Additional Information December 23~1.docx
DOCX document 21 KB Posted
- Attached to
- Sluice Gate and Controls Replacement
- Solicitation number
- S-R33123-00012354
- Issued by
- Wasco County, Oregon
About this file
This is an Additional Information document issued on December 23, 2024, by the Oregon Department of Transportation (ODOT) for the ESB OR542 (Powers Highway) MP12.66 Culvert Replacement project. The project involves culvert replacement work on a critical roadway that serves as the only route for emergency personnel, residents, the parks department, and rock quarries. ODOT will supply the culvert pipe, which is currently located at ODOT's yard in Coaledo and must be picked up by the contractor. The contractor is responsible for providing all installation materials including bands, anchor assemblies, and other necessary components. Upon completion, contractors must place 8 inches of asphalt in the trench, with payment based on actual quantities placed rather than the original thickness removed. ODOT will install culvert ID markers, and the contractor is not required to stripe the roadway but must place temporary reflectors in lieu of removed striping.
The contractor must pothole to confirm the existing asphalt thickness, estimated at 1–2 feet, and must coordinate disposal of removed materials with the adjacent landowner, Mr. Brown, as ODOT stockpile areas are not available for permanent storage. Full road closure is prohibited due to the roadway's critical emergency access function. The asphalt tonnage specified is an estimate only, with final payment based on actual placement. All workers must coordinate with ODOT regarding pipe delivery logistics and project scheduling to minimize disruption to emergency services and other authorized users of the roadway.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S-73000-00012355 Additional Information December 23, 2024.
1. A full road closure is not allowed on this road. This is the only route in and out for emergency personnel, residents, parks department, rock quarries etc.
1. The thickness of the road is approximately 1-2 feet. However, it is the contractor’s responsibility to pothole to confirm the thickness of the asphalt.
1. The contractor will not be required to stripe the roadway; however, they will need to place temporary reflectors in place of old striping that was removed.
1. ODOT stockpile areas are not for permanent storage of any material that is removed from the project location. There is an adjacent landowner (Mr. Brown) that may take the soil if it’s in good condition. However, it is up to the contractor to coordinate the disposal.
1. ODOT will supply the pipe.
1. The title of the Project is ESB OR542 (POWERS HWY) MP12.66 CULVERT REPLACEMENT.
1. Culvert ID markers will be installed by ODOT.
1. ODOT will not be delivering the pipe to the site. The pipe is located at ODOTs yard in Coaledo. ODOT is only supplying the pipe itself no bands, anchor assemblies etc. All other material needed to install the pipe will be on the contractor to provide.
1. The depth of asphalt to be placed back is 8 inches. The tonnage is an estimate only and quantities will be paid for based on the actual quantity placed.
1. The contractor will not be required to place the thickness that was removed; however, will be required to place 8 inches back in the trench.