This document is a presolicitation notice for architectural and engineering services for a design project at the Lebanon VA Medical Center. The scope of work includes providing investigative and feasibility design services, schematic design development drawings, construction documents, bid documents, specifications, calculations, cost estimates, narratives, and construction period services for improvements to campus roads, parking areas, and traffic flow.

The anticipated period of performance for design completion is 307 calendar days. Interested firms should submit Standard Form 330 statements of qualifications by September 16, 2022. A two-phase evaluation process will be conducted, with the first phase involving an assessment of SF330 submissions and the second phase consisting of interview presentations for shortlisted firms. The project has a small business set-aside for Service-Disabled Veteran-Owned Small Businesses. The design contract is expected to be awarded on or before December 31, 2022. Construction period services will be an option exercised after construction award.

View the file

Other files for this federal contract opportunity

Other files attached to C1LB--Pave and Modify Loop and Parking Phase II Design, newest first.
File Type Posted
36C24422R0121_1.docx DOCX document
36C24422R0121.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lebanon VA Medical Center Lebanon, Pennsylvania

ARCHITECT/ENGINEER SCOPE OF WORK

FOR

Pave & Modify Loop Parking Phase II

595-23-602

Bid Documents ready by: 307 Calendar Days after Notice to Proceed Contracting Officer: Karen Callahan Contracting Officer’s Representative (COR): Nicholas Bierman

-- Services --

Provide professional Architect/Engineer (A/E) services to include:

• Conduct site investigations - architectural, structural, mechanical, electrical, plumbing, site surveys, etc.

• Construction drawings and develop specifications

• Provide a 3rd Party cost estimates

• Provide a cost estimate of expected construction cost as per the schedule of values at the end of each phase

• Provide construction period services - review of submissions, provide recommendations regarding contractor change proposals, visit site per VA's request and add to drawings as-built conditions from contractor's record drawings and VA correspondence during construction.

A/E shall review all construction change orders and provide an independent cost estimate on each change order request. A/E shall respond on site within a two-hour period when requested and shall provide site visits as requested during construction.

• Develop an Infection Control Risk Assessment (ICRA) including a drawing and specification

-- Project Scope --

GENERAL OVERVIEW:

Provide a full set of construction drawings and specifications to make multiple improvements to campus traffic flow with a concentration on the main loop road and adjacent parking areas. Design shall reroute the roadway away from Building 18 and new addition of parking lot in front of Building

17. Design shall include an additional loop to prevent traffic bottlenecks. Remove Flagpole Loop in front of Building 1 and relocate the West Entrance and screening including a curb island with painted tapers..

SPECIFIC REQUIREMENTS:

This project involves site preparation and construction of several new portions of roadway on the campus roadway loop as well as milling and repaving the existing roadway and adjacent parking areas with new line and crosswalk painting. Parking areas along the loop will be improved and repainted.

• Provide a full set of construction documents for the project.

• Project shall create a new “b” shaped loop, to prevent traffic congestion.

• Project shall improve traffic flow and enhance our ability to conduct in-vehicle screening of drivers and passengers at our West entrance. This may require roadway widening and re-construction.

• The loop shall always be maintained allowing traffic to circumnavigate the campus in either direction.

• Existing roadways shall have a new bituminous wearing surface installed to match the grades of the existing parking lots and access points along the loop. Much of the campus roadway has concrete curbs with integral gutters that have been overlaid with asphalt pavement and so milling will be required in many areas.

• Where the road needs widening or where the base or sub-base has failed, grade and widen the existing surfaces down to acceptable soils for sub-grade or to a depth acceptable for emplaced sub-grade materials for new portion of roadway.

• All lines, crosswalks, and other markings on the bituminous roadways shall be repainted in accordance with current VA policies and standards.

• Project shall include new sidewalks and curbs where required by the addition of new paved areas or the repaving of existing road areas.

• Project shall demolish the closed portion of any roadway and return it to a green space.

• Changes to other utilities, including, but not limited to water, storm drainage, lighting, electrical, gas lines, and other underground utilities as required by the alterations to the driveways and parking lots.

• VA Physical Security standards shall be incorporated into the design as per Physical Security Design Manual for VA Mission Critical Facilities (JANUARY 2015).

• Other options as determined by design meetings for efficient delivery of service.

SCHEDULE:

Submit review package so they are received on or before the noted day. All days below are calendar days. The issuance of the Notice to Proceed (NTP) shall be the first PDT Meeting. A/E shall be required to attend and take minutes of each Project Design Team (PDT) Meeting.

Minutes shall be submitted electronically to the COR and Contracting Officer within three (3) business days of each meeting.

Initial Project Design Team (PDT) Meeting Day 0

Schematic Submission 28 Days after Initial PDT meeting

Government Review 21 Days after receipt

Design Development 1 (DD1) – 35% Design 60 Days after Schematic Approval

Government Review 21 Days after receipt

Design Development 2 (DD2) – 65% Design 45 Days after DD1 Approval

Government Review 14 Days after receipt

Construction Documents 1 (CD1) – 95% Design

45 Days after DD2 Approval

Government Review 14 Days after receipt

Construction Documents 2 (CD2) – 100% Design

30 Days after CD1 Approval

Government Review 14 Days after receipt

Bid Documents 15 Days after CD2 Approval

Total 307 Days

GENERAL REQUIREMENTS:

• Use the latest VA Master Construction Specifications (PG-18-1), supplemented by the Lebanon VAMC specific sections 01 00 00 General Requirements and 01 35 26 Safety Requirements. Where an appropriate specification does not exist, create a specification in the same format and ensure that it is not proprietary to a single manufacturer.

• Perform all services in accordance with the current VA Design and Construction Procedures

(PG-18-3)

• Perform all services in accordance with the current VA Building Information Modeling (BIM) Manual and current VA Drawing Deliverable Requirements (PG-18-4):

https://www.cfm.va.gov/til/projREq.asp

• Perform all services in accordance with the current VA Equipment Guides and Planning Information (PG-18-5):

• All designs shall be compliant with space criteria referenced in VA space planning criteria (PG-18-9): http://www.cfm.va.gov/til/space.asp

• Perform all work in accordance with current VA Design Manuals in PG-18-10, including Physical Security and Resiliency. If a section of one of the manuals cannot be met, the A/E shall notify the VA immediately, and assist the VA in the waiver process. These design manuals are supplemented by Lebanon VAMC specific design criteria.

https://www.cfm.va.gov/til/projREq.asp http://www.cfm.va.gov/til/space.asp

• Perform all work in accordance with current VA Barrier Free Design Standard (PG-18-13)

• Perform all work in accordance with current VA Roof Finishes, Door, and Hardware Schedule (PG-18-14)

• Ensure patient privacy criteria are met (e.g. computerized information, patient privacy, Health Insurance Portability and Accountability Act).

• Design and construction work shall be coordinated with other construction projects on-going at the hospital. A list of current projects will be provided upon approval of the 35% submission.

• A/E shall use most current healthcare delivery processes and the VA design criteria as a guide. The direction that fits the situation the best will be used in the design.

• If shutdowns are required during construction, a full shutdown plan shall be included in the design. Shutdown plans shall include the particular energy source to shut off (e.g. breaker, valve, etc.) and what area, outlets, utilities and/or equipment the shutdown affects. The specific name of the energy source to be shut off shall be identified, for example: “panel H1L1, breaker 2” for electric, or “Valve 3-f” for a water source, etc. Drawings and a written narrative shall be provided.

• A Leadership in Energy and Environmental Design (LEED) Silver Rating is desired with the construction. A rating will not be sought, but practices will reflect LEED Silver requirements.

Proof of possible LEED credits shall be provided. The VA shall conduct an Energy Review upon receipt of the 65% submittal (DD2).

• Bid Alternates/Deducts shall be designed into the project to decrease the price of the project 20%.

• A/E shall be responsible for providing certified industrial hygiene services to perform asbestos survey investigations, sampling, development of specifications and drawings, and construction period services. Any place where a sample is taken shall be restored to original condition.

• A/E shall pay particular attention to Occupational Safety and Health Administration (OSHA), National Fire Protection Association (NFPA), International Building Code (IBC), and Environmental Protection Agency (EPA) requirements. Upon receipt of the 65% (DD2) and 95% (CD1) submittals, the VA shall conduct a third-party life safety review. The A/E shall be responsible for making any necessary changes for code compliance and assisting the VA in the waiver process if required.

• A/E shall be responsible for providing all services necessary for design of this project, e.g.

structural, industrial hygiene, mechanical, electrical, etc.

SITE INVESTIGATION REQUIREMENTS:

Make site visits as required to determine existing as-built conditions affecting this project. Note:

Information including drawings and other documentation provided to the A/E shall be used as reference only. A/E shall field verify every aspect that relates to the project, including all dimensions, wall layouts, capacities, etc. A/E shall coordinate visits with the Contracting https://www.osha.gov/Publications/3439at-a-glance.pdf

Officer’s Representative (COR) as assigned after award. The A/E shall arrange for and oversee the performance of such investigations as required for the proper design of the project.

SUBMISSION REQUIREMENTS:

• Deliver all design packages in person directly or by traceable carrier to the COR on the established dates to allow the VA Project Design Teams to meet as scheduled. A transmittal letter is required to go to the Contracting Officer on the same day as delivery.

• Electronic Narratives shall be provided in portable document format (.pdf)

• Electronic Specifications shall be provided in both portable document format (.pdf) and Microsoft word (.docx) format compatible with the VA’s system.

• Electronic Drawings shall be provided in document format (.pdf), AutoCAD format (.dwg) and REVIT format compatible with the VA’s system.

• Schematic Submission o All items required in Attachment B Design Submission Requirements o At least three (3) proposed layouts (facility project) or solutions (utility project) as outlined at the initial PDT meeting. More layouts shall be required if the provided layouts do not meet the needs of the medical center. The A/E shall be required to present the advantages, disadvantages and costs of each layout to the Medical Center director for approval o One (1) physical copy and an electronic copy of the narrative report describing the layouts/solutions with their advantages, disadvantages and costs o One (1) physical copy and an electronic copy of the narratives required in Attachment B o Two (2) physical copies, 30” x 42” size, and an electronic copy of the drawings of each proposed layout/solution including all information required in Attachment B

• Design Development 1 Submission (35%) o All items required in Attachment B Design Submission Requirements o The A/E shall be required to present the layout, renderings and sample boards to the

Medical Center director for approval o One (1) physical copy and an electronic copy of all non-drawing items required in

Attachment B o Two (2) physical copies, 30” x 42” size, and an electronic copy of the drawings including all information required in Attachment B. One hard copy shall be broken up into Civil/Site, Structural, Architectural, Hazardous Material, Equipment, Life Safety and Fire Protection, Plumbing and Heating, Air Conditioning, and Electrical sections.

o Identification of potential bid deducts o Annotated responses to all comments provided by the VA during the review of the schematic submission o Provide the period of performance for the construction of the design

• Design Development 2 Submission (65%) o All items required in Attachment B Design Submission Requirements o The A/E shall be required to present the layout, renderings and sample boards to the

Medical Center director for approval o One (1) physical copy and an electronic copy of all non-drawing items required in

Attachment B o Two (2) physical copies, 30” x 42” size, and an electronic copy of the drawings of including all information required in Attachment B. One hard copy shall be broken up into Civil/Site, Structural, Architectural, Hazardous Material, Equipment, Life Safety and Fire Protection, Plumbing and Heating, Air Conditioning, and Electrical sections o Identification of potential bid deducts o Annotated responses to all comments provided by the VA during the review of the

Design Development 1 submission

• Construction Documents 1 Submission (95%) o All items required in Attachment B Design Submission Requirements o One (1) physical copy and an electronic copy of all non-drawing items required in

Attachment B o Two (2) physical copies, 30” x 42” size, and an electronic copy of the drawings including all information required in Attachment B. One hard copy shall be broken up into Civil/Site, Structural, Architectural, Hazardous Material, Equipment, Life Safety and Fire Protection, Plumbing and Heating, Air Conditioning, and Electrical sections o Identification of potential bid deducts o Annotated responses to all comments provided by the VA during the review of the

Design Development 2 submission, including the life safety review and energy review

• Construction Documents 2 Submission (100%) o All items required in Attachment B Design Submission Requirements o One (1) physical copy and an electronic copy of all non-drawing items required in

Attachment B o Two (2) physical copies, 30” x 42” size, and an electronic copy of the drawings including all information required in Attachment B o Identification of potential bid deducts o Annotated responses to all comments provided by the VA during the review of the

Construction Documents 1 submission, including the life safety review

• Bid Documents o One (1) physical copy and an electronic copy of all non-specifications/drawing items that changed during the CD2 review o One (1) physical copy and an electronic copy of the specifications with stamps/seals o Two (2) physical copies, 30” x 42” size, and an electronic copy of the drawings with stamps/seals o Annotated responses to all comments provided by the VA during the review of the Construction Documents 2 submission o Provide the period of performance for the construction of the design

CONSTRUCTION PERIOD SERVICES REQUIREMENTS:

• Assist the VA with a price reasonableness determination of bid prices

• Review all submissions and provide recommendations to the VA within fifteen calendar days

• Review and provide replies to contractor generated Requests for Information (RFI) within 5 workdays

• Review contractor’s change order request and provide an independent cost estimate for each change order request.

• Make 50 site visits, including those necessary for acceptance inspections, at the request of the VA and prepare written reports to include agreed upon changes in design as determined necessary during the construction. Visits made based on errors and omissions in design will be at no cost to the VA.

• Within 30 days after receipt of red-line drawings that the contractor kept during construction, prepare as-built drawings with A/E’s stamp. Transpose contractor’s as-builts to the current version of AutoCAD and provide a set of updated as-builts, specifications and BIM model.

Attachment A:

Project Areas

Loop road addition

Bldg. 17 parking addition

Bldg. 18 connector

Traffic island and flagpole area

Attachment B: Design Submission Requirements

1. GENERAL, SURVEY, GEOTECHNICAL, CIVIL AND LANDSCAPE: Submit the following:

General, Survey, Geotech, Civil, Landscape

Schematic 35% DD1 65% DD2 95% CD1 100% CD2

Narrative

• Site Feasibility Analysis

• Circulation Study

• Phasing Analysis

• Parking Analysis

• Subsurface Investigation Report

• Boring Logs

Drawings

• General Information o List of sheets and symbols o Code summary o Orientation Maps

• Layout Plan showing location of o Buildings and Structures o Roads o Fire Access o Parking o Accessible Spaces o Van Spaces o Mechanical and Electrical

Equipment on Grade o Future Expansion o Off-site Roads o Off-site Utilities o Service Areas o Entrances and Exits o Walks o Inlets o Contractor’s Staging Area o Temporary fencing o Soil borings o Vertical and Horizontal Road

Alignment o Paving Joint Patterns

• Grading Plan Showing:

o Existing Contours o Proposed Contours o Spot Elevations at Structure

Corners, Entrances, Equipment Pads, etc o First Floor Elevations o Rim and Invert Elevations on

Storm Drainage Fixtures o Erosion and Sedimentation Control o Rock Excavation (Quantity)

• Demolition Plan

• Planting Plan Showing o Landscape Drawings with Plant Groupings o List of Plant Material

• Site Details

• Landscape Details

• Signage Plan and Schedule

• Phasing Plan

• Infection Control Plan

2. HAZARDOUS MATERIALS: Submit the following:

Hazardous Materials Schematic 35% DD1 65% DD2 95% CD1 100% CD2 Narrative

• Summary results of building records

• Summary results of station personnel interview

• Determination of materials known to contain asbestos, lead, PCBs, Ozone Depleting Substances or other toxins

• Visual inspection of work area to determine location and condition of hazardous materials

• Sample strategy

• Table of quantities and types of materials to be abated Drawings

• Major Decontamination Areas o Limits of sealing off the location o Locations, types, and quantities of hazardous materials to be removed o Locations and quantities of hazardous materials to remain o Arrangements for auxiliary rooms o Engineering of negative air systems o Path of hazardous materials to loading areas o Location and connection to required utilities o Personal decontamination area

• Minor Decontamination Areas o Local, types and length of items to be abated by glove and bag approach o Other abatement features

• Restoration of impacted areas

• Abatement phasing

3. STRUCTURAL: Submit the following:

Structural: Schematic 35% DD1 65% DD2 95% CD1 100% CD2

• Three alternative structural systems for typical bays

• Supporting calculations

• Cost estimates for each system

• Recommend preferred system

Drawings

• Inspection Requirements

• Structural plans

• Sections

• Details

• Existing Columns

• New Columns

• Beams

• Lateral load resisting elements

• Shear load resisting elements

• Load bearing walls

• Slabs

• Foundations

• Elevations

• Schedules

• General notes

• Estimated quantity of rock

• Spray on fireproofing

• Phasing

4. ARCHITECTURAL, INTERIOR DESIGN, EQUIPMENT: Submit or show the following:

Architectural, Interior Design, Equipment:

Schematic 35% DD1 65% DD2 95% CD1 100% CD2

Narrative

• Schematic Options

• Circulation Study

• Phasing Analysis

• Written interior design concept

Floor Plans/Drawings

• Rooms (w/Names & Numbers)

• Doors

• Corridor(s)

• Basic column grid/sizes

• Electrical closets

• Equipment rooms

• IT closets

• Mechanical shafts and space

• Stair(s)

• Ramp(s)

• Elevator(s)

• Penthouse

• Program net/designed net SF

• Size and shape of all departmental functions and services

• Exterior dimensions/total building gross area

• Exterior building elevations

• Expansion and seismic joints

• Roof plan

• Pipe basement

• Pipe tunnel

• Reflected ceiling

• Demolition plans

• Exterior finishes

• Finish floor elevations

• Wall thickness and ratings

• Plumbing fixtures

• Wall sections

• Building sections

• Finish grades at corners, entrances, exits, platforms and ramps

• Lead-lined and radio-frequency-shielded partitions

• Psychiatric areas

• Fire extinguisher cabinets

• Construction details

• Drafting symbols, abbreviations, and general notes

• Door, window, and louver schedules

• Perspectives of key spaces

• Interior details, elevations, sections and perspectives

• Wayfinding and Signage

• Interior finishes Plan

• Wall protection and handrails

• Flooring

• Finish Schedule

• Major Equipment

• All Equipment from PG-18-5

• Equipment elevations and details

• Equipment schedule

• Phasing

Color renderings (interior and exterior) Sample Boards for interior and exterior materials, products, and finishes

Activation Equipment List (Excel format)

5. FIRE PROTECTION: Submit the following:

Fire Protection: Schematic 35% DD1 65% DD2 95% CD1 100% CD2 Narrative:

• Fire and smoke separation

• Fire sprinkler/standpipe system

• Size of fire pumps

• Water supply available/max.

demand

• Water flow testing results

• Fire alarm systems

• Calculations

• Estimated capacities for proposed air handling units in cubic meters (cubic feet) per minute

Drawings:

• Kitchen extinguishing systems

• Size of air handling unit

• Exit paths from each zone

• Distances to stairs

• Occupancy of each area

• Exit calculations for each floor

• Smoke control features

• Life Safety Summary

• Sprinkler zones

• Fire alarm zones

• Smoke zones

• Building water supply

• Interior sprinkler supply lines

• Standpipes

• Fire extinguisher cabinets

• Fireproofing of structural members

• Sprinkler/standpipe riser supply piping

• Termination of sprinkler main and inspector test drains

• Sprinkler alarm valves

• Waterflow and tamper switches

• Sprinkler system fire department connections

• Sprinkler design hazards per

NFPA 13

• Occupied areas not protected by automatic sprinklers

• Fire alarm system

• Annunciator panels

• Pull stations

• Flow switches

• Audio-visual devices

• Smoke detectors

• Duct smoke detectors

• Smoke dampers

• Fire dampers

• Fire alarm risers

• Exit signs

• Emergency lighting

• Fire sprinklers

• Standpipes

• Fire hydrants

• Fire pumps

• Post indicator valves

• Sectional valves

• Electromagnetic door hold- open devices

• Wall sections indicating fire resistive ratings

• Staff sleeping rooms

• Excavation plan signage

• Door and window schedule with fire rating or fire rated glazing

• Zoning of each fire alarm initiating device

• Details:

o Fire pump system (capacity and pressure) o Elevation and isometric view of fire pump o Stairwell sign o Annunciator panel

• Interconnection of fire alarm system with:

o Smoke dampers o Air handlers o Elevator controls o Kitchen fire extinguishing and fire pump system o HVAC system with smoke duct detectors

• Single line riser diagram for fire alarm system

• Height/configuration of storage racks and shelving

6. PLUMBING: Submit the following:

Plumbing Schematic 35% DD1 65% DD2 95% CD1 100% CD2

• Demolition plans

• Existing plumbing systems to be used and necessary modifications

• New plumbing systems

• New or modified water treatment

• Calculations (equipment & piping)

• Existing systems: water, sewer, storm, & gas with sources, disposal methods, pressures, condition, etc.

• New sanitary systems Floor Plans/Drawings

• Demolition Plan

• Room Names

• Identify o Existing and new plumbing fixtures w/VA numbering system o Existing and new equipment o Existing and new medical gas outlets o Existing and new laboratory/ process gas outlets o Existing and new sanitary connections and drains o Plumbing piping

• Size of Pipe

• Equipment schedule

• Fire & smoke partitions

• Riser diagrams

• Legend, notes, and details

• Invert Elevations

• Location/Size o Pumps o Storage Facilities o Treatment Equipment o Fire Hydrants o Sectional and post indicator valves o Backflow preventer o sprinkler riser, standpipes, system connection and fire pumps

• Profiles of sanitary & storm sewers

• Location of emergency eyewash and shower equipment

• Phasing

7. HVAC: Submit the following:

HVAC Schematic 35% DD1 65% DD2 95% CD1 100% CD2

• Description of HVAC systems

• Equipment for each functional space

• Life cycle cost analysis

• Block layout of equipment

• Selection of HVAC Equipment

• Engineering calculations

• Selection of HVAC equipment

• Catalog cuts of equipment

• Room by room heating and cooling loads

• Zone by zone heating & cooling loads

• Building block heating & cooling

• Tabulation of steam consumption

• Psychometric chart for air handling unit

• Fan motor heat gains

• Consumption of humidification

• Sound/acoustic analysis

• Total heating and cooling loads

• Domestic hot water load

• Humidification load

• Equipment steam demand

• Zoning of systems

• Capacity

• Quantity and type of equipment

HVAC Drawings

• Main supply, return and exhaust ductwork

• Volume dampers

• Fire and smoke partitions

• Smoke detectors

• Automatic control dampers

• Air Quantities for each room

• Air inlets/outlets

• Rises and drops in ductwork

• Expansion loops

• Anchors

• Vanes

• Drip Assemblies

• Balance Fittings

• Equipment Rooms

• Vertical shafts

• Louvers:

o Outside air o Exhaust air o Relief air

• Air changes per hour in each room

• Room-by-room air balance charts

• Coil entering and leaving conditions

• Interconnection of HVAC equipment with fire protection equipment (see fire protection)

• Plan/Section of mechanical rooms

• Schematic flow and riser diagrams

• HVAC demolition

• Phasing plan

• Equipment Schedule

• Seismic bracing

• VA symbols and abbreviations

• Section of

• Pumps

• Fans

• Expansion tanks

• Steam to hot water convertor

• Heat exchangers

• Complete data section

• Outside chilled water and condenser water distribution

• Automatic temperature control drawings

8. ELECTRICAL: Submit the following:

Electrical Schematic 35% DD1 65% DD2 95% CD1 100% CD2

• Design

• Life cycle cost analysis

• Method of short-circuit calculations

• Method of voltage drop and demand calculations

• Utility company correspondence

• Utility company requirements

• Load calculations for normal & emergency use

• Calculations for emergency generator(s)

Drawings Showing:

• Electric closets

• IT closets

• Signal closets

• Major Electrical equipment

• Electrical plot plan of existing and proposed underground power (including manholes)

• Signal inter-building systems

• Proposed electrical system

• Lighting fixture schedule

• Emergency Life Safety Equipment

(see fire protection)

• Electrical distribution equipment

• Symbols, note, abbreviations

• Lighting layouts

• Power layouts

• Signal layouts

• Specialty area layouts

• IT Layout

• Demolition plans

• Riser diagrams/On-Line diagrams

• Panel Schedules

• Engine-generator sets

• Substation/pad mounted transformer

• Location of smoke dampers and duct smoke detectors

• Phasing scheme

• Electrical details

9. AUTOMATIC TRANSPORT: Submit the following:

Automatic Transport: Schematic 35% DD1 65% DD2 95% CD1 100% CD2

• Narrative w/ recommended improvements for exiting system

• Traffic study including existing and proposed ATS w/ alternate methods of distribution

• Rail loadings

• Hydraulic elevator piston pit loads

Drawings:

• Automatic Transport Systems

• Elevators

• Dumbwaiters

• Other ATS systems

• Changes to existing systems

(arch. dwgs.)

• Hoistway (arch. dwg.)

• Machine room vents (arch.

dwg.)

• Type of ventilation (mech. dwg.)

• Electrical requirements (elect.

dwg.)

• Hoistway enclosures

• Pits

• Pit ladders

• Machine area ladder and railings

• Entrances

• Machine rooms

• Elevator cars

• Entrances

• Counterweights

• Trap doors

• Location of hoistway vents

• Location of steel hoisting beams

• Size of machine beams

• Size of end reactions

• Location/detail of machine beam pockets

• Hoistway entrances for elevators

• Carlifts

• Dumbwaiters

• Elevator machine room equipment layout

• Interface with automatic recall and shutdown (see fire protection)

10. SPACE PLANNING

SPACE PLANNING: Schematic 35% DD1 65% DD2 95% CD1 100% CD2

Space-Accounting Summary Table

11. ESTIMATING: Submit the following:

Estimating: Schematic 35% DD1 65% DD2 95% CD1 100% CD2 Cost estimate in compliance with Manual for Preparation of Estimates (separate estimates for new construction and alteration work)

12. SPECIFICATIONS

Specification: Schematic 35% DD1 65% DD2 95% CD1 100% CD2 Specifications:

• Table of Contents

• Marked up Specifications

• Complete Specifications

• Submittal Register

GENERAL OVERVIEW:
SPECIFIC REQUIREMENTS:
SCHEDULE:
GENERAL REQUIREMENTS:
SITE INVESTIGATION REQUIREMENTS:
SUBMISSION REQUIREMENTS:
CONSTRUCTION PERIOD SERVICES REQUIREMENTS:

File details come from the government source that posted it. Updated .