Addendum One .pdf
PDF 28 MB Posted
- Attached to
- RFB-103-26 24014AMLBAML, Lawrence County
- Solicitation number
- RFB-785-2600000188-2
- Issued by
- Jessamine County, Kentucky
About this file
This document is an Addendum and Invitation to Bid issued by the Commonwealth of Kentucky's Department for Facilities and Support Services, Division of Engineering and Contract Administration, and the Department for Natural Resources, Division of Abandoned Mine Lands for the 24014 AMLBAML AML Project in Lawrence County, Kentucky. The project involves a reclamation and drainage improvement effort across two designated areas, with a total project limit of 17.03 acres and an expected disturbance of 6 acres. The contract specifies a 90-calendar day completion timeline from the contract award date, with specific drainage, subdrain, ditch installation, and environmental restoration activities. The bid includes 23 separate line items covering mobilization, utility relocation, structure removal, site preparation, erosion control, earthwork, and revegetation efforts.
The bid schedule includes unit pricing for various project components, with an emphasis on sediment and erosion control best management practices. The project will involve installing subdrains, Class II and III ditches, replacing culverts, and addressing drainage issues caused by previous surface and auger mining activities. The total project cost is not explicitly stated, but bidders must conform to an Allowable Price Limit (APL) for each unit, with significant deviations potentially requiring written justification. The project includes provisions for potential bat habitat conservation, utility relocation, and strict adherence to environmental control measures, with the contractor responsible for obtaining necessary permits beyond those secured by the Kentucky Division of Abandoned Mine Lands.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final_RFB_785_2600000188_1_SO_FORM.PDF | ||
| Final_RFB_785_2600000188_2_SO_FORM.PDF |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-103-26
FOR: 24014 AMLBAML
AML Project Lawrence County, Kentucky
DATE: October 29, 2025
RFB-785-2600000188
ADDENDUM NO. One (1)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to attached addendum for all additions, deletions, and/or changes to specifications and/or drawings.
Item 2: Bidders must use Revised Bid Schedule 10/29/2025, in lieu of previously issued.
END OF ADDENDUM
Invitation to Bid No. RFB-103-26 For: 24014 AMLBAML
AML Project Lawrence County, Kentucky
Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration
NO. ITEM M.O.P. UNIT QUANTITY * Low APL UNIT PRICE TOTAL
1 MOBILIZATION L.S. L.S. 1.0 X NA ≤ NA = 25,000.00$
2 UTILITY RELOCATION/REPLACEMENT A.C.U. A.C.U. 1,500.0 X NA ≤ 1.00$ = 1,500.00$
3 STRUCTURE REMOVAL/REPLACEMENT L.S. A.C.U. 5,000.0 X NA ≤ =
4 SITE PREPARATION U.P. ACRE 6.0 X $750.00 ≤ $ = $
5 FILTER FABRIC U.P. SY 1,500.0 X $0.50 ≤ $ = $
6 GEO-GRID U.P. SY 1,715.0 X $2.00 ≤ $ = $
7 NO. 2 STONE BACKFILL U.P. TON 525.0 X $15.00 ≤ $ = $
8 SILT BARRIER - BALES & FENCE U.P. LF 2,500.0 X $1.00 ≤ $ = $
9 SILT TRAP - TYPE A & B U.P. EACH 1.0 X $500.00 ≤ $ = $
10 EARTHWORK - GRADEWORK U.P. ACRE 1.5 X $2,500.00 ≤ $ = $
11 EROSION CONTROL BLANKET- ECB U.P. SY 1,725.0 X $0.75 ≤ $ = $
12 CLASS II / III U.P. TON 1,275.0 X $20.00 ≤ $ = $
13 SUBDRAIN U.P. LF 1,570.0 X $15.00 ≤ $ = $
14 36" DIA. HDPE PIPE- STANDARD U.P. LF 40.0 X $0.00 ≤ $ = $
15 CONCRETE HEADWALL- PIPES ≤36" DIA. U.P. EACH 2.0 X $900.00 ≤ $ = $
16 SEEDBED PREPARATION U.P. ACRE 5.0 X $75.00 ≤ $ = $
17 AGRICULTURAL LIMESTONE U.P. TON 50.0 X $20.00 ≤ $ = $
18 FERTILIZER U.P. TON 2.0 X $600.00 ≤ $ = $
19 SEED U.P. LBS 400.0 X $4.00 ≤ $ = $
20 MULCH- STRAW & HAY U.P. ACRE 5.0 X $100.00 ≤ $ = $
21 COVER CROP U.P. BUSHEL 5.0 X $10.00 ≤ $ = $
22 DENSE GRADE AGGREGATE U.P. TON 50.0 X $20.00 ≤ $ = $
23 ROADWAY STONE U.P. TON 600.0 X $20.00 ≤ $ = $
BID TOTAL = $
* Any Unit Price outside the Allowable Price Limit (APL) range may be considered an unbalanced bid and may have to be justified in writing if such bid is deemed the low responsive bid.
24014AMLBAML RECLAMATION PROJECT (ADD. #1)
LAWRENCE COUNTY, KENTUCKY
BID SCHEDULE
NOTE: THE AUTHENTICATION OF BID AND STATEMENT OF NON-COLLUSION AND NON-CONFLICT OF INTEREST PAGE MUST BE PROPERLY EXECUTED FOR THE TOTAL BID
AMOUNT TO BE VALID.
REVISED BID SCHEUDLE 10/29/2025
RFB-103-26
Revised 12/11/2024
COR & BID & BMP 1
24014AMLBAML RECLAMATION PROJECT (ADD. #1)
LAWRENCE COUNTY, KENTUCKY
Written Location Directions: The site is located near Webbville in Lawrence County. GPS at site is 38.0868°N, 82.8636°W. Physical address is 566 Lick Fork Branch, Webbville KY. Driving Directions:
From the intersection of US-23 and KY-201 near Paintsville, travel KY-201N (toward Blaine) 15.3 miles and turn right onto KY-32. Travel 0.2 miles and turn left onto KY-201. Travel 5.6 miles and turn left onto Lick Creek Road. Travel 0.9 miles and turn left onto the citizens driveway. The project site is at the end of the driveway. All waste material generated by this project will be disposed of at the project site and within project limits.
Basic Project Description: This site is the location of previous surface/auger mine works. Drainage from the mine works is causing damage to the reclaimed pasture areas and was previously addressed partially as the Nelson Thompson Slide and Drainage HP AMLRP. This project proposes to correct drainage issues that persist after the previous project. This project has two separate areas (Areas “A” and “B”). At Area “A”, subdrains will be installed on the existing bench above the Barn/Lot. Additional subdrain will be installed on the slope above the Barn/Lot at a identified saturated area. This water will be conducted via Class II/III ditches and culverts to the established natural drain. Additional subdrain will be placed in the maintained pasture area where drainage is migrating to the surface. These subdrains will outlet to the existing diversion immediately downslope of the pasture area. At Area “B”, core drains that were previously installed have failed. The core drains will be removed and replaced with standard subdrains with the outlets to a previously installed ECB ditch.
The project site and waste areas have previously been disturbed by coal mining operations, residential development and landowner activities. These disturbances consist of significant upheaval, mixing, and removal of earthen material from deep excavation, grading, sub-surface drilling, fill material placement, and erosion. There should be no undisturbed earthen material to a depth of several feet at the areas slated for significant project-related construction activities.
The strict implementation and enforcement of standard AML sediment and erosion control Best Management Practices (BMPs) will prevent significant amounts of sediments disturbed by project related activities from entering area streams to create indirect impacts to aquatic resources. Sediment control will be installed prior to beginning any major earth disturbance (excluding initial site preparation for access only) until all measures are installed. These include but are not limited to silt barriers (bales & silt fence).
Project limits include 17.03 acres, which includes 0.46 acres being used for waste. There will be a total expected disturbance of 6 acres. Trees greater than 3” diameter at breast height will be cut for access to and installation of drainage (0.74 acres). No unstable areas have been identified for tree removal. If required, AML will elect to make a payment to the Imperiled Bat Conservation Fund in accordance with a determination from USFWS.
All disturbed areas will be promptly revegetated at the end of construction using lime, fertilizer, residential or wildlife seed, and mulch, as necessary. Revegetation bid items including cover crop are allotted for prompt establishment of vegetation. Trees and brush will be burned at the project site.
No caves or cave-like structures will be addressed as part of this project.
458 LF of current ephemeral stream impacted by Acid Mine Drainage will be replaced by the installation of Class II/III ditches. No other streams or water bodies will be impacted by this project.
40LF of 24” HDPE pipe (culvert) will be replaced with like material.
COR & BID & BMP 2
Access to the site is via state and county roads, residentially maintained driveways and yards. This project will include pre- and/or post- project maintenance and repair of existing previously constructed public county roads utilized during the construction of this project, which are administered by the county or local road authority. This construction activity will be conducted under the authority and supervision of the local public road authority and will consist of standard road construction practices appropriate to mitigate impacts to the local community from potential degraded road conditions in order to maintain public traffic safety.
A. STANDARD DOCUMENTS
The AML Standard Details, Technical Specifications, and Bid Item Descriptions are posted on the Division’s website at https://eec.ky.gov/Natural-Resources/Mining/Abandoned-Mine- Lands/Pages/default.aspx
Once on the web page, please click “Contractor Information” tab located on the right side. AML standard technical specification and detail are located under this tab. Contractors are strongly encouraged to review the complete AML website for additional information.
B. ALLOWABLE PRICE LIMIT
The lowest Allowable Price Limit (APL) is listed on the Bid Schedule as part of the bid documents. Unit Price, Plan Quantity, and Lump Sum are all methods of payment. Significantly low or high values entered by the CONTRACTOR on the Bid Schedule may be considered an unbalanced bid and may have to be justified in writing if such bid is deemed the low responsive bid.
An example would be if a CONTRACTOR assumes there may not be a need for the entire design quantity for Roadway Stone and entered a $10 value for Roadway Stone when the cost at the quarry is significantly higher. Another example would be if the CONTRACTOR enters a value of $30 per linear foot for “SILT BARRIER - BALES & FENCE” to front load payments for work items used near the beginning of the project. The CONTRACTOR is also cautioned that other considerations for rejection may be enforced such as the low bid being higher than the budgeted dollar amount for this project.
C. CONTRACT LENGTH
All work shall be completed within NINETY (90) calendar days from the effective date of the Award of Contract. Within the bounds of prudent project performance, it shall be the responsibility of the CONTRACTOR to plan and implement construction sequences which follow the intent of these CONTRACT DOCUMENTS, particularly as, reflected in the Drawings and Special Conditions and to protect any portion of the contract which may be completed before others.
D. CONTRACTOR’S INFORMATION SHEET
The AML CONTRACTOR/SUBCONTRACTOR INFORMATION FORM sheet must be filled out and submitted with the bid. Failure to submit the AML Contractor/Subcontractor Information Form sheet with the bid will be the basis for declaring the bid “Non-Responsive.”
E. SPECIAL CONDITIONS & PROJECT NOTES
COR & BID & BMP 3
- When applicable, AML is responsible for payment to the Imperiled Bat Conservation Fund
(ICBF). The CONTRACTOR will be responsible for adhering to the boundary for which payment was made and confirming with AML the acreage of trees removed.
- On occasion, a property owner may require a CONTRACTOR to add them on their General
Liability and/or Automobile Insurance as an “Additional Insured.” AML will inform the
CONTRACTOR when this requirement is being made by the property owner. In these cases, the
CONTRACTOR must submit to AML copies of their certificate of insurance documenting the
“Additional Insured” before they will be allowed to mobilize equipment and forces on to said properties. Any fees, rate increases, or other costs incurred by the CONTRACTOR for this requirement, if any, will be considered incidental to mobilization and as such no compensation will be made by AML. The “Additional Insured” must remain on the CONTRACTOR’s policy(s) for the full length of the contract.
F. DAVIS BACON SCALE WAGES
The CONTRACTOR and all SUBCONTRACTORS are required to pay scale wages as defined in the contract documents. If all employment categories that may be used have not been listed and specified in the contract document, then the contractor must make his best determination of what the missing wage rate will be. Subsequently after the bid is awarded, the contractor must request the specific rate from the
Department of Labor. AML will not issue change orders for additional compensation if the wage rate determined by DOL is higher than the rate the contractor used to develop his bid. If wage rates are not included for a specific category, AML suggests that the contractor assume the highest operator or laborer wages that are listed when developing his bid.
G. PERMITS & FEES – AML will be responsible for obtaining any permits that are checked below.
(Check all that apply)
☐KYTC Encroachment Permit
☐KY DOW Water Permits
☐USACE Permit
The CONTRACTOR is responsible for all other permits and/or fees necessary to begin the project. The
CONTRACTOR is advised that on occasion, other permits and/or fees may be required by federal, state, and local government(s). Other types of permits and/or fees are not the responsibility of AML and as such, these will be the complete and total responsibility of the CONTRACTOR to obtain. These must be obtained before AML will allow mobilization of equipment and forces on to said properties. All costs associated with other permits or fees will be the responsibility of the CONTRACTOR. Please refer to
“General Provisions” in the AML Technical Specifications.
COR & BID & BMP 4
BID ITEM DESCRIPTION
24014AMLBAML AML RECLAMATION PROJECT (ADD. #1)
LAWRENCE COUNTY, KENTUCKY
NO ITEM DESCRIPTION
1 MOBILIZATION This item consists of the mobilization and demobilization of the CONTRACTOR’S forces and equipment in accordance with the “Mobilization/Demobilization” AML Standard Technical Specification. The amount of this bid item is not to exceed 5 percent of the sum of the lump sum bid price.
Measurement: Not Applicable.
Payment: Payment shall be made at increments set in the AML Technical Specifications totaling the Lump Sum price.
2 UTILITY
RELOCATION /
REPLACEMENT
This consists of furnishing all materials, equipment, and labor necessary to replace utilities damaged by construction or relocate any utilities that are in the construction area in accordance with the “Utility Relocation” AML Standard Technical Specification. The CONTRACTOR is required to supply the ENGINEER with all documentation to support cost incurred to qualify for reimbursement.
Special Considerations: None Major Incidentals: These will be listed in writing by the ENGINEER prior to beginning the work.
Measurement: Not Applicable.
Payment: Payment shall be made for Actual Documented Costs for “UTILITY RELOCATION/REPLACEMENT” approved by the ENGINEER. The payment shall be a direct reimbursement for actual documented costs to the CONTRACTOR in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and incidentals.
COR & BID & BMP 5
3 STRUCTURE
REMOVAL/
REPLACEMENT
This item represents the ENGINEER'S best estimate of removal/replacement cost of designated qualifying structural features “in kind” to facilitate normal construction activities as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Structure Removal / Replacement” AML Standard Technical Specification. The CONTRACTOR is required to supply the ENGINEER with all documentation to support cost incurred to qualify for reimbursement.
Special Considerations: This bid item is intended for the removal and replacement of livestock fences and other features necessary to complete the construction as designed.
Inspector Notes: Inventory of structures, pictures, and dimensions, before construction starts. Any structures that are removed shall be accompanied by pictures.
Major Incidentals: These will be listed in writing by the ENGINEER prior to beginning the work.
Measurement: None Payment: Payment shall be made for Actual Documented Costs for “STRUCTURE REMOVAL/REPLACEMENT” approved IN ADVANCE by the ENGINEER. The payment shall be a direct reimbursement for actual documented costs to the CONTRACTOR in accordance with the “General
4 SITE PREPARATION This item of work shall consist of furnishing all materials, equipment, and labor as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Site Preparation” AML Standard Technical Specification.
Special Considerations: None Major Incidentals: Clearing, grubbing, windrowing, burning, pipe removal and disposal, pipe cleanout, temporary diversion ditch construction, domestic debris removal and disposal, concrete & bituminous asphalt debris removal and disposal, access improvement/construction, in-kind fence repair/replacement, and temporary stream diversion.
Measurement: Actual Quantities shall be measured with a handheld GPS and rounded up to the next whole 0.5 acre actually cleared and grubbed (excludes slurry and refuse areas.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “SITE PREPARATION” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and other items necessary to complete the work.
COR & BID & BMP 6
5 FILTER FABRIC This item consist of furnishing all materials, equipment, and labor, necessary to install filter fabric utilized in ditch construction as depicted on the Drawings and as directed by the ENGINEER in accordance with “Filter Fabric” AML Standard Technical Specification. This includes all types of filter fabric used on a jobsite. The standard details list the type and quantity of fabric for each purpose.
Special Considerations: None Inspector Notes: Collect manufacturer certificates for each unit.
Major Incidentals: Staples Measurement: Actual Quantities shall be measured as the next whole square yard installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “FILTER FABRIC” in accordance with the “General
6 GEOGRID This item consist of furnishing all materials, equipment, and labor, necessary to install geogrid, including all labor, materials, and accessories as depicted on the Drawings and as directed by the ENGINEER in accordance with “Geo-grid” AML Standard Technical Specification. All geo-grid is bi-axial, except for tails behind Non-reinforced Block Walls- Type I.
Special Considerations: None Inspector Notes: Collect manufacturer certificates for each unit.
Major Incidentals: Staples Measurement: Actual Quantities shall be measured as the next whole square yard installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “GEOGRID” in accordance with the “General
7 NO. 2 STONE
BACKFILL
This item shall consists of furnishing all materials, equipment, and labor necessary to place No. 2 stone aggregate as depicted on the Drawings and as directed by the ENGINEER in accordance with “Crushed Aggregate and Channel Lining” AML Standard Technical Specification.
Special Considerations: None Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) installed and accepted by the
ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “NO. 2 STONE BACKFILL” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and incidentals.
COR & BID & BMP 7
8 SILT BARRIER–
BALES & FENCE
This item consists of furnishing all materials, equipment, and labor necessary to maintain silt control as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Silt Control” AML Standard Technical Specification. Hay/straw bales shall be placed with an overlap equal to 0.4 bales per linear foot of silt control fencing. Silt fence shall be trenched and removed at the end of the project. Failure to remove silt control fence (geotextile fabrics) shall result in forfeiture of demobilization.
Special Considerations: None Major Incidentals: Maintenance, silt fence trenching and removal Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “SILT BARRIER - BALES & FENCE" in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for materials, equipment, labor, and
9 SILT CONTROL –
TRAP TYPE A & B
This item consist of furnishing all materials, equipment, and labor necessary to maintain silt control as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with “Silt Control” AML Standard Technical Specifications. When a 3:1 length to width ratio is not possible install baffles or turbidity curtains.
Special Considerations: None Major Incidentals: Excavation, rock, baffles/turbidity curtains, maintenance Measurement: Actual Quantities shall be measured as “EACH” unit installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “SILT CONTROL – TRAP TYPE A & B” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for materials, equipment, labor, and incidentals.
10 EARTHWORK –
GRADEWORK
This item consist of furnishing all materials, equipment, and labor necessary to accomplish the required excavating, placement, and grading of material as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Earthwork” AML Standard Technical Specification.
Special Considerations: None Measurement: Actual Quantities shall be measured with a handheld GPS and rounded up to the next whole 0.5 acre.
Payment: Payment shall be the product of the Plan Quantity Volume and the Unit Price bid for “EARTHWORK-GRADEWORK” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and other items necessary to complete the work—this includes all transportation and gradework efforts associated with designated waste areas.
COR & BID & BMP 8
11 EROSION
CONTROL
BLANKET-ECB
(BENCHES,
DITCHES, &
SLOPES)
This item consist of furnishing all materials, equipment, and labor necessary to install all types of erosion control blanket (ECB) as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Erosion Control Blanket” AML Standard Technical Specification.
Subgrade preparation shall be incidental. Placement of ECB for slope protection will also be covered by this bid item.
Special Considerations: None Major Incidentals: Excavation, subgrade preparation Measurement: Actual Quantities shall be measured as the next whole square yard, including overlaps, installed and approved by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “EROSION CONTROL BLANKET-ECB” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation full compensation for all labor, materials, equipment, and incidentals.
12 CLASS II / III –
(DITCHES,
ANCHORS, DRAINS,
& BUTTRESSES)
This item consist of furnishing all materials, equipment, and labor necessary to install Class II and Class III rock as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with “Crushed Aggregate and Channel Lining” and “Ditches” AML Standard Technical Specifications. Subgrade preparation shall be incidental. For channels with acid mine drainage DAML will use the current Limestone Sample Results published by the KY Department of Agriculture to determine an effective weight when material is from a source with < 85% calcium carbonate.
Special Considerations: None Inspector Notes: Collect supplier tickets.
Major Incidentals: Excavation, subgrade preparation Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) installed and accepted by the ENGINEER. Material for treating AMD and not meeting the 85% minimum is adjusted by multiplying the weight ticket tons by the ratio of the report % CaCO3 (as Calcium %) to the 85% minimum, rounded to the nearest ton.
Material exceeding the 85% minimum is not adjusted.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “CLASS II/III” in accordance with the “General constitute full compensation for all labor, materials, equipment, and incidentals.
COR & BID & BMP 9
13 SUBDRAIN This item of work shall consist of furnishing all materials, equipment, and labor necessary to install subsurface drains as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Crushed Aggregate and Channel Lining”, “Filter Fabric”, and “Subsurface Drains” AML Standard Technical Specifications.
Special Considerations: None Major Incidentals: Excavation to depth of 3’, pipe, filter fabric, aggregate backfill to depth of 3’.
Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER. Subdrains requiring more than the incidental quantity of rock will be paid from the No. 2 Stone bid item or Roadway Stone if a No. 2 Stone bid item is not listed. All excavation is incidental to the earthwork.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “SUBDRAIN” in accordance with the “General
36” DIA. HDPE PIPE-
STANDARD
This item consists of furnishing all materials, equipment, and labor, necessary to install standard, non-steel reinforced HDPE pipe as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Crushed Aggregate and Channel Lining”, “Grout Products”, and “Pipe” AML Standard Technical Specifications.
Special Considerations: None Inspector Notes: Collect manufacturer certificates for each unit.
Major Incidentals: Excavation, bedding, aggregate backfill to 1’ over top of pipe, steel plates for access maintenance.
Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “36” DIA. HDPE PIPE-STANDARD” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and incidentals.
COR & BID & BMP 10
15 CONCRETE
HEADWALL- PIPES
≤36” DIA.
This item consists of furnishing all materials, equipment, and labor, necessary to construct the headwalls as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Concrete Headwalls” AML Standard Technical Specification. Units cast in the field require fiber, pre-cast units require manufacturer certification that concrete meets or exceeds required strength.
Special Considerations: None Inspector Notes: For pre-cast units collect manufacturer certificate (includes strength of concrete used).
Major Incidentals: Concrete, steel reinforcement, fiber, grout, formwork, dissipaters, backfill Measurement: Actual Quantities shall be measured as “EACH” unit installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities installed and the Unit Price for “CONCRETE HEADWALL- PIPES ≤36”
DIA.” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and incidentals.
16 SEEDBED
PREPARATION
This item shall consist of furnishing all materials, equipment, and labor for the purpose of revegetation of the disturbed areas as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Revegetation” AML Standard Technical Specification.
Special Considerations: None Measurement: Actual Quantities shall be measured to the next whole full acre approved by and accepted by the ENGINEER.
Payment: Payment for revegetation shall the product of the Actual Accepted Quantities and the respective Unit Price bid for "SEEDBED
PREPARATION” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all materials, labor, equipment, and incidentals.
COR & BID & BMP 11
17 AGRICULTURAL
LIMESTONE
These items shall consist of furnishing all materials, equipment, and labor for the purpose of revegetation of the disturbed areas as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Revegetation” AML Standard Technical Specification. DAML will use the current Limestone Sample Results published by the KY Department of Agriculture to determine a Relative Neutralizing Value (RNV) for weight adjustment.
Special Considerations: None Inspector Notes: Collect supplier tickets.
Major Incidentals: Application and incorporation Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) of appropriately sized 85% calcium carbonate (min.) aggregate installed and accepted by the ENGINEER. Material not meeting the minimum sizing and/or calcium carbonate content will be adjusted by multiplying the weight ticket tons supplied by the ratio of the RNV to the minimum RNV rounded to the nearest ton. Material meeting or exceeding all the minimum values is not adjusted.
Payment: Payment for revegetation shall the product of the Actual Accepted Quantities and the respective Unit Price bid for "AGRICULTURAL
LIMESTONE” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all materials, labor, equipment, and incidentals.
18 FERTILIZER
and as directed by the ENGINEER in accordance with the “Revegetation” AML Standard Technical Specification.
Special Considerations: None Measurement: Actual Quantities shall be measured to the next whole half ton approved by and accepted by the ENGINEER.
Payment: Payment for revegetation shall the product of the Actual Accepted Quantities and the respective Unit Price bid for "FERTILIZER” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all materials, labor, equipment, and incidentals.
COR & BID & BMP 12
19 SEED
and as directed by the ENGINEER in accordance with the “Revegetation” AML Standard Technical Specification. Seed mixture will be listed on the Drawings, Project Description, and/or Special Conditions.
Special Considerations: None Inspector Notes: Collect manufacturer certificates for each unit.
Major Incidentals:
Measurement: Actual Quantities shall be measured to the next whole pound of pure live seed approved by and accepted by the ENGINEER.
Payment: Payment for revegetation shall the product of the Actual Accepted Quantities and the respective Unit Price bid for "SEED” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all materials, labor, equipment, and
20 MULCH- STRAW &
HAY
and as directed by the ENGINEER in accordance with the “Revegetation” AML Standard Technical Specification.
Special Considerations: None Measurement: Actual Quantities shall be measured to the next half acre approved by and accepted by the ENGINEER.
Payment: Payment for revegetation shall the product of the Actual Accepted Quantities and the respective Unit Price bid for "MULCH- STRAW & HAY” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all materials, labor, equipment, and incidentals.
21 COVER CROP
and as directed by the ENGINEER in accordance with the “Revegetation” AML Standard Technical Specification. Cover crop will be winter wheat in the fall and winter and German Foxtail Millet in the spring and summer months.
Special Considerations: None Measurement: Actual Quantities shall be measured to the next whole bushel approved by and accepted by the ENGINEER.
Payment: Payment for revegetation shall the product of the Actual Accepted Quantities and the respective Unit Price bid for “COVER CROP” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all materials, labor, equipment, and incidentals.
COR & BID & BMP 13
22 DENSE GRADE
AGGREGATE
This item shall consist of furnishing all materials, equipment, and labor necessary to place, and compact dense grade aggregate (DGA) as depicted on the Drawings and as directed by the ENGINEER in accordance with “Crushed Aggregate and Channel Lining” AML Standard Technical Specification.
Special Considerations: This item is for temporary paved roadway repairs and base preparation prior to bituminous repair. DGA for pipe backfill is incidental to the pipe.
Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) of aggregate installed and accepted by the
ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and Unit Price bid for "DENSE GRADE AGGREGATE FOR ROADWAYS” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and incidentals.
23 ROADWAY STONE This item shall consist furnishing all materials, equipment, and labor necessary to place and compact as necessary the various gradations of stone as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Crushed Aggregate and Channel Lining” AML Standard Technical Specification.
Special Considerations: None Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) of each type of channel lining, and/or aggregate installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “ROADWAY STONE” in accordance with the “General
COR & BID & BMP 14
Erosion and Sediment Control Best Management Practices (BMP) Plan
January 2017
COR & BID & BMP 15
OVERVIEW
This Best Management Practices (BMP) plan is a guide for Kentucky Division of Abandoned Mine Lands (DAML) projects. It contains information regarding preventing, reducing and controlling erosion, sediment, and pollutant runoff from Abandoned Mine Land (AML) Reclamation and Acid Mine Drainage (AMD) Abatement project construction sites. The information in this BMP will aid DAML staff and contractors in selecting, installing, and maintaining erosion prevention and sediment control measures during the different stages of construction. This BMP plan, in accordance with DAML Technical Specifications and Standard Drawings, is intended to protect Kentucky’s streams from potential water quality impacts resulting from DAML projects.
This general BMP document is to outline the various pollution prevention measures used on AML Reclamation or AMD Abatement Projects. The primary sources of pollutants are solids mobilized during storm events and precipitants from mineralized mine drainage. Other sources of pollutants include oil/fuel/grease from servicing and operating construction equipment, concrete washout water, sanitary wastes, and trash/debris.
EROSION PREVENTION AND SEDIMENT CONTROL MEASURES
Plans for Reclamation and AMD abatement construction projects will include erosion control measures on the planview sheets when possible, and will depict Disturbed Drainage Areas (DDAs) and related information. The construction notes and project description may describe other control measures. The Contractor and Engineer may select an additional BMP for the project as the project changes and construction progresses. Projects that do not have DDAs annotated in the plans will employ the same concepts selecting and implementing this general BMP plan.
Address disturbed areas or sources of sediments by the most effective means in the specific work area. Direct non-storm water discharges to sediment basins/traps or to a filter fence enclosure in a flat vegetated infiltration area or filtered via another approved commercial product. All deep mine and surface impoundment water will be tested and treated, when as necessary, to meet the DAML Water-Treatment and Disposal Technical Specification unless stricter limitations are listed in an existing Total Daily Maximum Load (TMDL) limit.
PERMITS
The DAML shall review each project during project development to determine whether any permits are required to implement the project work. When a permit is required, DAML will make every effort to obtain the permit prior to letting the project for bidding. Permit specific conditions shall trump any standard conditions and/or practices. All permits must be maintained onsite and produced when requested by regulatory authorizes inducing representative of the permitting authority.
Common permits types for DAML projects:
COR & BID & BMP 16
• 401 Water Quality Certification (WQC) o Issued by the KY Division of Water
• 402 KY Pollution Discharge Elimination System (KPDES) o DAML activities are covered under the AML KPDES General Permit
• 404 US Army Corps of Engineers (USACE) o Issued by the US Army Corps of Engineers- Nashville District, Louisville District, or Huntington District (Depending upon major drainage basin)
• KY Stream Construction (Floodplain) o Issued by the KY Division of Water
• Local Floodplain Permit o Issued by the County/Municipality
• Local Storm Water Construction o Issued by the County/Municipality
A) Field Review Walk-Thru:
The DAML will conduct a project review between the Project Engineer, Construction Branch Personnel, Project Design Technician, and Field Office Staff, to review the construction plans and identify any changes needed prior to letting the project for bidding. The group will evaluate the locations and types of site specific BMP and any other erosion prevention and sediment control measures chosen for incorporation into the final design plans.
B) Site Visit Meeting
DAML will present the project specific BMP and permit requirements/conditions to the potential contractors during the site visit meeting.
C) Pre-Construction Conference
Prior to the actual beginning of the project, DAML will hold a pre-construction conference between representatives of the DAML, the Contractor, including any Subcontractors, as well as other interested agencies and parties. Items discussed will include the time and sequence for construction, planned methods of operation, payment, and other relevant questions including any permit requirements and the erosion and sediment control plan.
D) Construction Access
This is the first land-disturbing activity. Construction entrances shall be a minimum of twenty
(20) feet wide by fifty (50) feet long, measured from the shoulder of the public road, and consist of No. 2 aggregate over a heavy weight non-woven filter fabric base. As soon as construction begins, stabilize bare areas with gravel and temporary mulch and/or vegetation.
E) Clearing and Grubbing
Use the following techniques for clearing and grubbing activities:
COR & BID & BMP 17
1) Leave areas undisturbed when possible.
2) Construct silt basins to provide silt volume for large areas.
3) Construct Silt Trap(s) Type A for small areas.
4) Construct Type B silt traps for areas with rapid runoff and sediment-laden runoff.
5) All silt traps should have a 3:1 flow length to width ratio. Add spreader bars, baffles, or turbidity curtains to maintain the flow path ratio when site conditions require traps sizes smaller than the standard detail dimensions.
6) Install geotextile bags and/or rock checks in front of existing drop inlets.
7) Construct diversion ditches to catch sheet runoff and carry it to basins or traps or to divert it around areas to be disturbed.
8) Maintain brush and/or other barriers to slow and/or divert runoff.
9) Construct silt fences/hay bales to catch sheet runoff on short slopes. For longer slopes, multiple rows of silt fence/hay bales may be considered.
10) Apply temporarily mulch to area not actively being disturbed or for any area left undisturbed for fourteen (14) days.
11) Employ non-standard or innovative methods.
F) Stream Crossings / Work Along Streams
1) Temporary low-water stream crossings follow the guidelines included in the DAML Technical Specifications and those established by the KY Division of Water Floodplain Management Section. Removal of a temporary crossing may be required to accommodate large storm events.
2) Do not completely block stream flow (even temporary). Instead, utilize some form of pass thru mechanism during all AML projects.
3) Work within a stream channel shall not cause flooding of properties upstream, downstream or within the project area or cause downstream water quality degradation. Minimize equipment contact time with the stream water by diverting water around equipment working in or along streams.
4) No flowing water will interact with any uncured concrete placed in the stream channel.
5) Divert all stream water around the work areas in accordance to methods listed in the DAML
Stream Protection & Relocation technical specification, AML Standard Details Section 60, and as by the appropriate permit guidelines.
6) Temporary out of channel stream diversion must use one of the three approved methods:
pipe diversion, sandbag/stone channel diversion, and/or fabric-based channel diversion.
Do not construct any temporarily diverted channel on bare, erodible soil. No temporary diversion shall be permanent without a 401, 404, and other appropriate permits.
COR & BID & BMP 18
G) Deep Mine and Surface Water Impoundments
The DAML Resident Inspector will test the mine water from deep mines and surface impoundments on the project area to determine the pH and total iron content. Treat the water until it meets the DAML Water-Treatment and Disposal Technical Specification or an existing TMDL, whichever is stricter, before release through a silt control structure(s).
Monitoring & Recording
The DAML Inspector will maintain a log of the pH and total iron content results prior to releasing and during each release day. Perform a minimum of two (2) tests downstream each day to ensure the maintenance of water quality during release and is not degrading the receiving stream.
Types of structures/facilities include:
1) Silt Traps Type A (20’L x 5’W x 2’D min dugout)
2) Silt Traps Type B (20’L x 5’W x 2’D min dugout with rock berm)
3) Silt Check - Rock checks with filter fabric core lining installed in channels and in front of pipes
4) Temporary silt control fence with Class II filter berm
5) Sediment collection bags
H) Cut and Fill and Placement of Drainage Structures
Areas at final grade will be seeded and mulched within five (5) days. Soil stock piles and areas that are not at final grade but where construction will cease for a period of fourteen (14) days or longer, shall receive temporary mulch no later than fourteen (14) days from the last construction activity in that area.
Types of structures/facilities include:
1) Silt Traps Type B (20’L x 5’W x 2’D min dugout with rock berm)
2) Silt Checks - Bags in front of pipes after they are placed
3) Channel lining
4) Erosion control blanket
5) Temporary mulch and/or seeding for areas where construction activities will be ceased for
14 days or more
6) Non-standard or innovative methods
I) Temporary Shutdown
Items to be completed prior to shutdown include:
1) Clean out behind, repair or replace silt fence and/or hay bales
2) Clean out all silt traps
COR & BID & BMP 19
3) Apply temporary mulch and track into the soil
4) Sow cover crop (weather permitting)
J) Finish Work
1) Establish permanent seeding and protection
2) Remove non-permanent silt checks from ditches and drains if protected with other BMPs sufficient to control erosion and vegetation is established.
3) Remove non-permanent silt traps and basins.
4) Remove geotextile silt fence.
5) Planting trees and/or shrubs where they are included in the project.
6) Clean out behind, repair, and/or replace bale silt barriers
7) Clean out all permanent silt traps and basins
K) Post-Construction
The Contractor shall assume responsibility for all workmanship and materials for a period of one year from the date of final payment, as directed by the Contract Documents. Any work found to be defective due to failure to comply with the provisions and intent of the Contract Documents shall be corrected at the Contractor's expense. Problems determined not to be created by the landowner or due to the Contractor will be addressed by the DAML for a period of up to three years, pending available funding.
OTHER CONTROL MEASURES
L) Solid Materials
No solid materials, including rock and building materials, shall be discharged into waters of the U.S. except as authorized by the Clean Water Act (CWA) Section 401 and Section 404 permits.
M) Waste Materials
Collect and store waste materials that may leach pollutants (paint and paint containers, caulk tubes, oil/grease containers, liquids of any kind, soluble materials, etc.) in appropriate covered waste containers. Remove waste containers from the project site frequently as to not allow wastes to become a source of pollution. Instruct all personnel regarding the correct procedure for waste disposal and dispose of wastes in accordance with appropriate regulations.
N) Hazardous Waste
Manage and dispose of hazardous waste materials in the manner specified by local or state regulation. Notify the Resident Inspector if there are any hazardous wastes generated, and provide a plan for the management and disposal of such materials. Instruct site personnel with regard to proper storage and handling of hazardous wastes when required and use the practices to reduce the risks associated with all hazardous materials. Keep products in original containers
COR & BID & BMP 20
unless they are not re-sealable with the original labels and material safety data sheets (MSDS) will be reviewed and retained.
O) Spill Prevention
Use good housekeeping and material management practices to reduce the risk of spills or other exposure of materials and substances to the weather and/or runoff. Manufacturers' recommended methods for spill cleanup will be maintained on site and readily available upon request. Make personnel aware of procedures and the location of the information and cleanup supplies.
Equipment and materials will include as appropriate, brooms, dust pans, mops, rags, gloves, oil absorbents, sand, sawdust, and plastic and metal trash containers.
Clean up all spills immediately after discovery. Keep the spill area well ventilated. Personnel will wear appropriate protective clothing to prevent injury from contract with a hazardous substance. Report spills of toxic or hazardous material to the appropriate state/local agency as required by KRS 224 and applicable federal law. Wastes from spill cleanup will be disposed of in accordance with appropriate regulations. The spill prevention plan will be adjusted, as needed, to prevent spills from reoccurring and improve spill response and cleanup.
P) Petroleum Products
Monitor vehicles and equipment fueled and maintained on site for leaks, and receive regular preventative maintenance to reduce the chance of leakage. Protect petroleum products onsite will be stored in tightly sealed, clearly labeled containers from exposure to weather. The CONTRACTOR shall not have a total of over 1,300 gallons of petroleum products on site at any given time.
Q) Fertilizers
Store fertilizers in a covered area away from water. Transfer the contents of any partially used bag of fertilizer to a sealable plastic bin to avoid spills. Once applied, work into the soil and apply mulch to limit exposure to storm water.
R) Concrete Truck Washout
Concrete truck mixers and chutes will not be washed on pavement, near storm drain inlets, or within seventy (75) feet of any ditch, stream, wetland, lake, or sinkhole. Where possible, discharge excess concrete and wash water to areas prepared for pouring new concrete, flat areas to be paved that are away from ditches or drainage system features, or other locations that will not drain off site. Where this approach is not possible, excavate a shallow earthen washbasin away from ditches to receive the wash water.
INSPECTIONS
Use inspection and maintenance practices to maintain erosion and sediment controls:
COR & BID & BMP 21
1) The Contractor and DAML Resident Inspector will inspect all erosion prevention and sediment control measures at least once each week and following any rain of 0.1 inch or more.
2) The DAML Resident Inspector will record the silt control inspections by in their daily report.
3) Silt fences/hay bales will be inspected for bypassing, overtopping, undercutting, depth of sediment, tears, and to ensure attachment to secure posts.
4) Inspect silt traps and basins for depth of sediment, and built-up sediment and clean out when it reaches 50% of the design capacity and at the end of the job.
5) Inspect diversion dikes and berms and promptly repaired any breaches. Repair areas that are eroding or scouring and re-seeded / mulched as needed.
6) Inspect temporary and permanent seeding and mulching for bare spots, washouts, and healthy growth. Repair bare or eroded areas as needed.
7) Inspect all material storage and equipment servicing areas that involve the management of bulk liquids fuels and bulk solids weekly for conditions that represent a release or possible release of pollutants to the environment.
MAINTENANCE
Maintain all measures in good working order; initiate corrective actions within twenty-four (24) hours of being reported and completed with five (5) days, address critical failures immediately unless site conditions are too dangerous. Remove Built-up sediment from behind the silt fence/hay bales before it has reached halfway up the height of the fence.
ENFORCEMENT
At all times, representatives from DAML and enforcement agencies will have access to the project site. The ENGINEER reserves right to stop work until erosion prevention and sediment control problems are addressed to his/her satisfaction.
AutoCAD SHX Text 0 + 00
AutoCAD SHX Text 0 + 20
AutoCAD SHX Text 0 + 40
AutoCAD SHX Text 0 + 60
AutoCAD SHX Text 0 + 80
AutoCAD SHX Text 1 + 00
AutoCAD SHX Text 1 + 20
AutoCAD SHX Text 1 + 40
AutoCAD SHX Text 1 + 60
AutoCAD SHX Text 1 + 80
AutoCAD SHX Text 2 + 00
AutoCAD SHX Text 2 + 20
AutoCAD SHX Text 2 + 40
AutoCAD SHX Text
COMMONWEALTH OF KENTUCKY
AutoCAD SHX Text Index of Sheets
AutoCAD SHX Text F:\Projects\AML\24014AMLBAML (Nelson Thompson Drainage Phase II)\1 Design Phase\1 Drawings\24014AMLBAML Plan Set A1.dwg
AutoCAD SHX Text
OVERVIEW 2 2 PLANVIEW - AREA "A" 3 3 PLANVIEW - AREA "B" 4 4 SECTIONS/DETAILS 55
AutoCAD SHX Text
24014AMLBAML RECLAMATION PROJECT (ADD. #1)
AutoCAD SHX Text
LAWRENCE COUNTY, KENTUCKY
AutoCAD SHX Text
24014AMLBAML RECLAMATION PROJECT (ADD. #1) LAWRENCE COUNTY