Advance Notice - Synopsis FY 26 Sandy Hook Maintenance Dredging.pdf
PDF 89 KB Posted
- Attached to
- Advance Notice: Maintenance Dredging of New York Harbor, Sandy Hook Federal Navigation Channel
- Solicitation number
- W912DS26BA018
About this file
This is a Synopsis of Proposed Dredging for a federal navigation project managed by the U.S. Army Corps of Engineers (USACE), New York District. The project involves maintenance dredging of the Sandy Hook Channel in New York Harbor to remove approximately 190,000 cubic yards of sand and gravel shoals, restoring the channel to an authorized depth of -35 feet Mean Lower Low Water (MLLW) plus 2 feet of allowable overdepth. The dredged material will be transported to and placed at the Sea Bright Offshore Borrow Area (SBOBA), located 5 miles southeast of Sandy Hook Point, New Jersey. Work must be performed using a mechanical dredge with a clamshell bucket, supported by ocean-going barges, tugboats, and ancillary equipment. The contractor must maintain an integrated production rate of at least 8,000 cubic yards per calendar day.
The contractor must commence work within five calendar days of receiving the Notice to Proceed (NTP) and complete all basic work ready for use within 60 calendar days of the NTP date. The estimated project cost ranges from $1,000,000 to $5,000,000. Solicitation is expected to be available in June 2026, with bid opening scheduled for July 2026 and government award intended for August 2026 with NTP issuance within 14 calendar days of award. Liquidated damages of $3,260.00 per calendar day will be assessed for any delay until contract work is accepted as complete. This is an unrestricted procurement open to all eligible contractors.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Synopsis of Proposed Dredging - Maintenance Dredging of Sandy Hook Channel, New York Harbor, Federal Navigation Project.
Background Information
The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of the New York Harbor, Sandy Hook Federal Navigation Channel.
The dredged material would be dredged and subsequently transported to and placed at the Sea Bright Offshore Borrow Area (SBOBA), 5 miles southeast of Sandy Hook Point, NJ. The proposed maintenance dredging would remove approximately 190,000 cubic yards of selected critical shoals from the Sandy Hook Channel. Dredging would be required to a depth of -35 feet Mean Lower Low Water (MLLW) plus 2 feet of allowable overdepth. The dredged material is expected to consist primarily of sand and gravel.
The purpose of the proposed work is to alleviate the effects of shoaling and restore the authorized project dimensions, thereby providing safe and economical use of Sandy Hook
Channel by military, commercial and recreational boating interests while providing future beneficial use of the dredged material.
Based on past dredging cycles, it is recommended that the proposed work only be performed by utilizing a mechanical dredge with a clamshell bucket. Additionally, multiple ocean-going barges, tug boats and ancillary equipment will be needed to perform the dredging, transport and placement activities. The entire channel will generally not require maintenance dredging; only areas where shoaling has reduced the depth of the channel will require dredging. The dredged material would be required to meet all federal, state, and local criteria required by the government agencies having jurisdiction where the placement site is located.
The Contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed, and to prosecute said work diligently and to complete all basic work ready for use not later than ninety (60) calendar days after the receipt by him of the notice to proceed (NTP). The contractor is required to maintain an integrated production of at least 8,000 cubic yards per calendar day.
The work is estimated to cost between $1,000,000 and $5,000,000. Solicitation for the subject project is expected to be available in June 2026, with bid opening in July 2026. It is the intention of the government to award in August 2026 and issue the NTP within fourteen (14) calendar days of the award date.
Liquidated Damages of $3,260.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete.
This is an unrestricted Procurement.
File details come from the government source that posted it. Updated .