This is a Past Performance Questionnaire (PPQ) and cover letter template for an Architect-Engineer services solicitation to replace roofs at the Ralph H. Johnson VA Health Care System in Charleston, SC. The PPQ is to be completed by previous clients of firms responding to solicitation #36C24725R0082.
The questionnaire evaluates A/E performance across 21 factors including design services, construction support, LEED compliance, BIM capabilities, and overall project management. Rating categories range from Exceptional to Unsatisfactory. Key areas assessed include technical competence, issue resolution, document accuracy, cost estimation, schedule adherence, submittal review, and construction period support. The form requires details about errors and omissions, associated cost impacts, and whether the evaluator would use the A/E firm again. Completed PPQs must be submitted electronically to the VA Contract Specialist by March 31, 2025 at 3:00 PM ET, with a 7MB file size limit per email.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24725R0082.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA CONTRACTING NCO 7
PAST PERFORMANCE QUESTIONNAIRE (PPQ) AND COVER LETTER
SECTION 1
PAST PERFORMANCE QUESTIONAIRE AND COVER LETTER
NCO 7 Contracting Office is reviewing the qualifications of the Offeror identified to Design and Replace Roofs Phase 2 at the Ralph H. Johnson VA Health Care System, Charleston, SC.
Your comments would be appreciated regarding this firm’s past performance. The intent of this form is to evaluate the company’s ability to perform the work as described in the solicitation. Please verify the accuracy of the information in Section 1 and complete the questionnaire as thoroughly as possible. NCO 7 Contracting may contact you to obtain any additional information.
Complete one set of letters and forms for each project identified. Additional space or blank sheets may be added to answer any question.
Transmittal Letter to Accompany Past Performance Questionnaire
FROM: [Insert Company Official Name, Title, and Company Name] SUBJECT: Past Performance Questionnaire for Contract(s):
[Insert Company Name] is currently responding to Department of Veterans Affairs (NCO 7) request for SF 330, Architect-Engineer Qualifications for a complete design and provide Professional Architect/Engineer (A/E) and healthcare planning services necessary to replace roofs that have a) reached the end of their useful life, b) are not sloped correctly to provide positive drainage or c) do not have the required secondary drains. This project also increases the thermal insulation to meet VA Energy Directives, corrects numerous issues with the lightning protection system and recertifies the building, replaces roof curbs due to seismic requirements and demolishes aged rooftop equipment or replaces it. The Charleston VAMC preference is for a modified SBS built up roof membrane system with a light-colored top fiber embedded cap sheet. A/E may provide alternatives based on their professional expertise for discussion and review by the VAMC. Roofs to be addressed are: 1C-1, 2AA-1, 2D-1, 2E-1, 2F-1, 2G-1, 2H-1, 2H-2, Undesignated roof outside 3BN This Request for SF 330’s requires respondents to identify customers and solicit their response regarding [Insert Company Name] performance.
[Insert Company Name] is providing past performance data to NCO 7 relating to our performance on contract [Insert contract name/number] and have identified [Insert name of reference] as the point of contact for this contract.
The request for SF 330 instructs that respondents provide customers with the attached questionnaire.
Please complete the questionnaire and submit it by March 31st, 2025 @ 3;00PM ET directly to the NCO 7 Contracting Specialist. The requested data MUST be submitted electronically via email to the Government representative identified below. ONLY electronic responses will be accepted.
Please send responses to Kenyon Dulaney, Contract Specialist at Kenyon.Dulaney@va.gov. Please note that the maximum file size the VA’s email system will allow is 7MB. If submission will require multiple emails, please identify them as “x of n”.
The information contained in the completed Past Performance Questionnaire is considered sensitive and cannot be released to [Insert Company Name]. Please direct any questions about the acquisition or the attached questionnaire to the VISN 7 NCO point of contact identified above.
Thank you, [Insert Company Official Name and Title]
AE FIRM INFORMATION
AE Firm Name:
Telephone:
Address:
Email Address:
City | State | Zip:
Point of Contact:
Firm Tax ID Number:
Firm Cage Code:
Firm DUNS Number:
Contract Number:
Dollar Amount:
Period of Performance:
Project Title:
Description of Project:
Description of A-E Firms’ Responsibilities:
The AE Firm was the << Please select one >>:
Prime Contractor | Sub-Contractor | Consultant | Team Member
Percent of the work performed by the AE:
Other (Please describe):
EVALUATOR INFORMATION
Company or Agency Name:
Address:
City | State | Zip:
Evaluator’s Name:
Evaluator’s Title:
Evaluator’s Phone:
Evaluator’s email:
SECTION 2
PERFORMANCE INFORMATION
ADJECTIVAL RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE
*THIS PAGE WILL BE REMOVED FOR EVALUATION PURPOSES AND NOT BE COUNTED TOWARD THE SF330 PAGE COUNT – IT IS FOR PPQ COMPLETION PURPOSES ONLY* Choose the appropriate rating that most accurately describes the A/E’s performance or situation. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ALL RATINGS OF Marginal or Unsatisfactory on the Narrative Summary found below.
| Exceptional |
| Very Good |
| Satisfactory |
| Marginal |
| Unsatisfactory |
| N/A |
| Performance meets or met contractual requirements and exceeds or exceeded many of your company’s expectations. The contractual performance reflects or reflected few minor problems and corrective actions taken by the contractor appear to be highly effective or corrective actions taken were effective. |
| Performance meets or met contractual requirements and exceeds or exceeded some of your company’s expectations. The contractual performance reflects or reflected some minor problems and corrective actions being taken by the contractor appear to be effective or Corrective actions taken were effective. |
| -Performance meets or met contractual requirements. The contractual performance reflects or reflected some minor problems. |
Corrective actions being taken by the contractor appear to be effective or Corrective actions taken were effective.
| -Performance does or did not meet some contractual requirements. The contractual performance reflects or reflected serious problems(s) for which the contractor has not yet identified acceptable corrective actions or did not provide acceptable corrective actions. |
| -Performance does or did not meet most contractual requirements and recovery is not likely or did not occur. The contractual performance contains or contained serious problem (s) for which the contractor’s corrective actions appear ineffective or were ineffective. |
| -Not applicable or rater has not observed performance in this area. |
VA CONTRACTING NCO 7
SECTION 3
PERFORMANCE INFORMATION
A-E FIRM’S NAME: PROJECT NAME:
Contract Period of Performance:
Note: Include this information on each page of the questionnaire form to ensure there is no mix up in information among contracts surveyed for respective primes/subs, etc.
Place an “X” in the appropriate column using the definitions matrix on the preceding page.
Item
FACTORS TO BE RATED
| Exceptional |
| Very Good |
| Satisfactory |
| Marginal |
| Unsatisfactory |
| N/A |
Design Services
| 1. |
| Overall skill level and technical competence of A/E’s personnel. |
| 2. |
| A/E’s ability to identify and resolve design issues expeditiously. |
| 3. |
| A/E’s responsiveness to design review questions. |
| 4. |
| A/E’s ability to effectively coordinate, integrate and manage their team consultants/subcontractors/team. |
| 5. |
| A/E’s effectiveness and responsiveness in interfacing with the Client’s staff. |
| 6. |
| Overall accuracy, completeness, and coordination of final design documents. (Quality) |
| 7. |
| A/E’s ability to provide detailed, accurate cost estimates. |
| 8. |
| A/E’s ability to meet contract schedule. |
Follow-On Construction Support Services
| 9. |
| Thoroughness and timely review of construction submittals. |
| 10. |
| Timely resolution of construction design issues. |
| 11. |
| Overall quality, responsiveness, and timeliness of A/E follow-on construction support services. |
LEED (If Applicable)
| 12. |
| Overall accuracy, completeness, timeliness, and coordination of LEED documentation. |
| 13. |
| A/E’s ability and understanding of the overall LEED process. |
BIM (If Applicable)
| 14. |
| Overall accuracy, completeness, timeliness, and coordination of BIM documentation. |
| 15. |
| A/E’s ability and understanding of the overall BIM process. |
Owner’s Representative on Design/Build Projects (If Applicable)
| 16. |
| Overall accuracy, completeness, timeliness and coordination of requirements documents and bridging documents. |
| 17. |
| A/E’s ability, thoroughness, timeliness, and support as Owner’s Representative throughout the project. |
Overall
| 18. |
| How would you rate the A/E’s ability to control cost? |
| 19. |
| How would you rate the A/E’s overall management performance on this contract? |
| 20. |
| How would you rate the A/E’s overall technical/quality performance on this contract? |
| 21. |
| Would you use this A/E again? (If “No”, please comment in the Narrative Summary) |
| YES |
| NO |
Number of A/E Design Errors & Omissions on Project:
(Please describe any major issues below)
Increased Project Cost Due to A/E Design Errors & Omissions (Yes | No):
(Please describe any major project impacts below) p
A-E FIRM’S NAME: PROJECT NAME:
Contract Period of Performance:
Note: Include this information on each page of the questionnaire form, as needed, to provide further details.
NARRATIVE SUMMARY (Use this section to explain any rating of marginal or unsatisfactory from the previous page)
| ITEM |
| COMMENTS |