 42CES/CEN Provided Materials. 42CES/CEN will provide hard copies of the subject building listed above from archive drawing files and other drawings selected by the A-E. The archive files are located in the Civil Engineering administrative building, 400 Cannon Street. The A/E will be required to retrieve all necessary drawings from the archives vault & reproduce them on site. We will also provide blank electronic copies of a submittal register (AF Form 66), a cost estimate form

(AF Form 3053), Tri-Services drawing format, title sheet, sample specification format, sample specifications for General Requirements, Schedule of Material, Submittal Procedures, and

Recycled / Recovered Materials.

4.11 Drawing Data

a. Drawing sheet size to be 11”x 17” with (Tri-Services Standards border)

b. Drawings shall be AutoCAD 2024

c. Pen settings shall be (Tri-Services Standards line weights/colors or as directed by

42CES/CEN).

In addition to other title block information, the following data shall be on each drawing sheet: (As appropriate)

Project Number: PNQS 24-2543

Project Title: PNQS 24-2543 INT/EXT REFRESH 842, MAXWELL AFB

5.0 DELIVERABLES:

5.1 Submittal Requirements. All submittals shall be hand delivered or express mailed to the following office:

6.0 TECHNICAL MONITOR:

Sandra Bredlow

400 Cannon Street, Bldg 1060

Maxwell AFB, AL 36106

(334) 953-3563 sandra.bredlow.ctr@us.af.mil

Receiving Office Percentage of Design Quantity of Doc. Sets

Sandra Bredlow

400 Cannon Street

(Bldg 1060)

Maxwell AFB, AL 36112-6523

Attn: Sandra Bredlow

65%

95%

RTA

2 spec originals &

2 set plans (+1 pdf copy)

2 spec originals &

2 set plans (+1 pdf copy)

1 CD includes spec originals & set plans, also

CAD files, pdf copies et al.

2 paper copies of spec originals & 2 set plans mailto:sandra.bredlow.ctr@us.af.mil