This is a Statement of Work (SOW) for Architectural and Engineering (A/E) design services to replace twelve domestic hot water heaters across multiple buildings at the Lyons VA Medical Center in New Jersey. The project requires a comprehensive design package, including site assessment, construction drawings, specifications, cost estimates, and construction period services, with a focus on integrating energy-efficient technologies and ensuring compliance with VA and federal standards. The design must address water heater replacements in Buildings 1, 3, 7, 13, 53, 54, 57, and 143, with a period of performance not exceeding 120 calendar days from the Notice to Proceed.

The related federal contract opportunity is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside procurement with an estimated construction cost range between $500,000 and $1,000,000. Interested firms must be registered in SAM, verified as an SDVOSB in the Dynamic Small Business Search, and submit an electronic SF 330 by 10 AM EST in July 2025 to scott.nussbaum@va.gov. The Department of Veterans Affairs anticipates awarding a firm fixed-price contract on or before September 19, 2025, with the A/E firm selection based on seven evaluation factors including professional qualifications, specialized experience, capacity, past performance, and geographical proximity.

View the file

Other files for this federal contract opportunity

Other files attached to C1DA--AE Design for Replace Multi Bldg Water Heaters Project Number: 561A4-23-101, newest first.
File Type Posted
36C24225R0091.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Project # 561A4-23-101 Replace Hot Water Heaters

1. Contract Title A/E Design Services for Hot Water Heater Replacement – Lyons VA Medical Center

2. Background The Lyons, New Jersey VA Medical Center is undertaking a project to replace twelve (12) domestic hot water heaters across multiple buildings, including Buildings 1, 3, 7, 13, 53, 54, 57, and 143. The existing systems are outdated, non-compliant with manufacturer and VA standards, and inefficient in delivering consistent hot water.

This A/E project involves professional design services including site investigation, assessment, and the preparation of a complete construction document package for the replacement and reconfiguration of domestic hot water systems. The design must integrate energy-efficient technologies, comply with all applicable VA and federal standards, and support optimal flow and temperature control within the facility.

3. Scope The A/E shall provide a complete set of professional design services to support the replacement hot water heaters. This includes:

-A full site assessment of existing systems
-Development of phasing plans for construction to minimize operational disruptions
-Creation of a full construction drawing and specification package
-Cost estimating, bid alternates, and value engineering recommendations
-Construction period services including submittal reviews and site visits

4. Specific Tasks

4.1 Site Investigation and Survey

- Conduct field verification of as-built conditions across the identified buildings

- Evaluate the feasibility of reclaiming and reusing any existing equipment -Evaluate and recommend in-kind replacement where applicable

- Diagnose malfunctioning systems, including failed units in Building 3 (Aerco steam water heaters, Model #24656)

4.2 Design Documentation

- Develop drawings and specifications for the complete removal and replacement of the existing water heaters

- Include mechanical, plumbing, and electrical coordination for new recirculation pumps and piping

- Design for loop system reconfiguration and energy-efficient water heating

- Incorporate historic preservation coordination and NEPA CATEX/EA requirements

- Prepare cost estimates at key milestones

4.3 Code Compliance

- Ensure compliance with all applicable VA design manuals, including but not limited to HVAC, Plumbing, and Electrical

- Review and adhere to codes including NFPA, NEC, JCAHO, OSHA, ASHRAE, and others

4.4 Deliverables

- Construction document package in AutoCAD 2022 or newer

- Three conceptual layouts for VA selection

- Independent cost estimates

- Record drawings, specifications, and site visit documentation

- Submittal and RFI logs

- Agenda and minutes for all meetings, including bi-weekly design meetings

4.5 Construction Period Services

- Submittal and RFI review with 5-day turnaround

- Support for change order pricing and negotiation

- Site visits aligned with key construction phases

- Generation of record drawings from contractor redlines

4.6 Optional Tasks

- Provide independent commissioning agent (CxA) services

- PIH/CIH consultation for asbestos scope coordination

5. Performance Monitoring Performance will be monitored by the VA COR using defined criteria including schedule adherence, design quality, stakeholder communication, and compliance with codes and design guides. Evaluation categories include:

- Quality and coordination of design deliverables

- Responsiveness to comments and submittals

- Schedule management

- Small business participation (if applicable)

- Regulatory compliance

6. Security Requirements The A/E’s personnel will require intermittent escorted access to the facility. PIV Flash Pass cards must be obtained upon contract award for all personnel requiring site access.

7. Government-Furnished Equipment (GFE)/Government-Furnished Information (GFI) N/A

8. Other Pertinent Information or Special Considerations

a. Identification of Possible Follow-on Work Not applicable.

b. Identification of Potential Conflicts of Interest (COI) Not applicable.

c. Inspection and Acceptance Criteria Acceptance of deliverables and services shall be confirmed by the VA COR. No invoices shall be processed without formal approval.

9. Risk Control The A/E shall provide a site-specific risk control plan, which includes infection control, pedestrian safety, and preservation of operational equipment. Work shall be coordinated to avoid interference with patient care operations.

10. Place of Performance Work will be performed at the Lyons VA Medical Center, across multiple buildings including administrative, clinical, and residential spaces.

11. Period of Performance The period of performance shall not exceed 120 calendar days from Notice to Proceed. The project is anticipated to begin in Q4 FY 2025 and conclude by Q1 FY 2026.