This is an Invitation to Bid (ITB) document from the Commonwealth of Kentucky's Department for Facilities and Support Services, Division of Engineering and Contract Administration, for the 24033 AMLBAML Reclamation Project located in Pike County, Kentucky. The project involves an abandoned mine lands (AML) reclamation effort focused on addressing subsurface drainage issues at a residential property. The bid is identified as RFB-98-26, with an addendum issued on October 10, 2025. The project scope includes installing subdrain between the toe of a slope and a residence to collect subsurface drainage, routing collected drainage to an existing roadside ditch, and replacing a culvert crossing the citizen's driveway. The total project area is 1.44 acres, with 0.13 acres designated for waste area, and the contract requires completion within 60 calendar days from the contract award date.

The bid schedule includes multiple line items with specific quantities and unit prices, such as mobilization, utility relocation, landscape allowance, traffic control, and various drainage and erosion control components. The project will be funded through the Kentucky Division of Abandoned Mine Lands (DAML) and is subject to Davis-Bacon wage scale requirements. Bidders must submit a Contractor/Subcontractor Information Form and comply with specific erosion and sediment control best management practices (BMPs). The project involves careful environmental considerations, including minimal tree disturbance, potential bat conservation fund payments, and strict sediment control measures to protect local waterways. Permits may be required from various state and federal agencies, including the Kentucky Division of Water and the US Army Corps of Engineers.

View the file

Other files

File Type Posted
Final_RFB_785_2600000160_2_SO_FORM.PDF PDF
Final_RFB_785_2600000160_1_SO_FORM.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-98-26

FOR: 24033 AMLBAML

AML Project Pike County, Kentucky

DATE: October 10, 2025

RFB-785-2600000160

ADDENDUM NO. One (1)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to attached addendum for all additions, deletions, and/or changes to specifications and/or drawings.

Item 2: Bidders must use Revised Bid Schedule in lieu of previously issued

END OF ADDENDUM

Invitation to Bid No. RFB-98-26 For: 24033 AMLBAML AML Project Pike County, Kentucky

Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration

NO. ITEM M.O.P. UNIT QUANTITY * Low APL UNIT PRICE TOTAL

1 MOBILIZATION L.S. L.S. 1.0 X NA ≤ NA = 5,000.00$

2 UTILITY RELOCATION/REPLACEMENT A.C.U. A.C.U. 10,000.0 X NA ≤ 1.00$ = 10,000.00$

3 LANDSCAPE ALLOWANCE A.C.U. A.C.U. 2,500.0 X NA ≤ 1.00$ = 2,500.00$

4 TRAFFIC CONTROL L.S. L.S. 1.0 X $500.00 ≤ $ = $

5 STRUCTURE REMOVAL/REPLACEMENT L.S. L.S. 1.0 X NA ≤ $ = $

6 SITE PREPARATION U.P. ACRE 1.0 X $750.00 ≤ $ = $

7 FILTER FABRIC U.P. SY 100.0 X $1.00 ≤ $ = $

8 GEO-GRID U.P. SY 100.0 X $2.00 ≤ $ = $

9 SILT BARRIER - BALES & FENCE U.P. LF 500.0 X $1.00 ≤ $ = $

10 SUBDRAIN U.P. LF 320.0 X $14.00 ≤ $ = $

11 SUBDRAIN CONCRETE COLLARS U.P. EACH 1.0 X $50.00 ≤ $ = $

12 8" DIA. HDPE PIPE- STANDARD U.P. LF 160.0 X $0.00 ≤ $ = $

13 15" DIA. HDPE PIPE- STANDARD U.P. LF 120.0 X $12.00 ≤ $ = $

14 COVER CROP U.P. BUSHEL 5.0 X $15.00 ≤ $ = $

15 RESIDENTIAL SEEDING U.P. ACRE 1.0 X $750.00 ≤ $ = $

16 ROADWAY STONE U.P. TON 100.0 X $15.00 ≤ $ = $

BID TOTAL = $

* Any Unit Price outside the Allowable Price Limit (APL) range may be considered an unbalanced bid and may have to be justified in writing if such bid is deemed the low responsive bid.

24033AMLBAML RECLAMATION PROJECT (Revised - Addendum #1)

PIKE COUNTY, KENTUCKY

BID SCHEDULE

NOTE: THE AUTHENTICATION OF BID AND STATEMENT OF NON-COLLUSION AND NON-CONFLICT OF INTEREST PAGE MUST BE PROPERLY EXECUTED FOR THE TOTAL BID

AMOUNT TO BE VALID.

REVISED BID SCHEDULE 10/10/2025

RFB-98-26

Revised 12/11/2024

COR & BID & BMP 1

24033AMLBAML RECLAMATION PROJECT

(REVISED – ADDENDUM #1)

PIKE COUNTY, KENTUCKY

Written Location Directions: The site is located at a residence near Ransom in Pike County. GPS at site is 37.5372°N, 82.2234°W. Physical address is 1199 Upper Blackberry, Ransom KY. Driving Directions:

From the intersection of US-23 and US-119 near Pikeville – Travel US-119 North 18.6 miles and turn right onto KY-199/Pond Creek Road. Travel 3.3 miles and turn left onto KY-1056. Travel 3.9 miles and turn right onto Upper Blackberry Road. Travel 1.2 miles to the project site on left. All waste generated by this project will be properly placed within the site project limits.

Basic Project Description: The yard around the residence at this site is being saturated by subsurface drainage from the eligible mined seam above. This project will install subdrain between the toe of the slope and the residence to collect the subsurface drainage saturating the yard. Collected drainage will be routed via installed culverts to the existing drainage at the roadside ditch along Upper Blackberry Road.

A culvert will also be replaced crossing the citizen’s driveway for drainage and construction access.

Project limits include 1.44 acres, which includes 0.13 acres being used for the waste area. There will be a total expected disturbance of 1 acre. No trees will be disturbed by this project, all work will occur on maintained residential property. If required, AML will elect to make a payment to the Imperiled Bat Conservation Fund in accordance with a determination from USFWS.

No identified streams or water bodies will be impacted by this project. A portion of the 100 year floodplain for Upper Blackberry Creek lies within the project limits, and no waste fill will be placed within this area.

No caves or cave-like structures will be impacted by this project.

The project site has previously been disturbed by coal mining operations, road construction, utility installation, residential development, landowner activities, and/or high velocity water flows associated with heavy rain events and flooding. These disturbances consist of significant upheaval, mixing, and removal of earthen material from deep excavation, grading, sub-surface drilling, fill material placement, and erosion. There should be no undisturbed earthen material to a depth of several feet at the areas slated for significant project-related construction activities.

The strict implementation and enforcement of standard AML sediment and erosion control Best Management Practices (BMPs) will prevent significant amounts of sediments disturbed by project related activities from entering area streams to create indirect impacts to aquatic resources. Sediment control will be installed prior to beginning any major earth disturbance (excluding initial site preparation for access only) until all measures are installed. These include but are not limited to silt barriers (bales & silt fence).

All disturbed areas will be promptly revegetated at the end of construction using lime, fertilizer, residential or wildlife seed, and mulch, as necessary. Revegetation bid items (traditional revegetation, hydroseeding and residential seeding) including cover crop are allotted for prompt establishment of vegetation. No woody material is expected to be encountered, but will be burned at the project site or otherwise properly disposed of as necessary.

Access to the site is via state and county roads, residentially maintained driveways and yards. This project will include pre- and/or post- project maintenance and repair of existing previously constructed public county roads utilized during the construction of this project, which are administered by the county

COR & BID & BMP 2

or local road authority. This construction activity will be conducted under the authority and supervision of the local public road authority and will consist of standard road construction practices appropriate to mitigate impacts to the local community from potential degraded road conditions in order to maintain public traffic safety.

A. STANDARD DOCUMENTS

The AML Standard Details, Technical Specifications, and Bid Item Descriptions are posted on the Division’s website at https://eec.ky.gov/Natural-Resources/Mining/Abandoned-Mine- Lands/Pages/default.aspx

Once on the web page, please click “Contractor Information” tab located on the right side. AML standard technical specification and detail are located under this tab. Contractors are strongly encouraged to review the complete AML website for additional information.

B. ALLOWABLE PRICE LIMIT

The lowest Allowable Price Limit (APL) is listed on the Bid Schedule as part of the bid documents. Unit Price, Plan Quantity, and Lump Sum are all methods of payment. Significantly low or high values entered by the CONTRACTOR on the Bid Schedule may be considered an unbalanced bid and may have to be justified in writing if such bid is deemed the low responsive bid.

An example would be if a CONTRACTOR assumes there may not be a need for the entire design quantity for Roadway Stone and entered a $10 value for Roadway Stone when the cost at the quarry is significantly higher. Another example would be if the CONTRACTOR enters a value of $30 per linear foot for “SILT BARRIER - BALES & FENCE” to front load payments for work items used near the beginning of the project. The CONTRACTOR is also cautioned that other considerations for rejection may be enforced such as the low bid being higher than the budgeted dollar amount for this project.

C. CONTRACT LENGTH

All work shall be completed within SIXTY (60) calendar days from the effective date of the Award of Contract. Within the bounds of prudent project performance, it shall be the responsibility of the CONTRACTOR to plan and implement construction sequences which follow the intent of these CONTRACT DOCUMENTS, particularly as, reflected in the Drawings and Special Conditions and to protect any portion of the contract which may be completed before others.

D. CONTRACTOR’S INFORMATION SHEET

The AML CONTRACTOR/SUBCONTRACTOR INFORMATION FORM sheet must be filled out and submitted with the bid. Failure to submit the AML Contractor/Subcontractor Information Form sheet with the bid will be the basis for declaring the bid “Non-Responsive.”

E. SPECIAL CONDITIONS & PROJECT NOTES

COR & BID & BMP 3

- When applicable, AML is responsible for payment to the Imperiled Bat Conservation Fund

(IBCF). The CONTRACTOR will be responsible for adhering to the boundary for which payment was made and confirming with AML the acreage of trees removed.

- On occasion, a property owner may require a CONTRACTOR to add them on their General

Liability and/or Automobile Insurance as an “Additional Insured.” AML will inform the

CONTRACTOR when this requirement is being made by the property owner. In these cases, the

CONTRACTOR must submit to AML copies of their certificate of insurance documenting the

“Additional Insured” before they will be allowed to mobilize equipment and forces on to said properties. Any fees, rate increases, or other costs incurred by the CONTRACTOR for this requirement, if any, will be considered incidental to mobilization and as such no compensation will be made by AML. The “Additional Insured” must remain on the CONTRACTOR’s policy(s) for the full length of the contract.

F. DAVIS BACON SCALE WAGES

The CONTRACTOR and all SUBCONTRACTORS are required to pay scale wages as defined in the contract documents. If all employment categories that may be used have not been listed and specified in the contract document, then the contractor must make his best determination of what the missing wage rate will be. Subsequently after the bid is awarded, the contractor must request the specific rate from the

Department of Labor. AML will not issue change orders for additional compensation if the wage rate determined by DOL is higher than the rate the contractor used to develop his bid. If wage rates are not included for a specific category, AML suggests that the contractor assume the highest operator or laborer wages that are listed when developing his bid.

G. PERMITS & FEES – AML will be responsible for obtaining any permits that are checked below.

(Check all that apply)

☐KYTC Encroachment Permit

☐KY DOW Water Permits

☐USACE Permit

The CONTRACTOR is responsible for all other permits and/or fees necessary to begin the project. The

CONTRACTOR is advised that on occasion, other permits and/or fees may be required by federal, state, and local government(s). Other types of permits and/or fees are not the responsibility of AML and as such, these will be the complete and total responsibility of the CONTRACTOR to obtain. These must be obtained before AML will allow mobilization of equipment and forces on to said properties. All costs associated with other permits or fees will be the responsibility of the CONTRACTOR. Please refer to

“General Provisions” in the AML Technical Specifications.

COR & BID & BMP 4

BID ITEM DESCRIPTION

24033AMLBAML AML RECLAMATION PROJECT (REVISED ADDENDUM #1)

PIKE COUNTY, KENTUCKY

NO ITEM DESCRIPTION

1 MOBILIZATION This item consists of the mobilization and demobilization of the CONTRACTOR’S forces and equipment in accordance with the “Mobilization/Demobilization” AML Standard Technical Specification. The amount of this bid item is not to exceed 5 percent of the sum of the lump sum bid price.

Measurement: Not Applicable.

Payment: Payment shall be made at increments set in the AML Technical Specifications totaling the Lump Sum price.

2 UTILITY

RELOCATION /

REPLACEMENT

This consists of furnishing all materials, equipment, and labor necessary to replace utilities damaged by construction or relocate any utilities that are in the construction area in accordance with the “Utility Relocation” AML Standard Technical Specification. The CONTRACTOR is required to supply the ENGINEER with all documentation to support cost incurred to qualify for reimbursement.

Special Considerations: None Major Incidentals: These will be listed in writing by the ENGINEER prior to beginning the work.

Measurement: Not Applicable.

Payment: Payment shall be made for Actual Documented Costs for “UTILITY RELOCATION/REPLACEMENT” approved by the ENGINEER. The payment shall be a direct reimbursement for actual documented costs to the CONTRACTOR in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and incidentals.

COR & BID & BMP 5

3 LANDSCAPE

ALLOWANCE

This item of work shall consist of furnishing all materials, equipment, and labor necessary to replace damaged landscape structures, plants and trees as depicted on Drawings and as directed by ENGINEER in accordance with the “Revegetation” AML Standard Technical Specification. The CONTRACTOR is required to supply the ENGINEER with all documentation to support cost incurred to qualify for reimbursement.

Special Considerations: None Inspector Notes: Conduct a picture inventory of landscape items that may be affected before construction starts and keep an item list of those landscape items that are affected.

Major Incidentals: These will be listed in writing by the ENGINEER prior to beginning the work.

Measurement: Not Applicable Payment: Payment for Actual Documented Costs “LANDSCAPE ALLOWANCE” approved IN ADVANCE by the ENGINEER. The payment shall be a direct reimbursement for the removal/replacement of landscape features as approved/directed by the ENGINEER in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and incidentals.

4 TRAFFIC CONTROL This item consists of maintaining and controlling traffic on existing roads (public and private) affected by this project as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Traffic Control” AML Standard Technical Specification. Appropriate signs shall be erected at the project limits and flag persons shall be used as needed.

Special Considerations: None Major Incidentals: Signs, flaggers, steel plates, immediately clearing debris from roadway.

Measurement: Not Applicable.

Payment: Payment shall be made at the Lump Sum price bid for “TRAFFIC CONTROL” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for materials, equipment, labor, and incidentals.

COR & BID & BMP 6

5 STRUCTURE

REMOVAL/

REPLACEMENT

This item represents the ENGINEER'S best estimate of removal/replacement cost of designated qualifying structural features “in kind” to facilitate normal construction activities as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Structure Removal / Replacement” AML Standard Technical Specification. The CONTRACTOR is required to supply the ENGINEER with all documentation to support cost incurred to qualify for reimbursement.

Special Considerations: This bid item is intended for removal and replacement of existing structures encountered during subdrain and pipe installation, specifically (but not limited to) outbuilding and electrical service behind the residence.

Inspector Notes: Inventory of structures, pictures, and dimensions, before construction starts. Any structures that are removed shall be accompanied by pictures.

Major Incidentals: These will be listed in writing by the ENGINEER prior to beginning the work.

Measurement: None Payment: Payment shall be made at the Lump Sum price bid for “STRUCTURE REMOVAL/REPLACEMENT” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for materials, equipment, labor, and

6 SITE PREPARATION This item of work shall consist of furnishing all materials, equipment, and labor as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Site Preparation” AML Standard Technical Specification.

Special Considerations: None Major Incidentals: Clearing, grubbing, windrowing, burning, pipe removal and disposal, pipe cleanout, temporary diversion ditch construction, domestic debris removal and disposal, concrete & bituminous asphalt debris removal and disposal, access improvement/construction, in-kind fence repair/replacement, and temporary stream diversion.

Measurement: Actual Quantities shall be measured with a handheld GPS and rounded up to the next whole 0.5 acre actually cleared and grubbed (excludes slurry and refuse areas.

Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “SITE PREPARATION” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and other items necessary to complete the work.

COR & BID & BMP 7

7 FILTER FABRIC This item consist of furnishing all materials, equipment, and labor, necessary to install filter fabric utilized in ditch construction as depicted on the Drawings and as directed by the ENGINEER in accordance with “Filter Fabric” AML Standard Technical Specification. This includes all types of filter fabric used on a jobsite. The standard details list the type and quantity of fabric for each purpose.

Special Considerations: None Inspector Notes: Collect manufacturer certificates for each unit.

Major Incidentals: Staples Measurement: Actual Quantities shall be measured as the next whole square yard installed and accepted by the ENGINEER.

Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “FILTER FABRIC” in accordance with the “General

8 GEOGRID This item consist of furnishing all materials, equipment, and labor, necessary to install geogrid, including all labor, materials, and accessories as depicted on the Drawings and as directed by the ENGINEER in accordance with “Geo-grid” AML Standard Technical Specification. All geo-grid is bi-axial, except for tails behind Non-reinforced Block Walls- Type I.

Special Considerations: None Inspector Notes: Collect manufacturer certificates for each unit.

Major Incidentals: Staples Measurement: Actual Quantities shall be measured as the next whole square yard installed and accepted by the ENGINEER.

Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “GEOGRID” in accordance with the “General

COR & BID & BMP 8

9 SILT BARRIER–

BALES & FENCE

This item consists of furnishing all materials, equipment, and labor necessary to maintain silt control as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Silt Control” AML Standard Technical Specification. Hay/straw bales shall be placed with an overlap equal to 0.4 bales per linear foot of silt control fencing. Silt fence shall be trenched and removed at the end of the project. Failure to remove silt control fence (geotextile fabrics) shall result in forfeiture of demobilization.

Special Considerations: None Major Incidentals: Maintenance, silt fence trenching and removal Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER.

Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “SILT BARRIER - BALES & FENCE" in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for materials, equipment, labor, and

10 SUBDRAIN This item of work shall consist of furnishing all materials, equipment, and labor necessary to install subsurface drains as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Crushed Aggregate and Channel Lining”, “Filter Fabric”, and “Subsurface Drains” AML Standard Technical Specifications.

Special Considerations: None Major Incidentals: Excavation to depth of 3’, pipe, filter fabric, aggregate backfill to depth of 3’.

Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER. Subdrains requiring more than the incidental quantity of rock will be paid from the No. 2 Stone bid item or Roadway Stone if a No. 2 Stone bid item is not listed. All excavation is incidental to the earthwork.

Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “SUBDRAIN” in accordance with the “General

COR & BID & BMP 9

11 SUBDRAIN

CONCRETE

COLLARS

This item of work shall consist of furnishing all labor, materials, and equipment necessary to construct subdrain concrete collars as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Concrete” and “Subsurface Drains” AML Standard Technical Specifications.

Special Considerations: None Major Incidentals: Concrete, forming, steel Measurement: Actual Quantities shall be measured as “EACH” unit installed and accepted by the ENGINEER.

Payment: Payment shall be the product of the Actual Accepted Quantities installed and the Unit Price for “SUBDRAIN CONCRETE COLLARS” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and incidentals.

8” DIA. HDPE PIPE-

STANDARD

This item consists of furnishing all materials, equipment, and labor, necessary to install standard, non-steel reinforced HDPE pipe as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Crushed Aggregate and Channel Lining”, “Grout Products”, and “Pipe” AML Standard Technical Specifications.

Special Considerations: None Inspector Notes: Collect manufacturer certificates for each unit.

Major Incidentals: Excavation, bedding, aggregate backfill to 1’ over top of pipe, steel plates for access maintenance.

Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER.

Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “8” DIA. HDPE PIPE-STANDARD” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and incidentals.

COR & BID & BMP 10

15” DIA. HDPE PIPE-

STANDARD

This item consists of furnishing all materials, equipment, and labor, necessary to install standard, non-steel reinforced HDPE pipe as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Crushed Aggregate and Channel Lining”, “Grout Products”, and “Pipe” AML Standard Technical Specifications.

Special Considerations: Excavation/Cleanout of existing ditches to ensure proper flow (upstream and downstream) is incidental to this bid item.

Inspector Notes: Collect manufacturer certificates for each unit.

Major Incidentals: Excavation, bedding, aggregate backfill to 1’ over top of pipe, steel plates for access maintenance, ditch cleanout at inlet and outlet as necessary to ensure proper flow.

Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER.

Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “15” DIA. HDPE PIPE-STANDARD” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and incidentals.

14 COVER CROP

These items shall consist of furnishing all materials, equipment, and labor for the purpose of revegetation of the disturbed areas as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Revegetation” AML Standard Technical Specification. Cover crop will be winter wheat in the fall and winter and German Foxtail Millet in the spring and summer months.

Special Considerations: None Measurement: Actual Quantities shall be measured to the next whole bushel approved by and accepted by the ENGINEER.

Payment: Payment for revegetation shall the product of the Actual Accepted Quantities and the respective Unit Price bid for “COVER CROP” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all materials, labor, equipment, and incidentals.

COR & BID & BMP 11

15 RESIDENTIAL

SEEDING

This item shall consist of furnishing all materials, equipment, and labor for the purpose of revegetation of the disturbed areas as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Revegetation” AML Standard Technical Specification.

Special Considerations: None Major Incidentals: Seedbed preparation, agriculture limestone, fertilizer, seed, and mulch Measurement: Actual Quantities shall be measurement as the next tenth of an acre seeded as approved by the ENGINEER.

Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “RESIDENTIAL SEEDING” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and

16 ROADWAY STONE This item shall consist furnishing all materials, equipment, and labor necessary to place and compact as necessary the various gradations of stone as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Crushed Aggregate and Channel Lining” AML Standard Technical Specification.

Special Considerations: None Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) of each type of channel lining, and/or aggregate installed and accepted by the ENGINEER.

Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “ROADWAY STONE” in accordance with the “General

COR & BID & BMP 12

Erosion and Sediment Control Best Management Practices (BMP) Plan

January 2017

COR & BID & BMP 13

OVERVIEW

This Best Management Practices (BMP) plan is a guide for Kentucky Division of Abandoned Mine Lands (DAML) projects. It contains information regarding preventing, reducing and controlling erosion, sediment, and pollutant runoff from Abandoned Mine Land (AML) Reclamation and Acid Mine Drainage (AMD) Abatement project construction sites. The information in this BMP will aid DAML staff and contractors in selecting, installing, and maintaining erosion prevention and sediment control measures during the different stages of construction. This BMP plan, in accordance with DAML Technical Specifications and Standard Drawings, is intended to protect Kentucky’s streams from potential water quality impacts resulting from DAML projects.

This general BMP document is to outline the various pollution prevention measures used on AML Reclamation or AMD Abatement Projects. The primary sources of pollutants are solids mobilized during storm events and precipitants from mineralized mine drainage. Other sources of pollutants include oil/fuel/grease from servicing and operating construction equipment, concrete washout water, sanitary wastes, and trash/debris.

EROSION PREVENTION AND SEDIMENT CONTROL MEASURES

Plans for Reclamation and AMD abatement construction projects will include erosion control measures on the planview sheets when possible, and will depict Disturbed Drainage Areas (DDAs) and related information. The construction notes and project description may describe other control measures. The Contractor and Engineer may select an additional BMP for the project as the project changes and construction progresses. Projects that do not have DDAs annotated in the plans will employ the same concepts selecting and implementing this general BMP plan.

Address disturbed areas or sources of sediments by the most effective means in the specific work area. Direct non-storm water discharges to sediment basins/traps or to a filter fence enclosure in a flat vegetated infiltration area or filtered via another approved commercial product. All deep mine and surface impoundment water will be tested and treated, when as necessary, to meet the DAML Water-Treatment and Disposal Technical Specification unless stricter limitations are listed in an existing Total Daily Maximum Load (TMDL) limit.

PERMITS

The DAML shall review each project during project development to determine whether any permits are required to implement the project work. When a permit is required, DAML will make every effort to obtain the permit prior to letting the project for bidding. Permit specific conditions shall trump any standard conditions and/or practices. All permits must be maintained onsite and produced when requested by regulatory authorizes inducing representative of the permitting authority.

Common permits types for DAML projects:

COR & BID & BMP 14

• 401 Water Quality Certification (WQC) o Issued by the KY Division of Water

• 402 KY Pollution Discharge Elimination System (KPDES) o DAML activities are covered under the AML KPDES General Permit

• 404 US Army Corps of Engineers (USACE) o Issued by the US Army Corps of Engineers- Nashville District, Louisville District, or Huntington District (Depending upon major drainage basin)

• KY Stream Construction (Floodplain) o Issued by the KY Division of Water

• Local Floodplain Permit o Issued by the County/Municipality

• Local Storm Water Construction o Issued by the County/Municipality

A) Field Review Walk-Thru:

The DAML will conduct a project review between the Project Engineer, Construction Branch Personnel, Project Design Technician, and Field Office Staff, to review the construction plans and identify any changes needed prior to letting the project for bidding. The group will evaluate the locations and types of site specific BMP and any other erosion prevention and sediment control measures chosen for incorporation into the final design plans.

B) Site Visit Meeting

DAML will present the project specific BMP and permit requirements/conditions to the potential contractors during the site visit meeting.

C) Pre-Construction Conference

Prior to the actual beginning of the project, DAML will hold a pre-construction conference between representatives of the DAML, the Contractor, including any Subcontractors, as well as other interested agencies and parties. Items discussed will include the time and sequence for construction, planned methods of operation, payment, and other relevant questions including any permit requirements and the erosion and sediment control plan.

D) Construction Access

This is the first land-disturbing activity. Construction entrances shall be a minimum of twenty

(20) feet wide by fifty (50) feet long, measured from the shoulder of the public road, and consist of No. 2 aggregate over a heavy weight non-woven filter fabric base. As soon as construction begins, stabilize bare areas with gravel and temporary mulch and/or vegetation.

E) Clearing and Grubbing

Use the following techniques for clearing and grubbing activities:

COR & BID & BMP 15

1) Leave areas undisturbed when possible.

2) Construct silt basins to provide silt volume for large areas.

3) Construct Silt Trap(s) Type A for small areas.

4) Construct Type B silt traps for areas with rapid runoff and sediment-laden runoff.

5) All silt traps should have a 3:1 flow length to width ratio. Add spreader bars, baffles, or turbidity curtains to maintain the flow path ratio when site conditions require traps sizes smaller than the standard detail dimensions.

6) Install geotextile bags and/or rock checks in front of existing drop inlets.

7) Construct diversion ditches to catch sheet runoff and carry it to basins or traps or to divert it around areas to be disturbed.

8) Maintain brush and/or other barriers to slow and/or divert runoff.

9) Construct silt fences/hay bales to catch sheet runoff on short slopes. For longer slopes, multiple rows of silt fence/hay bales may be considered.

10) Apply temporarily mulch to area not actively being disturbed or for any area left undisturbed for fourteen (14) days.

11) Employ non-standard or innovative methods.

F) Stream Crossings / Work Along Streams

1) Temporary low-water stream crossings follow the guidelines included in the DAML Technical Specifications and those established by the KY Division of Water Floodplain Management Section. Removal of a temporary crossing may be required to accommodate large storm events.

2) Do not completely block stream flow (even temporary). Instead, utilize some form of pass thru mechanism during all AML projects.

3) Work within a stream channel shall not cause flooding of properties upstream, downstream or within the project area or cause downstream water quality degradation. Minimize equipment contact time with the stream water by diverting water around equipment working in or along streams.

4) No flowing water will interact with any uncured concrete placed in the stream channel.

5) Divert all stream water around the work areas in accordance to methods listed in the DAML

Stream Protection & Relocation technical specification, AML Standard Details Section 60, and as by the appropriate permit guidelines.

6) Temporary out of channel stream diversion must use one of the three approved methods:

pipe diversion, sandbag/stone channel diversion, and/or fabric-based channel diversion.

Do not construct any temporarily diverted channel on bare, erodible soil. No temporary diversion shall be permanent without a 401, 404, and other appropriate permits.

COR & BID & BMP 16

G) Deep Mine and Surface Water Impoundments

The DAML Resident Inspector will test the mine water from deep mines and surface impoundments on the project area to determine the pH and total iron content. Treat the water until it meets the DAML Water-Treatment and Disposal Technical Specification or an existing TMDL, whichever is stricter, before release through a silt control structure(s).

Monitoring & Recording

The DAML Inspector will maintain a log of the pH and total iron content results prior to releasing and during each release day. Perform a minimum of two (2) tests downstream each day to ensure the maintenance of water quality during release and is not degrading the receiving stream.

Types of structures/facilities include:

1) Silt Traps Type A (20’L x 5’W x 2’D min dugout)

2) Silt Traps Type B (20’L x 5’W x 2’D min dugout with rock berm)

3) Silt Check - Rock checks with filter fabric core lining installed in channels and in front of pipes

4) Temporary silt control fence with Class II filter berm

5) Sediment collection bags

H) Cut and Fill and Placement of Drainage Structures

Areas at final grade will be seeded and mulched within five (5) days. Soil stock piles and areas that are not at final grade but where construction will cease for a period of fourteen (14) days or longer, shall receive temporary mulch no later than fourteen (14) days from the last construction activity in that area.

Types of structures/facilities include:

1) Silt Traps Type B (20’L x 5’W x 2’D min dugout with rock berm)

2) Silt Checks - Bags in front of pipes after they are placed

3) Channel lining

4) Erosion control blanket

5) Temporary mulch and/or seeding for areas where construction activities will be ceased for

14 days or more

6) Non-standard or innovative methods

I) Temporary Shutdown

Items to be completed prior to shutdown include:

1) Clean out behind, repair or replace silt fence and/or hay bales

2) Clean out all silt traps

COR & BID & BMP 17

3) Apply temporary mulch and track into the soil

4) Sow cover crop (weather permitting)

J) Finish Work

1) Establish permanent seeding and protection

2) Remove non-permanent silt checks from ditches and drains if protected with other BMPs sufficient to control erosion and vegetation is established.

3) Remove non-permanent silt traps and basins.

4) Remove geotextile silt fence.

5) Planting trees and/or shrubs where they are included in the project.

6) Clean out behind, repair, and/or replace bale silt barriers

7) Clean out all permanent silt traps and basins

K) Post-Construction

The Contractor shall assume responsibility for all workmanship and materials for a period of one year from the date of final payment, as directed by the Contract Documents. Any work found to be defective due to failure to comply with the provisions and intent of the Contract Documents shall be corrected at the Contractor's expense. Problems determined not to be created by the landowner or due to the Contractor will be addressed by the DAML for a period of up to three years, pending available funding.

OTHER CONTROL MEASURES

L) Solid Materials

No solid materials, including rock and building materials, shall be discharged into waters of the U.S. except as authorized by the Clean Water Act (CWA) Section 401 and Section 404 permits.

M) Waste Materials

Collect and store waste materials that may leach pollutants (paint and paint containers, caulk tubes, oil/grease containers, liquids of any kind, soluble materials, etc.) in appropriate covered waste containers. Remove waste containers from the project site frequently as to not allow wastes to become a source of pollution. Instruct all personnel regarding the correct procedure for waste disposal and dispose of wastes in accordance with appropriate regulations.

N) Hazardous Waste

Manage and dispose of hazardous waste materials in the manner specified by local or state regulation. Notify the Resident Inspector if there are any hazardous wastes generated, and provide a plan for the management and disposal of such materials. Instruct site personnel with regard to proper storage and handling of hazardous wastes when required and use the practices to reduce the risks associated with all hazardous materials. Keep products in original containers

COR & BID & BMP 18

unless they are not re-sealable with the original labels and material safety data sheets (MSDS) will be reviewed and retained.

O) Spill Prevention

Use good housekeeping and material management practices to reduce the risk of spills or other exposure of materials and substances to the weather and/or runoff. Manufacturers' recommended methods for spill cleanup will be maintained on site and readily available upon request. Make personnel aware of procedures and the location of the information and cleanup supplies.

Equipment and materials will include as appropriate, brooms, dust pans, mops, rags, gloves, oil absorbents, sand, sawdust, and plastic and metal trash containers.

Clean up all spills immediately after discovery. Keep the spill area well ventilated. Personnel will wear appropriate protective clothing to prevent injury from contract with a hazardous substance. Report spills of toxic or hazardous material to the appropriate state/local agency as required by KRS 224 and applicable federal law. Wastes from spill cleanup will be disposed of in accordance with appropriate regulations. The spill prevention plan will be adjusted, as needed, to prevent spills from reoccurring and improve spill response and cleanup.

P) Petroleum Products

Monitor vehicles and equipment fueled and maintained on site for leaks, and receive regular preventative maintenance to reduce the chance of leakage. Protect petroleum products onsite will be stored in tightly sealed, clearly labeled containers from exposure to weather. The CONTRACTOR shall not have a total of over 1,300 gallons of petroleum products on site at any given time.

Q) Fertilizers

Store fertilizers in a covered area away from water. Transfer the contents of any partially used bag of fertilizer to a sealable plastic bin to avoid spills. Once applied, work into the soil and apply mulch to limit exposure to storm water.

R) Concrete Truck Washout

Concrete truck mixers and chutes will not be washed on pavement, near storm drain inlets, or within seventy (75) feet of any ditch, stream, wetland, lake, or sinkhole. Where possible, discharge excess concrete and wash water to areas prepared for pouring new concrete, flat areas to be paved that are away from ditches or drainage system features, or other locations that will not drain off site. Where this approach is not possible, excavate a shallow earthen washbasin away from ditches to receive the wash water.

INSPECTIONS

Use inspection and maintenance practices to maintain erosion and sediment controls:

COR & BID & BMP 19

1) The Contractor and DAML Resident Inspector will inspect all erosion prevention and sediment control measures at least once each week and following any rain of 0.1 inch or more.

2) The DAML Resident Inspector will record the silt control inspections by in their daily report.

3) Silt fences/hay bales will be inspected for bypassing, overtopping, undercutting, depth of sediment, tears, and to ensure attachment to secure posts.

4) Inspect silt traps and basins for depth of sediment, and built-up sediment and clean out when it reaches 50% of the design capacity and at the end of the job.

5) Inspect diversion dikes and berms and promptly repaired any breaches. Repair areas that are eroding or scouring and re-seeded / mulched as needed.

6) Inspect temporary and permanent seeding and mulching for bare spots, washouts, and healthy growth. Repair bare or eroded areas as needed.

7) Inspect all material storage and equipment servicing areas that involve the management of bulk liquids fuels and bulk solids weekly for conditions that represent a release or possible release of pollutants to the environment.

MAINTENANCE

Maintain all measures in good working order; initiate corrective actions within twenty-four (24) hours of being reported and completed with five (5) days, address critical failures immediately unless site conditions are too dangerous. Remove Built-up sediment from behind the silt fence/hay bales before it has reached halfway up the height of the fence.

ENFORCEMENT

At all times, representatives from DAML and enforcement agencies will have access to the project site. The ENGINEER reserves right to stop work until erosion prevention and sediment control problems are addressed to his/her satisfaction.

24033AMLBAML RECLAMATION PROJECT

ADDENDUM #1

PIKE COUNTY, KENTUCKY

24033AM

LBAM

L AM

L R

EC

LAM

ATIO

N

PR

O

JEC

T

AD

D

EN

D

U M

#1

PIKE C

O U

N

TY

FINANCE AND ADMINISTRATION CABINET

DEPARTMENT FOR FACILITIES & SUPPORT SERVICES DIVISION OF

ENGINEERING & CONTRACT ADMINISTRATION

FRANKFORT, KENTUCKY

ENERGY AND ENVIRONMENT CABINET

DEPARTMENT FOR NATURAL RESOURCES

DIVISION OF ABANDONED MINE LANDS

COMMONWEALTH OF KENTUCKY

AutoCAD SHX Text Index of Sheets

AutoCAD SHX Text F:\Projects\AML\24033AMLBAML (Sean Adams Drainage)\1 Design Phase\1 Drawings\24033AMLBAML Plan Set A1 (for Stamp).dwg

AutoCAD SHX Text

PLANVIEW W/ PHOTO PLANVIEW W/ CONTOURS

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text DRIVING DIRECTIONS: LATITUDE: 37.5372N LONGITUDE:82.2234W 37.5372N LONGITUDE:82.2234W LONGITUDE:82.2234W DIRECTIONS - FROM THE INTERSECTION OF US-23 AND US-119 NEAR PIKEVILE - TRAVEL US-119 NORTH 18.6 MILES AND TURN RIGHT ONTO KY-199/POND CREEK ROAD. TRAVEL 3.3 MILES AND TURN LEFT ONTO KY-1056. TRAVEL 3.9 MILES AND TURN RIGHT ONTO UPPER BLACKBERRY ROAD. TRAVEL 1.2 MILES TO THE PROJECT SITE ON RIGHT. ALL WASTE GENERATED BY THIS PROJECT WILL BE PROPERLY PLACED WITHIN THE SITE PROJECT LIMITS.

AutoCAD SHX Text THE AML STANDARD DETAILS AND TECHNICAL SPECIFICATIONS ARE AVAILABLE ON OUR WEBSITE AT: HTTPS://EEC.KY.GOV/NATURAL-RESOURCES/MINING/ABANDONED-MINE-LANDS/PAGES/CONTRACTOR_INFORMATION.ASPX UNDER "STANDARD DETAILS AND SPECIFICATIONS". BY BIDDING ON THIS PROJECT THE CONTRACTOR ACKNOWLEDGES THEY HAVE REVIEWED AND UNDERSTAND THE STANDARD DETAILS AND TECHNICAL SPECIFICATIONS AS THEY APPLY TO THIS PROJECT. UTILITY NOTE PRIOR TO ANY EXCAVATION OR THE PLACEMENT OF FILL, THE CONTRACTOR IS REQUIRED TO CALL “KENTUCKY KENTUCKY 811” TWO (2) BUSINESS DAYS PRIOR TO ANY EXCAVATION / EXCAVATION ACTIVITIES. IF THERE ARE UTILITIES TWO (2) BUSINESS DAYS PRIOR TO ANY EXCAVATION / EXCAVATION ACTIVITIES. IF THERE ARE UTILITIES IN THE WORK AREAS THAT ARE NOT MEMBERS OF “KENTUCKY 811”, EACH UTILITY HAS TO BE CONTACTED KENTUCKY 811”, EACH UTILITY HAS TO BE CONTACTED , EACH UTILITY HAS TO BE CONTACTED DIRECTLY TO HAVE THEIR FACILITIES MARKED. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO ABIDE BY THE "UTILITY RELOCATION" TECHNICAL SPECIFICATION AND SECTION 22.3 OF THE "GENERAL PROVISIONS" TECHNICAL SPECIFICATION. DEPICTION OF THE UTILITIES ON THE PLANS ARE APPROXIMATE AND MAY NOT INCLUDE ALL EXISTING UTILITIES.

AutoCAD SHX Text

PROJECT SITE

ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ððð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð

AutoCAD SHX Text

SEAN ADAMS

AutoCAD SHX Text

UPPER BLACKBERRY ROAD

AutoCAD SHX Text

LAT: 37.5372 LON:-82.2234

AutoCAD SHX Text

WATER METER

AutoCAD SHX Text

WATER METER

AutoCAD SHX Text

SEPTIC

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

WASTE

AutoCAD SHX Text

UPPER BLACKBERRY (STREAM)

AutoCAD SHX Text

WELL STRUCTURE

AutoCAD SHX Text F:\Projects\AML\24033AMLBAML (Sean Adams Drainage)\1 Design Phase\1 Drawings\24033AMLBAML Plan Set A1 (for Stamp).dwg

AutoCAD SHX Text

COMMONWEALTH OF KENTUCKY

AutoCAD SHX Text

DRAWN BY

AutoCAD SHX Text

DATE

AutoCAD SHX Text

CHECKED BY

AutoCAD SHX Text

PLANVIEW W/ PHOTO

AutoCAD SHX Text

JSM

AutoCAD SHX Text

DLS

AutoCAD SHX Text

24033AMLBAML RECLAMATION PROJECT ADDENDUM #1

AutoCAD SHX Text ENERGY AND ENVIRONMENT CABINET DEPARTMENT OF NATURAL RESOURCES DIVISION OF ABANDONED MINE LANDS FRANKFORT, KY

AutoCAD SHX Text

PIKE

AutoCAD SHX Text

COUNTY OF

AutoCAD SHX Text

SHEET NO.

AutoCAD SHX Text

TOTAL SHEETS

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 10/9/2025

AutoCAD SHX Text FINANCE & ADMINISTRATION CABINET DEPARTMENT FOR FACILITIES & SUPPORT SERVICES DIVISION OF ENGINEERING & CONTRACT ADMINISTRATION FRANKFORT, KY

AutoCAD SHX Text

INSTALL 320 LF SUBDRAIN (AML 22-30-1)

AutoCAD SHX Text

INSTALL SUBDRAIN COLLAR (AML 22-30-2)

AutoCAD SHX Text

INSTALL 160 LF 8" DIA. HDPE PIPE - STANDARD (AML 23-50-2)

AutoCAD SHX Text

EXISTING 18" DIA. RCP W/ CONCRETE HEADWALLS

AutoCAD SHX Text

INSTALL 120LF 15" HDPE PIPE - STANDARD (AML 23-50-2)

AutoCAD SHX Text

INSTALL TEE TO CONNECT 8" OUTLET TO 15" DIA. CULVERT

AutoCAD SHX Text

EXISTING CONCRETE DROP STRUCTURE

AutoCAD SHX Text

EXISTING 18" DIA. RCP W/ CONCRETE HEADWALLS

AutoCAD SHX Text

STORAGE BUILDING - REMOVE AND REPLACE FOR SUBDRAIN INSTALLATION

AutoCAD SHX Text

CLEAN OUT UP TO 15 LF ROADSIDE DITCH FOR OPTIMUM FLOW INTO CULVERT

EXISTING DITCH - CLEAN OUT AS NECESSARY FOR DRAINAGE FROM CULVERT

ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ððð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð ð

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

SEAN ADAMS

AutoCAD SHX Text

UPPER BLACKBERRY ROAD

AutoCAD SHX Text

LAT: 37.5372 LON:-82.2234

AutoCAD SHX Text

WATER METER

AutoCAD SHX Text

WATER METER

AutoCAD SHX Text

SEPTIC

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

WASTE

AutoCAD SHX Text

UPPER BLACKBERRY (STREAM)

AutoCAD SHX Text

WELL STRUCTURE

AutoCAD SHX Text F:\Projects\AML\24033AMLBAML (Sean Adams Drainage)\1 Design Phase\1 Drawings\24033AMLBAML Plan Set A1 (for Stamp).dwg

AutoCAD SHX Text

COMMONWEALTH OF KENTUCKY

AutoCAD SHX Text

DRAWN BY

AutoCAD SHX Text

DATE

AutoCAD SHX Text

CHECKED BY

AutoCAD SHX Text

PLANVIEW

AutoCAD SHX Text

JSM

AutoCAD SHX Text

DLS

AutoCAD SHX Text

24033AMLBAML RECLAMATION PROJECT (ADDENDUM #1)

AutoCAD SHX Text ENERGY AND ENVIRONMENT CABINET DEPARTMENT OF NATURAL RESOURCES DIVISION OF ABANDONED MINE LANDS FRANKFORT, KY

AutoCAD SHX Text

PIKE

AutoCAD SHX Text

COUNTY OF

AutoCAD SHX Text

SHEET NO.

AutoCAD SHX Text

TOTAL SHEETS

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 10/9/2025

AutoCAD SHX Text FINANCE & ADMINISTRATION CABINET DEPARTMENT FOR FACILITIES & SUPPORT SERVICES DIVISION OF ENGINEERING & CONTRACT ADMINISTRATION FRANKFORT, KY

AutoCAD SHX Text

INSTALL 320 LF SUBDRAIN (AML 22-30-1)

AutoCAD SHX Text

INSTALL SUBDRAIN COLLAR (AML 22-30-2)

AutoCAD SHX Text

INSTALL 160 LF 8" DIA. HDPE PIPE - STANDARD (AML 23-50-2)

AutoCAD SHX Text

EXISTING 18" DIA. RCP W/ CONCRETE HEADWALLS

AutoCAD SHX Text

INSTALL 120LF 15" HDPE PIPE - STANDARD (AML 23-50-2)

AutoCAD SHX Text

INSTALL TEE TO CONNECT 8" OUTLET TO 15" DIA. CULVERT

AutoCAD SHX Text

EXISTING CONCRETE DROP STRUCTURE

AutoCAD SHX Text

EXISTING 18" DIA. RCP W/ CONCRETE HEADWALLS

AutoCAD SHX Text

CONTOUR INTERVAL = 1 FT

AutoCAD SHX Text

100-YR FLOODPLAIN

AutoCAD SHX Text

CLEAN OUT UP TO 15 LF ROADSIDE DITCH FOR OPTIMUM FLOW INTO CULVERT

AutoCAD SHX Text

EXISTING DITCH - CLEAN OUT AS NECESSARY FOR DRAINAGE FROM CULVERT

STORAGE BUILDING - REMOVE AND REPLACE FOR SUBDRAIN INSTALLATION

Addendum One
24033AMLBAML Bid Schedule A1
24033AMLBAML COR A1
24033AMLBAML Plan Set A1 (stamped)