See attached.

View the file

Other files

File Type Posted
TA-63 TWF Phase B.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Notice for Federal Business Opportunities

(Note: fields in bold purple below are mandatory within the FBO system.)

General Information

Document Type: Presolicitation

Solicitation Number: ADPM-003 Title:

TA-63 TWF Phase B

Response Date:

June 4, 2012, 2:00 pm MST

Classification Code:

Y Set Aside:

N/A

NAICS:

236210 Is this a Recovery Act project? No Contracting Office Address

Department of Energy, Los Alamos National Laboratory (DOE Contractor), PO Box 1663 MS D442, Los Alamos, NM 87545.

Description: The TRU Waste Facility (TWF) Project is located in the TA-63 site south of the Puye Road and east of Pajarito Road. It is designed, permitted, will be constructed, and commissioned as Hazard Category (HC)-2 nuclear facilities with a Resource Conservation and Recovery Act (RCRA) permit to store hazardous wastes.

SUBCONTRACTOR is expected to contribute to the foregoing goals and objectives in the following manner: SUBCONTRACTOR shall perform the Work safely, in accordance with CONTRACTOR’s Environmental, Health and Safety Program, procure materials, construct the facility meeting the requirements of SD 330 Quality Assurance as a minimum and accepting ASME NQA-1 2008 (ASME NQA-1a-2009) for ML-1,ML-2 and ML-3 selected structures systems and components (SSCs) and activities in an effort to complete the work with zero accidents and quality performance.

The facility will consist of multiple structural steel buildings for the storage of TRU waste to meet Nuclear Facility requirements for staging of newly generated solid TRU wastes in support of LANL programs and missions. A RCRA-permitted concrete pad will be designed and constructed for characterization and testing trailers that are required to certify containers to the Waste Isolation Pilot Plant (WIPP) Waste Acceptance Criteria (WAC). Other functions provided at the TWF include intra-site shipping and receiving, operational support facilities, and necessary utilities and services.

S:\Mike Martin\TRU Waste Phase B (Construction)\TRU WASTE -FINAL - Request for Interest-ADPM Construction Phase B.docx Point Of Contact:

Karin Antal

ASM-Constr

Contract Specialist

505-606-2317

Email: kantal@lanl.gov