Addendum Two .pdf

PDF 9 MB Posted

Attached to
RFB-255-25 Parks Carter Caves Sewer Upgrade Phase 3
Solicitation number
RFB-785-2500000681-3
Issued by
Calloway County, Kentucky

About this file

This is Addendum No. 2 for the Sewer Upgrades Phase 3 Wastewater Treatment Plant project at Carter Caves State Resort Park, issued by the Commonwealth of Kentucky's Department for Facilities and Support Services, Division of Engineering and Contract Administration. The addendum provides clarifications and answers to potential bidders' questions about the project, including requirements for concrete work, special inspections, waterproofing, temporary chlorine lines, and pipe capping. The project involves upgrades to the existing wastewater treatment plant, with specific details about concrete mix, construction techniques, and operational considerations during the renovation.

The addendum includes technical responses to seven specific questions from potential contractors, addressing issues such as shrinkage reducing admixture requirements, special inspection responsibilities, concrete stoop details, waterproofing specifications, rock removal, temporary chlorination methods, and pipe capping procedures. An attachment includes photographs of the existing effluent structure to provide additional context for bidders. The document is dated June 17, 2025, with a bid reference number RFB-255-25 and a DECA Account No. 670-CBAX-CC21-00, indicating this is part of a structured procurement process for a state parks infrastructure improvement project.

View the file

Other files

File Type Posted
Final_RFB_785_2500000681_2_SO_FORM.PDF PDF
Final_RFB_785_2500000681_1_SO_FORM.PDF PDF
Addendum One.pdf PDF
Final_RFB_785_2500000681_3_SO_FORM.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-255-25

FOR: Sewer Upgrades Phase 3

Wastewater Treatment Plant Carter Caves State Resort Park Department of Parks Olive Hill, Kentucky

DATE: June 17, 2025

RFB-785-2500000681

ADDENDUM NO. Two (2)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.

END OF ADDENDUM

Invitation to Bid No. RFB-255-25 For: Sewer Upgrades Phase 3

Wastewater Treatment Plant Carter Caves State Resort Park Department of Parks Olive Hill, Kentucky

Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration

DECA Account No. 670-CBAX-CC21-00 Page 1

GRW Project No. 4803-02

ADDENDUM NO. 2

CONTRACT DOCUMENTS

PARKS – CARTER CAVES SRP (CC) – SEWER UPGRADES PHASE 3

WASTEWATER TREATMENT PLANT IMPROVEMENTS

DECA ACCOUNT NO. 670-CBAX-CC21-00

GRW PROJECT NO. 4803-04

JUNE 17, 2025

TO ALL PROSPECTIVE SUBMITTERS:

Please be advised of the following clarifications to the above referenced Bid:

Questions Answers

1. Is the shrinkage reducing admixture at 2% mentioned in the specifications required for all concrete applications on the project?

Yes, the shrinkage reducing admixture is required for all Class A and Class B concrete.

2. Are special inspections the responsibility of the contractor?

It is the responsibility of the owner to hire the 3rd party special inspectors. It is the Contractor’s responsibility to ensure the special inspectors are given ample notification of all upcoming and ongoing work requiring inspection as well as providing safe means of access to inspect the work.

3. Is there a detail and sizing of the concrete stoops outside of the new control building and other misc pads?

See Plan 2 on A-08-101 for stoop sizes. See Section

2 on S-08-301 for stoop reinforcing detailing. All other “misc. pad” slabs-on-grade are dimensioned and detailed in the structural drawings.

4. Are there any below grade waterproofing requirements for walls of new structures?

Provide embedded PVC waterstops at construction joints where shown on drawings. Provide vapor barrier under control building slab and along foundation wall as shown on Section 1/S-08-301.

There are no other waterproofing requirements.

5. Is there a rock removal allowance and/or for the removal of unsuitable soils?

No. There is only a geotechnical report to aid with decision making and risk assessment.

6. What type of material and size is required for the temporary chlorine line? Does the temporary line need to be buried? If so, is there a detail on how to connect to the existing effluent structure?

The Contractor cannot impact the WWTP in such a way that causes a KPDES permit violation. A means for disinfecting and dechlorinating (if needed) needs to be provided if normal disinfection operations at the

WWTP are inhibited, stopped, or interrupted. This could be temporary UV disinfection, chlorine tablets

(with dechlorination), underground or above ground temporary chlorine dosing line (material needs to be compatible with whatever chemical is being used).

Sheet 13 of the as-built plans that were included in

Addendum No. 1 show how the current disinfection

DECA Account No. 670-CBAX-CC21-00 Page 2

GRW Project No. 4803-02

Questions Answers structure is setup. See attached photos of effluent structure.

7. Do the lines TBA need to be capped with ductile iron caps?

Yes, these need ductile iron caps. Mortar caps also work at the end of an abandoned pipe if the seal is water tight.

ATTACHMENT:

• Effluent Structure Photos

Addendum No. 2 Attachment � Effluent Structure Photos

Addendum Two
Addendum No 2 (4)
Attachment - Effluent Structure Photos