Addendum Two .pdf

PDF 2 MB Posted

Attached to
RFB-156-25 DOC EKCC Water Tower Rehabilitation
Solicitation number
RFB-785-2500000344-3
Issued by
Metcalfe County, Kentucky

About this file

This is Addendum Two for Invitation to Bid RFB-156-25 issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration for the Water Tower Rehabilitation project at Eastern Kentucky Correctional Complex in West Liberty, Kentucky. The project involves cleaning and repainting of the 1,500,000-gallon Elevated Water Storage Tank, including abrasive blasting, relining the tank interior, exterior surface preparation, and coating as specified. The addendum adds Sherwin Williams and Carboline coating systems as approved alternatives to the original Tnemec system specification. The bid date has been postponed to January 23, 2025, with questions due by January 10, 2025. The contract requires substantial completion within 120 calendar days and final completion within 150 calendar days.

The engineer's estimate for the project is $2,100,000 with liquidated damages of $750/day beyond substantial completion and $450/day beyond final completion. The contractor is responsible for containment requirements, temporary power, pump station operations, and maintaining prison water supply including 150,000 gallons of fire suppression storage, 600 GPM flow for sprinkler systems, up to 300 GPM flow for peak conditions, and maintaining 125 psi pressure. Technical specifications detail the coating systems, surface preparation requirements, inspection procedures, and disinfection requirements. The contractor must coordinate with prison maintenance staff and utility companies but is not required to provide site lighting, remote monitoring, or temporary security fencing.

View the file

Other files

File Type Posted
Final_RFB_785_2500000344_3_SO_FORM.PDF PDF
Final_RFB_785_2500000344_2_SO_FORM.PDF PDF
Addendum One .pdf PDF
Final_RFB_785_2500000344_1_SO_FORM.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-156-25

FOR: Water Tower Rehabilitation Eastern Kentucky Correctional Complex Department of Corrections West Liberty, Kentucky

DATE: January 13, 2025

ADDENDUM NO. Two (2)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.

END OF ADDENDUM

Invitation to Bid No. RFB-156-25 For: Water Tower Rehabilitation Eastern Kentucky Correctional Complex Department of Corrections

Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration

GRW | engineering | architecture | geospatial

801 Corporate Drive | Lexington, KY 40503

859.223.3999 | www.grwinc.com

ADDENDUM NO. 2

Eastern Kentucky Correctional Complex Water Tower Rehabilitation

GRW Project No. 5106-03

January 13, 2025

SUPPLEMENTAL INFORMATION/ CLARIFICATIONS

1. In addition to the Tnemec coating system in the original Bid Documents, Sherwin Willims and

Carboline coating systems have also been added. Other equal alternate paint systems are allowed but must be submitted for approval.

2. Containment will be required on this project.

3. Background images on the Drawings have been updated.

4. The plan indicated in the drawings is conceptual and intended to provide parameters for maintaining the prison water system and fire suppression and give bidders a general idea of what needs to happen. The Contractor will be required to submit their own plan for maintaining the prison water system and fire suppression. Contractors are encouraged to use the most economical and feasible plan. Contractor must provide the following:

- 150,000 gallons of fire suppression storage and 600 GPM of flow for sprinkler systems.

- Provide up to 300 GPM of flow for peak flow under normal conditions and 140,000 GPD for normal usage.

- Maintain a pressure of 125 psi (measured from the existing pump station) on the prison water system.

SPECIFICATIONS

Section 099713 – Cleaning and Repainting of Steel Water Storage Tank

Replace Paragraph 2.1.A in its entirety with the following.

A. The Paint System shall be as scheduled below:

INTERIOR COATINGS

Tnemec Dry

Mils Sherwin Williams

Dry

Mils Carboline

Dry

Mils

Primer Series 93/94-H2O Hydro-Zinc aromatic zinc – “Greenish Gray”

2.5 – 3.5

Corothane Galvapac –

“Grey”

2.5 – 3.5 Hydroplate 621 PW 2.5 – 3.5

Intermediate

“Stripe Coat”

Series N140-1255 Pota-

Pox Plus – “Beige”

4.0 – 6.0 SherPlate 600 – “Beige” 4.0 – 6.0 Hydroplate 1080 3.0 – 5.0

Intermediate Series 21 Epoxoline –

39BL “Delft Blue”

6.0 – 8.0 SherPlate 600 – “Blue” 6.0 – 8.0 Hydroplate 1080 6.0 – 8.0

Finish Series 21 Epoxoline –

WH16 “Off White”

6.0 – 8.0 SherPlate 600 – “White” 6.0 – 8.0 Hydroplate 1080 6.0 – 8.0

Total

14.5 – 19.5

In the event that pitting has occurred to interior plates then modified polyamine epoxy filler and surfacer shall be applied after the prime coat and trowelled even with the surface of the interior plate. Any fins or protrusions of filler/surface material shall be ground smooth prior to spot priming the surface with polyamidoamine epoxy prior to the application of phenalkamine epoxy.

EXTERIOR COATINGS

Dry

Mils Sherwin Williams

Dry

Mils Carboline

Dry

Mils

Primer

Series 93/94-H2O Hydro-

Zinc aromatic zinc-rich urethane – “Greenish

Gray”

2.5 – 3.5 Corothane Galvapac – “Grey”

2.5 – 3.5 Carbozinc 859 3.0 – 5.0

Intermediate

Series 1095 Endura-

Shield aliphatic acrylic polyurethane – “Beige”

2.0 – 4.0 Hi Solids Polyurethane –

“Beige”

2.0 – 3.0 Carbothane 133LH 3.0 – 5.0

Finish*

Series 700 Hydroflon fluoropolymer polyurethane – 15BL

“Tank White”

2.0 – 3.0 FluoroKem HS 100 2.0 – 3.0 Carboxane 950VOC 2.0 – 3.0

Total 6.5 – 10.5 6.5 – 9.5 8.0 – 13.0

*Finish coat shall be applied by roller application.

EXTERIOR INSIGNIA

Dry

Mils Sherwin Williams

Dry

Mils Carboline

Dry

Mils

Insignia /

Lettering*

Series 700 Hydroflon fluoropolymer polyurethane – 2 coats – 35GR “Black”

2.0 – 3.0 each coat

FluoroKem HS 100 – 2 coats – Black

2.5 – 3.5 each coat

Carboxane 950VOC – 2 coats – C900 “Black”

2.0 – 3.0 each coat

Total 4.0 – 6.0 5.0 – 7.0 4.0 – 6.0

*Insignia / Lettering shall be applied by brush or roller.

Notes: 1. All completed painted areas shall be holiday tested with NACE RPO 188-99 Discontinuity (Holiday) Testing of

New Protective Coatings on Conductive Substrates.

2. An equal alternate paint system is allowed but must be submitted for approval.

Lettering shall be placed on the tank in two locations as directed by the Owner and Engineer. The

Contractor shall submit scaled drawing delineating exact sizing for approval. Lettering shall read

“EKCC”.

Notes:

1. All completed painted areas shall be holiday tested with NACE RPO 188-99 Discontinuity

(Holiday) Testing of New Protective Coatings on Conductive Substrates.

2. An equal alternate paint system is allowed, but must be submitted for approval prior to the bid opening.”

Add Paragraphs 3.9.A and 3.9.B to the end of the section.

A. The Contractor shall prevent the migration of any abrasive blast media, dust, and paint residue onto or from the property of the OWNER. Refer to SSPC-Guide 6 I (CON) Guide for

Containing Debris Generated During Paint Removal Operations. Containment shall be in accordance with applicable federal, state, and local requirements.

B. The Contractor shall be responsible for all cost associated with containment and waste disposal that may result from the execution of this project.

PLANS

Replace Sheets C-00-101 and C-00-102 with the attached sheets.

QUESTIONS

ITEM 1

Q: Who will bring the temporary power proximate to the pump stations?

A: Contractor is responsible for coordination to supply temporary power to pump stations.

ITEM 2

Q: Who will be responsible for paying for temporary power required to run pump stations?

A: The contractor will be responsible for paying for temporary power required to run the pump stations.

ITEM 3

Q: Will there be any requirements for site lighting?

A: There will be no requirements site lighting.

ITEM 4

Q: Will there be any remote monitoring or remote alarm requirements?

A: There will be no remote monitoring or remote alarm requirements.

ITEM 5

Q: Who will make the connections from the power source to the pump stations?

A: The contractor will be responsible for coordinating the connections with the utility company and installing any required conduits.

ITEM 6

Q: Will temporary security fencing be required?

A: No temporary security fencing will be required.

ITEM 7

Q: Who will be responsible for periodic monitoring of the operation of the pump station and the tanks and related documentation?

A: The contractor will be responsible for monitoring and operation of the pump station and coordinating with the prison maintenance staff in the case of an emergency situation.

ITEM 8

Q: Is the 8” line coming from the existing water storage tank still connected to the 10” line coming from West Liberty, Kentucky?

A: The 8” line from the tank is still connected to the 10” main from West Liberty but is valved off.

ITEM 9

Q: Is there any containment required?

A: The contractor will be responsible for containment. Paragraph 3.9 CONTAINMENT AND

DISPOSAL OF DEBRIS has been added to Specification Section 099713 PAINTING ((CLEANING, REPAIRING AND RE-PAINTING OF WATER STORAGE TANKS).

ITEM 10

Q: Is there any specifications that talk about the potable water system that is needed?

A: No. The minimum requirements for fire storage and temporary pump station is listed on the plans. The contractor has the freedom to use the most feasible and economical plan. The winning contractor will be required to submit their own plan for maintaining the prison water supply and fire suppression.

ITEM 11

Q: Is the project prevailing wage?

A: The project is not prevailing wage.

ITEM 12

Q: Is there an 8” hot tap on the inlet for the 600 GPM emergency pump?

A: Either a hot tap or sleeve and valve connection are acceptable. The plan indicated on the drawings is conceptual and intended to provide parameters for maintaining the prison water system and fire suppression and give bidders a general idea of what needs to happen. The Contractor will be required to submit their own plan for maintaining the prison water system and fire suppression.

ITEM 13

Q: Is the location of water line is under roadway?

A: Yes, a portion of the water line is under pavement along the Road to Justice. Water main locations on the Drawings are shown based on existing records but are not exact. Please coordinate all taps connections with EKCC maintenance staff. EKCC will allow for pavement to be cut if needed to execute the Contractor’s plan for maintaining the prison water and fire suppression.

ITEM 14

Q: Is 150K gallons sufficient for fire suppression?

A: Yes, 150k gallons is sufficient for fire suppression.

ITEM 15

Q: Does yelomine pipe have to be used for the above-ground site piping, can welded HDPE be used?

A: No, yelomine does not have to be used for the above-ground site piping and yes HDPE can be used. The plan indicated on the drawings is Conceptual and intended to provide parameters for maintaining the prison water system and fire suppression and give bidders a general idea of what needs to happen. The Contractor will be required to submit their own plan for maintaining the prison water system and fire suppression.

GRW Engineers, Inc.

Name

Project Manager

Attachments:

Specification Section 099713 – Cleaning and Repainting of Steel Water Storage Tank

Sheet C-00-101 Temporary Booster Pumping Plan

Sheet C-00-102 Temporary Storage Plan

Pre-Bid Conference Meeting Minutes

Plan Holders List

5106-03 PAINTING (CLEANING, REPAIRING AND RE-PAINTING 099713-1

OF WATER STORAGE TANKS)Add 1

SECTION 099713 – CLEANING AND REPAINTING OF STEEL WATER STORAGE TANK

PART 1 - GENERAL

1.1 SCOPE OF WORK

The scope of work to be accomplished under this section shall consist of the furnishing of all labor, materials, equipment, and services necessary for the cleaning and re-painting of the Eastern

Kentucky Correctional Complex 1,500,000-gallon Elevated Water Storage Tank. The project involves abrasive blasting and relining the tank interior, as well as exterior surface preparation, and coating as specified.

This specification contains the detailed criteria for the selection of materials, surface preparation, and the furnishing of all coatings, labor, equipment and appliances for field repainting of steel water storage facilities. The following specifications shall govern with modifications as specified herein: ANSI/AWWA D102-11 “AWWA Standard for painting steel water storage tanks” and shall be approved by the Kentucky Division of Water and the National Sanitation Foundation, N.S.F.

1.2 PRODUCT SUBMITTALS

A. Descriptive literature, catalog cuts, and dimensional prints clearly indicating all dimensions and materials of construction, shall be submitted on all items specified herein to the Engineer for review before ordering. Comply with provisions of Part III General Conditions, Article 5 Shop

Drawings-Submittals.

B. At the time of submission, the Contractor shall, in writing, call Engineer's attention to any deviations that the submittals may have from the requirements of the Engineer's Contract

Drawings and Specifications.

PART 2 - PRODUCTS

2.1 PAINT SYSTEM

A. The Paint System shall be as scheduled below:

INTERIOR COATINGS

Dry

Mils Sherwin Williams

Dry

Mils Carboline

Dry

Mils

Primer Series 93/94-H2O Hydro-Zinc aromatic zinc - “Greenish Gray”

2.5 – 3.5

Corothane Galvapac –

“Grey”

2.5 – 3.5 Hydroplate 621 PW 2.5 – 3.5

Intermediate

"Stripe Coat"

Series N140-1255 Pota-

Pox Plus - “Beige”

4.0 - 6.0 SherPlate 600 – “Beige” 4.0 - 6.0 Hydroplate 1080 3.0 – 5.0

5106-03 PAINTING (CLEANING, REPAIRING AND RE-PAINTING 099713-2

Intermediate Series 21 Epoxoline -

39BL “Delft Blue”

6.0 – 8.0 SherPlate 600 – “Blue” 6.0 – 8.0 Hydroplate 1080 6.0 – 8.0

Finish Series 21 Epoxoline -

WH16 “Off White”

6.0 – 8.0 SherPlate 600 – “White” 6.0 – 8.0 Hydroplate 1080 6.0 – 8.0

Total

In the event that pitting has occurred to interior plates then modified polyamine epoxy filler and surfacer shall be applied after the prime coat and trowelled even with the surface of the interior plate. Any fins or protrusions of filler/surface material shall be ground smooth prior to spot priming the surface with polyamidoamine epoxy prior to the application of phenalkamine epoxy.

EXTERIOR COATINGS

Dry

Mils Sherwin Williams

Dry

Mils Carboline

Dry

Mils

Primer

Series 93/94-H2O Hydro-

Zinc aromatic zinc-rich urethane - “Greenish

Gray”

2.5 - 3.5 Corothane Galvapac - “Grey”

2.5 - 3.5 Carbozinc 859 3.0 - 5.0

Intermediate Series 1095 Endura- Shield aliphatic acrylic polyurethane - “Beige”

2.0 - 4.0 Hi Solids Polyurethane –

“Beige”

2.0 - 3.0 Carbothane 133LH 3.0 - 5.0

Finish*

Series 700 Hydroflon fluoropolymer polyurethane - 15BL

“Tank White”

2.0 - 3.0 FluoroKem HS 100 2.0 - 3.0 Carboxane 950VOC 2.0 - 3.0

Total 6.5 – 10.5 6.5 – 9.5 8.0 – 13.0

*Finish coat shall be applied by roller application.

EXTERIOR INSIGNIA

Dry

Mils Sherwin Williams

Dry

Mils Carboline

Dry

Mils

Insignia /

Lettering*

Series 700 Hydroflon fluoropolymer polyurethane – 2 coats -

35GR “Black”

2.0 – 3.0 each coat

FluoroKem HS 100 – 2 coats - Black

2.5 - 3.5 each coat

Carboxane 950VOC – 2 coats – C900 “Black”

2.0 - 3.0 each coat

Total 4.0 – 6.0 5.0 – 7.0 4.0 – 6.0

*Insignia / Lettering shall be applied by brush or roller.

Notes: 1. All completed painted areas shall be holiday tested with NACE RPO 188-99 Discontinuity (Holiday) Testing of

New Protective Coatings on Conductive Substrates.

2. An equal alternate paint system is allowed but must be submitted for approval.

Lettering shall be placed on the tank in two locations as directed by the Owner and Engineer.

The Contractor shall submit scaled drawing delineating exact sizing for approval. Lettering shall read “EKCC”.

Notes: 1. All completed painted areas shall be holiday tested with NACE RPO 188-99

Discontinuity (Holiday) Testing of New Protective Coatings on Conductive

Substrates.

2. An equal alternate paint system is allowed, but must be submitted for approval prior to the bid opening.

B. Workmanship and Materials: Workmanship, procedures, and materials shall in general comply with the requirements of AWWA D102 where applicable.

5106-03 PAINTING (CLEANING, REPAIRING AND RE-PAINTING 099713-3

C. Product Delivery, Storage and Handling:

1. The Contractor shall be responsible for the delivery, storage and handling of coating products.

2. Deliver all materials to the job site in original, new unopened packages and containers bearing manufacturer’s name and label.

3. Provide labels on each container with the following information:

a. Name or title of material;

b. Manufacturer’s stock and batch number;

c. Manufacturer’s name;

d. Contents by Volume, for major pigment and vehicle constituents;

e. Expiration date after which the material should not be used;

f. Thinning instructions; and

g. Application instructions.

4. Store coating products in sealed and labeled containers. Properly store coatings to prevent degradation of the coating products. Do not use coating products that have been damaged during storage, which have not been applied prior to the applicable expiration date, or which do not otherwise comply with the specifications. Promptly remove damaged coating products from the job site.

5. Restrict storage to coating materials and related equipment. Store materials in an area protected in accordance with NFPA Bulletin 101.

6. Product delivery, storage and handling shall meet the requirements of safety, health and fire regulations. Remove used rags from the job site and take all necessary steps to prevent spontaneous combustion.

2.2 INSPECTION EQUIPMENT

A. The Contractor shall furnish the following for purposes of inspection.

1. Pictorial surface preparation standards as provided by the SSPC: The Society for

Protective Coatings (SSPC - Vis 1) or the American Society for Testing and Materials

(ASTM D 2200);

2. Wet film thickness measurement gage;

3. Dry film thickness measurement gage;

4. Appropriate thickness shims for calibration.

5. Steel temperature gages;

6. Sling psychrometer and associated psychrometric tables.

7. Low voltage wet sponge holiday detection equipment.

5106-03 PAINTING (CLEANING, REPAIRING AND RE-PAINTING 099713-4

B. Additionally, the Contractor shall provide any necessary rigging to facilitate the inspection of all tank areas. Proper coordination with the Engineer is intended to prevent extensive re-rigging by the Contractor. Therefore, it is the responsibility of the Contractor to keep the Engineer fully informed on the status of the painting operation.

PART 3 -EXECUTION

3.1 INTERIOR/EXTERIOR WELDS ASSOCIATED WITH REPAIRS

Field preparation of weld seams shall be done in accordance with SSPC SP3 Power Tool Clean methods, removing weld spatter while creating a smooth weld. The weld preparation will be done in such a manner that the surrounding surfaces will have the same surface profile as indicated in Section 3.3.

3.2 CAULKING UN-WELDED ROOF LAP SEAMS

Apply Sikaflex 1A urethane caulk to all voids, stitch welds and un-welded lap seam in roof plates. Care shall be taken to install material to result in a void free continuous film with good adhesion to the finish coat of epoxy. Material shall be installed after the finish coat is complete.

3.3 PREPARATION OF SURFACES

A. Interior Surface Preparation:

The Owner will drain the majority of the water from the tank. The Contractor shall remove all remaining water, mud and debris from the tank.

The tank interior which includes all surfaces, plates, structural shapes, etc. shall be cleaned by grit or abrasive blasting in accordance with Steel Structural Painting Council Surface Preparation

Specification No. 10 (SSPC-SP10/NACE 2) (Near White Metal Blast Cleaning) to achieve a 2.0 minimum sharp angular abrasive blast profile and be in accordance with the requirements of

AWWA D-102-(latest edition). The surface profile shall be verified by measuring with Testex replica tape. All rust, scale, old paint blast media, grit and sediment collected inside the tank bottom shall be entirely removed from the tank and the inside surface swept clean. In cleaning the tank, such rust, scale, and other sediment shall be collected and disposed of, as stated hereinafter.

All interior surfaces shall be cleaned by grit or abrasive blasting. The grit or abrasive blasting equipment shall have ample capacity to furnish the required volume of compressed air to operate the blast effectively. The air shall be free of oil and or moisture. After cleaning, all surfaces shall be wiped free of any residue, dust, or other contaminants before applying prime coat. Prime coat must be applied on the same day that the surface is prepared and before any deterioration of the surface occurs.

B. Exterior Surface Preparation

5106-03 PAINTING (CLEANING, REPAIRING AND RE-PAINTING 099713-5

The tank exterior which includes all surfaces, plates, structural shapes, etc. shall be cleaned by grit or abrasive blasting in accordance with Steel Structural Painting Council Surface Preparation

Specification No. 6 (SSPC-SP6) (Commercial Blast Cleaning) to achieve a minimum 2.0 minimum sharp angular abrasive blast profile and be in accordance with the requirements of

AWWA D-102-(latest edition). The surface profile shall be verified by measuring with Testex replica tape. All rust, scale, old paint blast media, grit and sediment collected shall be entirely removed from the tank. In cleaning the tank, such rust, scale, and other sediment shall be collected and disposed of, as stated hereinafter.

The containment and collection of paint removal debris shall include as a minimum ground cover panels (tarps, etc.). All rust, scale, old paint blast media, grit and sediment shall be collected and disposed of in conformance with the requirements of US EPA and State Regulations.

C. Surface Preparation

Surfaces shall be clean, dry and adequately protected from dampness. Surfaces shall be free of any material, which will adversely affect adhesion or appearance of painting and coating.

Cleanliness shall be checked by wiping the prepared steel surface with a white cloth dampened with manufacturer’s thinner for the particular paint system. If a dark spot or obvious soil appears on the rag from light wiping, the Contractor shall take steps to clean the surface more thoroughly before applying paint via SSPC SP1 standards.

3.4 PAINTING

A. General: All paint shall be applied only under favorable conditions and by skilled painters. All surfaces to which paint is applied shall be clean and dry to the satisfaction of the Engineer. No paint shall be applied during wet or foggy weather, or when the temperature of the air is below

50°F unless otherwise allowed or restricted by the coating manufacturer. The steel surface temperature shall be a minimum of 5°F above dew point. All painting shall be done strictly in accordance with the paint manufacturer's instructions and performed in a manner satisfactory to the Engineer. All coatings shall be in accordance with current EPA Standards.

B. Quality of Paint: The paints and paint products of the manufacturer mentioned in the following specifications are set up as standards of quality and the bid for this Contract shall be based on providing the products of the manufacturer mentioned hereinafter. The products of other manufacturers comparable in quality and type to those specified will be acceptable if said paints are offered by the Contractor with satisfactory data on past performance on water storage tanks, composition, directions for use and other information required, and if approved by the

Engineer. All materials shall be brought to the job site in the original sealed and labeled containers of the paint manufacturer and shall be subject to inspection by the Engineer's inspector on the job. All materials shall be of same manufacturer’s system. In no case shall the products of more than one manufacturer be applied to the same surface.

1. The Contractor shall submit to the Engineer, immediately upon completion of the job, certification from the manufacturer indicating that the quantity of each coating purchased was sufficient to properly coat all surfaces. Such certification shall make reference to the square footage figures provided to the manufacturer by the Contractor.

C. Application of Paint: The painter shall apply each coating at the rate, and in the manner, specified by the manufacturer. The application shall be completed in accordance with SSPC-

5106-03 PAINTING (CLEANING, REPAIRING AND RE-PAINTING 099713-6

PA-2. If the material has thickened or must be diluted for application by spray gun, the coating shall be built up to the same film thickness achieved with undiluted material. The interior immersion finish coating shall be completely without defects permitting moisture penetration when tested according to the low voltage wet-sponge method. Deficiencies in film thickness shall be corrected by the application of an additional coat of paint. Excessive film thickness shall be removed in a manner approved by the coating manufacturer. The paint applicator shall have available on the project site both wet film and dry film thickness measuring devices.

D. Coating Procedures:

1. All coating work shall meet the requirements of the coating manufacturer.

2. All surfaces to be coated shall be in the proper condition to receive the specified coatings before any coatings are applied. Do not blast clean any more surfaces than can be primed within the same working day that the sandblasting is done. Round off all sharp edges and rough welds. Remove all burrs and weld splatter. Remove oil, grease and heavy deposits of surface contaminants by solvent or detergent cleaning. All surfaces shall be clean, dry and free of any dirt, dust, grease, oils, salts, and other deleterious substances before coatings are applied.

3. Whatever metal is cleaned during a working day shall be coated with primer on the same working day.

4. Apply additional stripe coats to all interior critical locations on steel such as welds, corners, fasteners, and edges by the brush method on field prime coat and field intermediate coats. On the exterior welds, corners, fasteners and edges apply additional stripe coat by the brush method using the prime coat.

5. Coatings shall be applied in such a manner to produce as uniform a thickness of coating and as complete coverage as possible, free of lap marks.

6. Each coat shall be allowed to cure within the required air, temperature and humidity ranges as instructed by the manufacturer.

7. The dry film thickness specified shall be obtained. Additional coats shall be applied at the

Contractor’s expense, if required to achieve the specified dry film thickness.

8. Only good, clean brushes and equipment shall be used. Clean all brushes, rollers, buckets and spray equipment at the end of each coating period.

9. Do not start filling the coated tank with water before the coatings have properly dried or cured. The minimum drying or curing time allowed shall not be less than seven (7) days at 75 degrees F.

E. Painting System:

1. Prior to the application of the prime coat, all steel surfaces shall be prepared in accordance with SSPC level specified in 3.3. Create a blast profile of 1.5 to 2.5 mils.

After blast cleaning, all surfaces shall be thoroughly and completely cleaned of all traces of residue and dust.

5106-03 PAINTING (CLEANING, REPAIRING AND RE-PAINTING 099713-7

2. All interior and exterior steel surfaces shall be given a primer coat as specified hereinafter. The primer coat shall be applied the same day as the blast cleaning is completed and prior to the formation of rust. Spray all surfaces within two inches of the edge with one coat, to a dry film thickness as specified. The cleaning and application of the primer are to be done by the fabricator.

3. Interior floor of the tank shall be completely swept clean of all debris, dirt, and loose particles prior to field surface preparation and painting.

4. The interior field intermediate and finish coats shall be as specified hereinafter. Spray all interior surfaces to achieve the dry film thickness as specified. The total dry film thickness for the coating system shall be as specified. Curtains and sags will not be acceptable.

5. The interior of the tank is to have forced ventilation and circulating air continually for the curing period supplied by an exhaust fan capable of circulating air at 25,000 CFM, or of adequate size in relation to the size of the tank. The tanks also shall be allowed to dry at least seven to ten days at atmospheric temperatures of 60º F. or higher to allow proper curing of the completed coating system and solvent removal before it is disinfected and filled with water. During this period, access and ventilation manholes in the tanks shall be left open.

6. The exterior intermediate and finish coats shall be applied to all steel surfaces to the dry coating thickness as specified.

F. Touch-Up and Repair

At completion, all painted surfaces and coatings shall be inspected. All damaged spots, whether due to defective materials or workmanship or defects of surfaces covered shall be touched up and the finish restored. Additional coats of paint and coatings required to cover all spots or discoloration of every sort shall be applied at no additional costs to the Owner.

The Contractor shall furnish to the Owner at least one (1) extra gallon of finish paint specified above for exterior paint for touch-up repairs due to vandalism.

3.5 DISINFECTION OF THE TANK

A. Upon completion of Work and prior to placing the water storage facility into service, it shall be thoroughly sprayed down and disinfected according to the following:

1. Water and chlorine shall be added to the storage facility in amounts such that the solution will initially contain 50 mg/L available chlorine and will fill approximately 5 percent of the total storage volume. This solution shall be sprayed directly onto all surfaces of the water storage facility that would be in contact with water when the water storage facility is full to the overflow elevation. This solution shall be held in the storage facility for a period of not less than 6 hours. The storage facility shall then be filled to the overflow level by flowing potable water into the highly chlorinated water. It shall be held full for a period of not less than 24 hours.

5106-03 PAINTING (CLEANING, REPAIRING AND RE-PAINTING 099713-8

2. Chlorine shall be added to the storage facility by the method described in Section 4.3.1.1, Section 4.3.1.2, or Section 4.3.1.3 of AWWA Standard C652-02, such that a uniform chlorine concentration is obtained during the entire filling operation. The actual volume of the 50-mg/L chlorine solution shall be such that, after the solution is mixed with filling water and the storage facility is held full for 24 hours, there will be a free-chlorine residual of not less than 2 mg/L.

3. After the chlorination procedure is completed, all highly chlorinated water shall be purged from the drain piping and bacteriological sampling and testing shall be performed to ensure that no coliform bacteria are present. Two consecutive samples must show negative results, or the disinfection method must be repeated.

4. Upon completion of successful bacteriological testing, the remaining water may be delivered to the distribution system.

B. Disinfection of the tank shall meet all current requirements of the Kentucky State Division of

Water, shall conform to AWWA C652-02 and shall be accomplished to the satisfaction of the

Engineer. The Contractor shall furnish the disinfectant and accomplish the procedures as specified herein. All necessary water for initial disinfection will be furnished by the Owner.

Additional water needed for repeated disinfection shall be paid for by the Contractor.

3.6 JOB CONDITIONS

A. The Contractor shall ascertain that job conditions are suitable for the application of coatings.

B. Do not apply coatings when the surrounding air temperature, measured in the shade is below

50°F. Do not apply coatings when the temperature of the surface to be coated is below 50°F. Do not apply coating when the relative humidity exceeds 85%. Do not apply coatings in extreme heat. Do not apply coating sin dust or smoke-laden air.

C. Take all precautions necessary to prevent damage of adjoining properties due to coating work.

The Contractor shall be solely liable for such damage.

D. Conduct all operations in a clean and sanitary manner.

E. The Contractor shall not operate valves or controls in the existing waterworks. The Owner will operate all existing valves, hydrants, blowoffs and controls.

F. The Contractor shall furnish (and use) a sling psychrometer with a wet and dry bulb to determine the dewpoint. Adequate surface thermometers shall be provided.

3.7 INSPECTION

A. The Engineer or an outside inspection service representing the Engineer will make inspections noted in this Article. Additional inspection will be made if required. It shall be the responsibility of the Contractor to request an inspection by at least the end of the second day proceeding the inspection day. Should Engineer be summoned to inspect a completed phase of construction and find the work incomplete and, therefore, not ready for inspection, the Contractor shall bear the cost of inspection. It is not the intent to charge the Contractor for an inspection if discrepancies

5106-03 PAINTING (CLEANING, REPAIRING AND RE-PAINTING 099713-9

are found in the completed phase of construction as long as the discrepancies do not necessitate additional inspection trips.

B. The following inspections will be made:

1. After uncoated surfaces in the interior of a tank have been blast cleaned and before coatings are applied, the uncoated surfaces in the exterior of a tank, tower, and appurtenances shall be blasted and primed immediately; however, if the inspector removes any field primer, over blasted or shop primed areas and finds evidence of improper blasting and cleaning, the inspector may order all questionable coatings removed by blasting and the cleaned areas reprimed at no cost to the Owner.

2. After all coating work has been completed; at this time, the total required mil thickness, lack of “holidays” and aesthetic acceptability will be checked by the Engineer.

Additionally, a first anniversary inspection shall be made at approximately one-year’s time after the painting work has been completed to determine whether any repair work is necessary. The Owner shall establish the date for the inspection and shall notify the

Contractor at least 30 days in advance. If an inspection day has not been established with

13 months after final acceptance of the painting work by the Owner, the first anniversary inspection shall be considered to be waived. The Owner shall drain the tank, and the

Contractor shall provide all lighting, ventilation and other equipment necessary to complete the inspection.

Any location where coats of paint have peeled off, bubbled or cracked and any location where rusting is evident shall be considered to be a failure of the paint system. The

Contractor shall make repairs at no cost to the Owner at all points where failures are observed by removing the deteriorated coating, cleaning the surface and recoating with the same paint system. If the areas of failures exceeds 25 percent of the area of a portion of the tank surface, then for that portion, the entire paint system shall be removed and repainted. For purposes of determining the need for complete repainting, the inside roof, shell and floor and the outside roof, shell and floor shall be considered separately.

The Contractor shall prepare and deliver to the Owner an inspection report covering the first anniversary inspection, setting forth the number and type of failure observed, the percentage of the surface area where failure has occurred, and the names of the persons making the inspection. Color photographs shall be included in the report.

C. The Contractor shall furnish the following for purposes of inspection by the Owner.

1. Pictorial surface preparation standards as provided by the Steel Structures Painting

Council (SSPC-Vis 1) or the American Society for Testing and Materials (ASTMD2200):

2. Wet film thickness measurement gauge;

3. Dry film thickness measurement gauge;

4. Certified thickness calibration standards;

5. Steel temperature gauges;

5106-03 PAINTING (CLEANING, REPAIRING AND RE-PAINTING 099713-10

6. Wet bulb and dry bulb temperature-measuring equipment and psychometric tables;

7. Low voltage wet sponge instrument; and

8. “Tooke” gauge.

Additionally, the Contractor shall provide any necessary rigging to facilitate the inspection of all tank areas. Proper coordination with the Engineer is intended to prevent extensive re-rigging by the Contractor. Therefore, it is the responsibility of the Contractor to keep the Owner fully informed on the status of the painting operation.

3.8 SCHEDULING OF WORK

The cleaning and painting of the elevated water storage tank shall be coordinated with the Owner so that the Owner can make arrangements for a constant pressure water supply.

3.9 CONTAINMENT AND DISPOSAL OF DEBRIS

A. The Contractor shall prevent the migration of any abrasive blast media, dust, and paint residue onto or from the property of the OWNER. Refer to SSPC-Guide 6 I (CON) Guide for Containing

Debris Generated During Paint Removal Operations. Containment shall be in accordance with applicable federal, state, and local requirements.

B. The Contractor shall be responsible for all cost associated with containment and waste disposal that may result from the execution of this project.

END OF SECTION 099713

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W

W W

W

W

W

W

W

W

W

W

US

TEMP. BOOSTER PUMPS

1 - 300 GPM PRIMARY PUMP

1 - 300 GPM BACKUP PUMP

SUCTION PRESSURE : 55 PSI

DISCHARGE PRESSURE : 125 PSI

-CONTRACTOR TO PROVIDE

PUMPS CAPABLE TO MAINTAIN

EXISTING SYSTEM CONDITIONS

CLOSE EXISTING VALVE

ROAD TO JUSTICE

6"

12"

10"

8"

EXISTING PUMP STATION

PROVIDES 140,000 GDP,

TDH IS 162'

EX. METER PIT

8" CHECK VALVE

WATER TANK REHABILITATION

EASTERN KENTUCKY CORRECTIONAL COMPLEX

WEST LIBERTY, KENTUCKY

GRW ENGINEERS, INC.

801 CORPORATE DRIVE

LEXINGTON, KY.

(859) 223-3999 / FAX (859) 223-8917

engineeringarchitecturegeospatial www.grwinc.com

TEMP. BOOSTER PUMP

1 - 600 GPM EMERGENCY PUMP

1 - 12"x12"x12" TAPPING TEE 1 - 12"x10" REDUCER

1 - 10"x10"x10" TAPPING TEE

10" RESTRAINED JOINT YELOMINE PIPE

TO BE TEMPORARILY INSTALLED ABOVE

GROUND

GENERAL NOTES:

1. AFTER INSTALLATION OF THE TEMPORARY PIPING,

VALVES, PUMPS, AND TANKS THE CONTRACTOR

SHALL FILL THE TANKS AND CLOSE THE ISOLATION

VALVES ON THE TEMPORARY LINES UNTIL A FIRE

DEMAND IS NEEDED.

2. CONTRACTOR SHALL PROVIDE POWER (OR FUEL)

NEEDED TO OPERATE THE TWO PRIMARY PUMPS

FOR THE ENTIRE TIME THE TANK IS OUT OF SERVICE.

3. CONTRACTOR SHALL PROVIDE POWER (OR FUEL)

NEEDED TO OPERATE THE EMERGENCY PUMP FOR 6

HOURS MINIMUM.

4. CONTRACTOR TO PROVIDE TRAINING/SOP TO DOC

STAFF TO ASSIST IN THE EVENT OF AN EMERGENCY

FIRE SITUATION. THIS INCLUDES CALLING 911,

OPENING/CLOSING VALVES, STARTING THE PUMPS,

AND NOTIFYING UTILITY COMPANY AND DOC.

5. CONTRACTOR SHALL COORDINATE WITH LOCAL

WATER DISTRICT WHEN SWITCHING FROM EXISTING

PUMP STATION TO TEMPORARY PUMPS.

6. THIS IS A CONCEPTUAL LAYOUT OF THE MINIMUM

REQUIREMENTS FOR TEMPORARY WATER SUPPLY

AND FIRE SUPPRESSION WHILE THE TANK IS OUT OF

SERVICE. CONTRACTOR SHALL SUBMIT PLAN FOR

TEMPORARY WATER SUPPLY AND FIRE

SUPPRESSION.

8" RESTRAINED JOINT

YELOMINE PIPE

1 - 12"x12"x8" TAPPING TEE

HORIZONTAL SCALE: 1" = 10'-0"

20'10'0 30'5'

AutoCAD SHX Text

WM

AutoCAD SHX Text

AS BUILT DATE

AutoCAD SHX Text

DECA LOG #

AutoCAD SHX Text

A&E FILE NO.

AutoCAD SHX Text

CHECKED BY

AutoCAD SHX Text

DRAWN BY

AutoCAD SHX Text

SEPTEMBER,2024

AutoCAD SHX Text

DRAWING DATE

AutoCAD SHX Text

DRAWING INFORMATION

AutoCAD SHX Text

AutoCAD SHX Text

DRAWING NO.

AutoCAD SHX Text

DECA REVIEWED

AutoCAD SHX Text

RTA DATE

AutoCAD SHX Text

FRANKFORT, KENTUCKY

AutoCAD SHX Text

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

AutoCAD SHX Text

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

AutoCAD SHX Text

FINANCE AND ADMINISTRATION CABINET

AutoCAD SHX Text

COMMONWEALTH OF KENTUCKY

AutoCAD SHX Text

ACCOUNT NO.

AutoCAD SHX Text

DATE

AutoCAD SHX Text

DATE

AutoCAD SHX Text

APPROVED FOR PROGRAM CONCEPT ONLY

AutoCAD SHX Text

APPROVED FOR PROGRAM CONCEPT ONLY

AutoCAD SHX Text

AGENCY

AutoCAD SHX Text

DIVISION OF

AutoCAD SHX Text

ENGINEERING

AutoCAD SHX Text

AUTHORIZED AGENT

AutoCAD SHX Text

FOR INTENT ONLY

AutoCAD SHX Text

JFE

AutoCAD SHX Text

MSW

AutoCAD SHX Text

527 CAL 6VR 3900

AutoCAD SHX Text C-00-101

AutoCAD SHX Text

TEMPORARY BOOSTER PUMPING - PLAN

AutoCAD SHX Text

ADDENDUM 1

W W

W W

W

W

W

W

W W

W W

W W

W W

W

W

W

W

W

W

W

W W

W W

W

W

W

W

W W

W W

W W

W W

W

W

W

W

W

W W

ROAD TO JUSTICE

8"

12"

MINIMUM TOTAL

150,000 GALLON

STORAGE TANKS

1 - 12"x12"x8" TEE

1 - 12" GATE VALVE

1 - 8" GATE VALVE

1 - 8" CHECK VALVE

1 - 8"x8"x8" TEE

2 - 8" GATE VALVE

WATER TANK REHABILITATION

EASTERN KENTUCKY CORRECTIONAL COMPLEX

WEST LIBERTY, KENTUCKY

GRW ENGINEERS, INC.

801 CORPORATE DRIVE

LEXINGTON, KY.

(859) 223-3999 / FAX (859) 223-8917

engineeringarchitecturegeospatial www.grwinc.com

CONCRETE

BARRICADE

CONCRETE

BARRICADE

TRAFFIC RAMP

OVER TEMPORARY

WATER LINE

TRAFFIC RAMP

OVER TEMPORARY

WATER LINE

8" RESTRAINED JOINT YELOMINE PIPE

TO BE TEMPORARILY INSTALLED ABOVE

GROUND

1. CONTRACTOR TO PROVIDE TRAINING/SOP TO DOC

STAFF TO ASSIST IN THE EVENT OF AN EMERGENCY

FIRE SITUATION. THIS INCLUDES CALLING 911,

OPENING/CLOSING VALVES, STARTING THE PUMPS,

AND NOTIFYING UTILITY COMPANY AND DOC.

2. CONTRACTOR SHALL COORDINATE WITH LOCAL

WATER DISTRICT WHEN SWITCHING FROM EXISTING

PUMP STATION TO TEMPORARY PUMPS.

3. THIS IS A CONCEPTUAL LAYOUT OF THE MINIMUM

REQUIREMENTS FOR TEMPORARY WATER SUPPLY

AND FIRE SUPPRESSION WHILE THE TANK IS OUT OF

SERVICE. CONTRACTOR SHALL SUBMIT PLAN FOR

TEMPORARY WATER SUPPLY AND FIRE

SUPPRESSION.

GENERAL NOTES:

HORIZONTAL SCALE: 1" = 20'-0"

0 20' 40' 60'10'

AutoCAD SHX Text

AS BUILT DATE

AutoCAD SHX Text

DECA LOG #

AutoCAD SHX Text

A&E FILE NO.

AutoCAD SHX Text

CHECKED BY

AutoCAD SHX Text

DRAWN BY

AutoCAD SHX Text

SEPTEMBER,2024

AutoCAD SHX Text

DRAWING DATE

AutoCAD SHX Text

DRAWING INFORMATION

AutoCAD SHX Text

AutoCAD SHX Text

DRAWING NO.

AutoCAD SHX Text

DECA REVIEWED

AutoCAD SHX Text

RTA DATE

AutoCAD SHX Text

FRANKFORT, KENTUCKY

AutoCAD SHX Text

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

AutoCAD SHX Text

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

AutoCAD SHX Text

FINANCE AND ADMINISTRATION CABINET

AutoCAD SHX Text

COMMONWEALTH OF KENTUCKY

AutoCAD SHX Text

ACCOUNT NO.

AutoCAD SHX Text

DATE

AutoCAD SHX Text

DATE

AutoCAD SHX Text

APPROVED FOR PROGRAM CONCEPT ONLY

AutoCAD SHX Text

APPROVED FOR PROGRAM CONCEPT ONLY

AutoCAD SHX Text

AGENCY

AutoCAD SHX Text

DIVISION OF

AutoCAD SHX Text

ENGINEERING

AutoCAD SHX Text

AUTHORIZED AGENT

AutoCAD SHX Text

FOR INTENT ONLY

AutoCAD SHX Text

JFE

AutoCAD SHX Text

MSW

AutoCAD SHX Text

527 CAL 6VR 3900

AutoCAD SHX Text C-00-102

AutoCAD SHX Text

TEMPORARY STORAGE - PLAN

AutoCAD SHX Text

ADDENDUM 1

Pre-Bid Meeting Minutes

EKCC Water Tower Rehabilitation, West Liberty, KY Account Number 527 CAL 6VR 3900

RFB 156-25

Date: December 20, 2024

1. Welcome / Sign In Sheet:

A. Attendees were asked to type their name and company in the chat to serve as the sign-in sheet.

Greg Schenck DECA

Susan Ward DECA

Gene Whitaker EKCC / DOC

Michael Smith EKCC / DOC

Tony Waddell DOC

Frank England GRW Engineers, Inc

Mike Jacobs GRW Engineers, Inc

Dominic Pedersen Viking Industrial Painting

Jeff Hidebrandt Currens Construction

Dave Cull Currens Construction

Jeff Coulter Currens Construction

Bailey Mitchell E&L Contractors, Inc

Stephen Bazant TMI Coatings

Rocky Bentley Debcon, Inc

Kathleen Anderson D & M Painting Corporation

Mike Ritterbeck CPS Tank Assist

Jessie Almon Pittburg Tank & Tower Maintenance Co., Inc

2. Introductions:

A. Owner – Department of Corrections - EKCC

- Shawn McKenzie, Warden, shawn.mckenzie@ky.gov

- Tony Waddle, Project Manager, tonya.waddelle@ky.gov

- Doug Nickell, Maintenance Branch Manager at EKCC, Douge.nickell@ky.gov

B. Funding – DECA

- Susan Ward, Purchasing Agent, (502) 226-0335, susan.ward@ky.gov

- Greg Schenk, Project Manager, (502) 234-0519 greg.schenck@ky.gov

C. GRW Engineers, Inc.

- Frank England, PE, Project Manager, (606) 307-4862, fengland@grwinc.com

- Mike Jacobs, PE, Principal, (859) 552-0406, mjacobs@grwinc.com

3. Brief Project Overview:

mailto:shawn.mckenzie@ky.gov mailto:tonya.waddelle@ky.gov mailto:Douge.nickell@ky.gov mailto:susan.ward@ky.gov mailto:greg.schenck@ky.gov mailto:fengland@grwinc.com mailto:mjacobs@grwinc.com

RFB 156-25

The scope of work to be accomplished under this section shall consist of the furnishing of all labor, materials, equipment, and services necessary for the cleaning and re-painting of the Eastern Kentucky Correctional Complex 1,500,000-gallon Elevated Water Storage Tank. The project involves abrasive blasting and relining the tank interior, as well as exterior surface preparation, and coating as specified. Additional work included installing and maintaining the temporary potable water pumping systems, water storage ground fire suppression tanks and pumps.

A. Construction Contract Time

- Substantial Completion: 120 Calendar Days

- Final Completion: 150 Calendar Days

- Contract standard work hours 7:30 to 3:30

B. Bidding Documents (Plans/Specifications) Available at:

https://www.stateofkyplanroom.com/

C. Engineer’s Estimate $2,100,000

D. Liquidated Damages

- $750/day for each day beyond Substantial Completion

- $450/day for each day beyond Final Completion

4. Bidding:

A. All questions including the ones asked at the Pre-Bid meeting must be submitted in writing to Frank England, fengland@grwinc.com.

B. Bid questions due no later than 1/10/2025

C. Bid Date/Time is being postponed to January 23, 2025 (currently set for 12/30/24 at 1:30 PM

ET) - See the digital submission process is described in the Advertisement on the State of Ky Plan Room website.

5. General Items:

A. Review site access and DOC requirements.

B. Review temporary pumping and water storage plan (general requirements).

https://www.stateofkyplanroom.com/ mailto:fengland@grwinc.com

RFB 156-25

6. Contractors Comments/Questions:

A. Attendees were reminded that any answers given at the meeting were unofficial and to submit any questions they had via email to the engineer.

B. Q: Who will bring the temporary power proximate to the pump stations?

A: Contractor is responsible for coordination to supply temporary power to pump stations.

C. Q: Who will be responsible for paying for temporary power required to run pump stations?

A: The contractor will be responsible for paying for temporary power required to run the pump stations.

D. Q: Will there be any requirements for site lighting?

A: There will be no requirements site lighting.

E. Q: Will there be any remote monitoring or remote alarm requirements?

A: There will be no remote monitoring or remote alarm requirements.

F. Q: Who will make the connections from the power source to the pump stations?

A: The contractor will be responsible for coordinating the connections with the utility company and installing any required conduits.

G. Q: Will temporary security fencing be required?

A: No temporary security fencing will be required.

H. Q: Who will be responsible for periodic monitoring of the operation of the pump station and the tanks and related documentation?

I. A: The contractor will be responsible for monitoring and operation of the pump station and coordinating with the prison maintenance staff in the case of an emergency situation.

J. ITEM 8

K. Q: Is the 8” line coming from the existing water storage tank still connected to the 10” line coming from West Liberty, Kentucky?

A: The 8” line from the tank is still connected to the 10” main from West Liberty but is valved off.

L. Q: Is there any containment required?

A: Yes, containment will be required. This will be addressed in the final addendum.

Addendum Two
EKCC Tank Rehab - Addendum #2
099713 - Cleaning and Repainting of Steel Water Storage Tank
5106-C-00-101-3.1
3.1
5106-C-00-102-3.2
3.2
Pre-Bid Minutes
Plan Holders List

File details come from the government source that posted it. Updated .