Addendum One .pdf
PDF 5 MB Posted
- Attached to
- RFB-122-24 Lisa Combs Slide Perry County
- Solicitation number
- RFB-785-2400000232-3
- Issued by
- Montgomery County, Brooksville City, Kentucky
About this file
This document is an addendum to an Invitation to Bid (ITB) for the Lisa Combs Slide AML Reclamation Project in Perry County, Kentucky, issued by the Commonwealth of Kentucky's Department for Facilities and Support Services, Division of Engineering and Contract Administration.
The project involves the construction of additional gabion walls, concrete gravity walls, drainage ditches, and the replacement of HDPE pipe and headwalls to address an existing landslide below a residence. The bid schedule includes 26 line items for various construction activities. The addendum revises the bid schedule, project description, and construction notes. The project must be completed within 150 calendar days of the contract award. Contractors are required to submit the AML Contractor/Subcontractor Information Form with their bid. The Kentucky Division of Abandoned Mine Lands will be responsible for obtaining certain permits, while the contractor is responsible for all other necessary permits.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final_RFB_785_2400000232_1_SO_FORM.PDF | ||
| Final_RFB_785_2400000232_2_SO_FORM.PDF | ||
| Final_RFB_785_2400000232_3_SO_FORM.PDF | ||
| Addendum Two .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-122-24
FOR: Lisa Combs Slide
AML Project Perry County, Kentucky
DATE: November 30, 2023
ADDENDUM NO. One (1)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.
Item 2: Bidder must use REVISED BID SCHEDULE 11/30/2023 in lieu of previously issued.
Item 3: Construction Notes
Item 4: Revised Project Description
Item 5: Revised COR Documents
Item 6: Revised planset
END OF ADDENDUM
Invitation to Bid No. RFB-122-24 For: Lisa Combs Slide
AML Project Perry County, Kentucky
Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration
NO. ITEM M.O.P. UNIT QUANTITY UNIT PRICE TOTAL
1 MOBILIZATION L.S. L.S. 1.0 X NA = 25,000.00$
2 UTILITY RELOCATION/REPLACEMENT A.C.U. A.C.U. 1.0 X 10,000.00$ = 10,000.00$
3 LANDSCAPE ALLOWANCE A.C.U. A.C.U. 1.0 X 2,500.00$ = 2,500.00$
4 TRAFFIC CONTROL L.S. L.S. 1.0 X = $
5 SITE PREPARATION U.P. ACRE 1.0 X $ = $
6 SITE PREPARATION- WASTE AREAS U.P. ACRE 1.0 X $ = $
7 GROUT U.P. CY 25.0 X $ = $
8 60 KSI REINFORCING STEEL U.P. LBS 50.0 X $ = $
9 CONCRETE- FORMED & FINISHED U.P. CY 25.0 X $ = $
10 FILTER FABRIC U.P. SY 320.0 X $ = $
11 NO. 2 STONE BACKFILL U.P. TON 25.0 X $ = $
12 CLASS II BACKFILL U.P. TON 710.0 X $ = $
13 SILT BARRIER - BALES & FENCE U.P. LF 300.0 X $ = $
14 HOE RAM U.P. HOUR 50.0 X $ = $
15 EARTHWORK (LUMP SUM) L.S. L.S. 1.0 X $ = $
16 CLASS II / III U.P. TON 150.0 X $ = $
17 GABION RECTANGULAR DITCH U.P. CY 24.0 X $ = $
18 RETAINING WALL SUBDRAIN U.P. LF 160.0 X $ = $
19 24" DIA. HDPE PIPE- STANDARD U.P. LF 100.0 X $ = $
20 CONCRETE HEADWALL- PIPES ≤36" DIA. U.P. EACH 2.0 X $ = $
21 GABION RETAINING WALL U.P. CY 300.0 X $ = $
22 RESIDENTIAL SEEDING U.P. ACRE 2.0 X $ = $
23 ROADWAY STONE U.P. TON 100.0 X $ = $
24 BITUMINOUS REPAIR U.P. TON 150.0 X $ = $
25 DEBRIS BARRIER WALL- BALE & PLYWOOD U.P. LF 50.0 X $ = $
26 CHAIN-LINK FENCE U.P. LF 220.0 X $ = $
BID TOTAL = $
23063AMLBAML LISA COMBS SLIDE (AML) RECLAMATION PROJECT
PERRY COUNTY, KENTUCKY
BID SCHEDULE
NOTE: THE AUTHENTICATION OF BID AND STATEMENT OF NON-COLLUSION AND NON-CONFLICT OF INTEREST PAGE MUST BE
PROPERLY EXECUTED FOR THE TOTAL BID AMOUNT TO BE VALID.
REVISED BID SCHEUDLE 11/30/2023 RFB-122-24
23063AMLBAML LISA COMBS SLIDE
Construction Notes (11-29-2023)
1. Bid Item #10 an additional 300 Square Yards of Filter Fabric.
2. Bid Item #12 an additional 60 tons of Class II stone for ditch construction.
3. Bid Item # 20 an additional 60 LF of 24” HDPE pipe
4. Bid Item #21 an additional one each of 24” Standard Headwall.
5. Bid Item #22 an additional 90 Cubic Yards of Gabions
6. The addition of Gabion Rectangular Ditch to turn water from drain onto Class II ditch below residence and railroad grade.
23063AMLBAML LISA COMBS SLIDE
AML RECLAMATION PROJECT
PERRY COUNTY
PROJECT DESCRIPTION:
This project is located in Perry County near the community of Bulan KY, at Latitude 37.2966°N
Longitude -83.1746°W. To reach the site from the Intersection of KY Hwy 80 and KY Hwy 15, travel Northeast on KY Hwy 80 3.84 miles to KY Hwy 1146, turn right and continue on KY
Hwy 1146 for 1.24 miles to the intersection of KY Hwy 550/476, turn right onto KY Hwy
550/476 and travel 1.00 miles to Indianhead Hollow, turn right onto Indianhead Hollow and travel 0.28 miles to driveway below Combs Residence, turn right onto driveway and travel 0.03 miles to residence below Combs Residence site is directly behind and to the side of residence.
This Site will consist of an additional 36 Liner Foot of 6’ high Gabion Wall added to the top of existing Gabion wall below the residence, with an additional 84 Liner Foot of 12’ high Gabion
Wall added at the end of existing Gabion Wall to contain slide below Combs Residence. The construction of 50 Liner Foot of 3’ high Concrete Gravity Wall, construction of 80 Liner Foot of
Cut-into-Rock 2’ Flat Bottom Ditch. Installation of 90 Liner Foot of Class III Ditch-4 foot flat bottom with Grout. The replacement of 40 Linear Foot of 24” HDPE pipe with one Standard
Headwall. The Construction of 60 LF of 24” HDPE pipe and one Standard Headwall. The construction of an Gabion Ditch to control drainage. Silt Checks-Rock will be installed as needed by Scientist on site at appropriate locations. Class II aggregate and filter fabric will be installed behind the wall.
Mobilization is setup to provide for construction equipment to be delivered to the site. Hoe Ram hours included if rock encounter during the construction of walls and ditches. Utility Relocation, Site Prep is included, at both the sites and waste area to prep the areas for reclamation and material storage. Residential Seeding are included for all revegetation efforts within the site and waste area. Roadway Stone are included to provide for access during normal reclamation.
Bituminous Repair is included to repair “in kind” all asphalt surfaces damage due to normal reclamation activities. Earthwork work bid item is included to excavate material to seat wall and at other areas as directed by the ENGIEER. Material will be transported to an off-site waste area.
Waste Area: This offsite waste area is located on a previously disturbed mined area. To access the site from Intersection of KY Hwy 15 and KY Hwy 80 in Perry County. Travel North on KY Hwy 15 6.80 miles to Trus Joist Lane, turn left and continue on Trus Joist Lane Road for
0.25 miles to Keith Miller Drive, turn right onto Keith Miller Drive and travel 0.32 miles to
Waste Area on right road. The coordinates are 37.364684° N -83.261967° W.
Any permits will be obtained prior to construction. No trees 3” diameter or more at breast height will be disturbed, no cave-like structures will be closed, and no cliff-lines will be disturbed.
Revised 5/10/2023
COR & BID & BMP 1
23063AMLBAML LISA COMBS SLIDE (AML) RECLAMATION PROJECT
PERRY COUNTY, KENTUCKY
Written Location Directions: This project is located in Perry County near the community of Bulan
KY, at Latitude 37.2966°N Longitude -83.1746°W. To reach the site from the Intersection of KY
Hwy 80 and KY Hwy 15, travel Northeast on KY Hwy 80 3.84 miles to KY Hwy 1146, turn right and continue on KY Hwy 1146 for 1.24 miles to the intersection of KY Hwy 550/476, turn right onto KY Hwy 550/476 and travel 1.00 miles to Indianhead Hollow, turn right onto Indianhead
Hollow and travel 0.28 miles to driveway below Combs Residence, turn right onto driveway and travel 0.03 miles to residence below Combs Residence site is directly behind and to the side of residence.
Basic Project Description: This Site will consist of an additional 36 Liner Foot of 6’ high Gabion
Wall added to the top of existing Gabion wall below the residence, with an additional 84 Liner
Foot of 12’ high Gabion Wall added at the end of existing Gabion Wall to contain slide below
Combs Residence. The construction of 50 Liner Foot of 3’ high Concrete Gravity Wall, construction of 80 Liner Foot of Cut-into-Rock 2’ Flat Bottom Ditch. Installation of 90 Liner Foot of Class III Ditch-4 foot flat bottom with Grout. The replacement of 40 Linear Foot of 24” HDPE pipe with one Standard Headwall. The Construction of 60 LF of 24” HDPE pipe and one Standard
Headwall. The construction of an Gabion Ditch to control drainage. Silt Checks-Rock will be installed as needed by Scientist on site at appropriate locations. Class II aggregate and filter fabric will be installed behind the wall.
A. ALLOWABLE PRICE LIMIT
Allowable Price Limit (APL) is part of the contract documents and is stated on the Bid Schedule. The
Unit Price (UP) / Lump Sum Price (LS) has a low value defined for each item on the Bid Schedule. Any
Unit Price / Lump Sum Price outside this value may be considered an unbalanced bid and may have to be justified in writing if such bid is deemed the low responsive bid. The CONTRACTOR is also cautioned that other considerations for rejection, notwithstanding the APL, may be enforced (e.g.
total bid price being excessively over the ENGINEER’S ESTIMATE).
B. CONTRACT LENGTH
All work shall be completed within ONE HUNDRED FIFTY (150) calendar days from the effective date of the Award of Contract. Within the bounds of prudent project performance, it shall be the responsibility of the CONTRACTOR to plan and implement construction sequences which follow the intent of these CONTRACT DOCUMENTS, particularly as, reflected in the Drawings and Special
Conditions and to protect any portion of the contract which may be completed before others.
C. CONTRACTOR’S INFORMATION SHEET
The AML CONTRACTOR/SUBCONTRACTOR INFORMATION FORM sheet must be filled out and submitted with the bid. Failure to submit the AML Contractor/SubContractor Information Form sheet with the bid will be the basis for declaring the bid “Non-Responsive”
D. SPECIAL CONDITIONS & PROJECT NOTES
Revised 5/10/2023
COR & BID & BMP 2
- On occasion, a property owner may require a CONTRACTOR to add them on their General
Liability and/or Automobile Insurance as an “Additional Insured.” AML will inform the
CONTRACTOR when this requirement is being made by the property owner. In these cases, the
CONTRACTOR must submit to AML copies of their certificate of insurance documenting the
“Additional Insured” before they will be allowed to mobilize equipment and forces on to said properties. Any fees, rate increases, or other costs incurred by the CONTRACTOR for this requirement, if any, will be considered incidental to mobilization and as such no compensation will be made by AML. The “Additional Insured” must remain on the CONTRACTOR’s policy(s) for the full length of the contract.
- Add any special conditions, notes, exceptions to standard documents or write “None”.
- Add Bid Item descriptions that are contrary to standards notes.
E. PERMITS & FEES – AML will be responsible for obtaining any permits that are checked below.
(check all that apply)
☐KYTC Encroachment Permit
☐KY DOW Water Permits
☐USACE Permit
The CONTRACTOR is responsible for all other permits and/or fees necessary to begin the project. The
CONTRACTOR is advised that on occasion, other permits and/or fees may be required by federal, state, and local government(s). Other types of permits and/or fees are not the responsibility of AML and as such, these will be the complete and total responsibility of the CONTRACTOR to obtain. These must be obtained before AML will allow mobilization of equipment and forces on to said properties. All costs associated with other permits or fees will be the responsibility of the CONTRACTOR. Please refer to
“General Provisions” in the AML Technical Specifications.
Revised 1/12/2023
COR & BID & BMP 3
BID ITEM DESCRIPTION
23063AMLBAML LISA COMBS SLIDE AML RECLAMATION PROJECT
PERRY COUNTY, KENTUCKY
NO ITEM DESCRIPTION
1 MOBILIZATION This item consists of the mobilization and demobilization of the
CONTRACTOR’S forces and equipment in accordance with the
“Mobilization/Demobilization” AML Standard Technical Specification. The amount of this bid item is AS STATED ON THE BID SCHEDULE.
Measurement: Not Applicable.
Payment: Payment shall be made at increments set in the AML Technical
Specifications totaling the Lump Sum price.
2 UTILITY
RELOCATION /
REPLACEMENT
This consists of furnishing all materials, equipment, and labor necessary to replace utilities damaged by construction or relocate any utilities that are in the construction area in accordance with the “Utility Relocation” AML Standard
Technical Specification. The CONTRACTOR is required to supply the
ENGINEER with all documentation to support cost incurred to qualify for reimbursement.
Special Considerations: None
Major Incidentals: These will be listed in writing by the ENGINEER prior to beginning the work.
Measurement: Not Applicable.
Payment: Payment shall be made for Actual Documented Costs for
“UTILITY RELOCATION/REPLACEMENT” approved by the
ENGINEER. The payment shall be a direct reimbursement for actual documented costs to the CONTRACTOR in accordance with the “General
Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and incidentals.
COR & BID & BMP 4
3 LANDSCAPE
ALLOWANCE
This item of work shall consist of furnishing all materials, equipment, and labor necessary to replace damaged landscape structures, plants and trees as depicted on Drawings and as directed by ENGINEER in accordance with the
“Revegetation” AML Standard Technical Specification. The CONTRACTOR is required to supply the ENGINEER with all documentation to support cost incurred to qualify for reimbursement.
Special Considerations: None
Inspector Notes: Conduct a picture inventory of landscape items that may be affected before construction starts and keep an item list of those landscape items that are affected.
Major Incidentals: These will be listed in writing by the ENGINEER prior to beginning the work.
Measurement: Not Applicable
Payment: Payment for Actual Documented Costs “LANDSCAPE
ALLOWANCE” approved IN ADVANCE by the ENGINEER. The payment shall be a direct reimbursement for the removal/replacement of landscape features as approved/directed by the ENGINEER in accordance with the
“General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and incidentals.
4 TRAFFIC CONTROL This item consists of maintaining and controlling traffic on existing roads
(public and private) affected by this project as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Traffic Control” AML
Standard Technical Specification. Appropriate signs shall be erected at the project limits and flag persons shall be used as needed.
Special Considerations: None
Major Incidentals: Signs, flaggers, steel plates, immediately clearing debris from roadway.
Measurement: Not Applicable.
Payment: Payment shall be made at the Lump Sum price bid for “TRAFFIC
CONTROL” in accordance with the “General Provisions” AML Standard
Technical Specification. Such payment shall constitute full compensation for materials, equipment, labor, and incidentals.
COR & BID & BMP 5
5 SITE PREPARATION This item of work shall consist of furnishing all materials, equipment, and labor as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Site Preparation” AML Standard Technical Specification.
Special Considerations: None
Major Incidentals: Clearing, grubbing, windrowing, burning, pipe removal and disposal, pipe cleanout, temporary diversion ditch construction, domestic debris removal and disposal, concrete & bituminous asphalt debris removal and disposal, access improvement/construction, in-kind fence repair/replacement, and temporary stream diversion.
Measurement: Actual Quantities shall be measured with a handheld GPS and rounded up to the next whole 0.5 acre actually cleared and grubbed (excludes slurry and refuse areas.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “SITE PREPARATION” in accordance with the
“General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and other items necessary to complete the work.
6 SITE
PREPARATION-
WASTE AREAS
This item of work shall consist of furnishing all materials, equipment, and labor as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Site Preparation” AML Standard Technical Specification.
Special Considerations: None
Major Incidentals: Clearing, grubbing, windrowing, burning, pipe removal and disposal, pipe cleanout, temporary diversion ditch construction, domestic debris removal and disposal, access improvement/construction, in-kind fence repair/replacement.
Measurement: Actual Quantities shall be measured with a handheld GPS and rounded up to the next whole 0.5 acre actually cleared and grubbed (excludes slurry and refuse areas).
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “SITE PREPARATION- WASTE AREAS” in accordance with the “General Provisions” AML Standard Technical
Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and other items necessary to complete the work.
7 GROUT
This item consists of furnishing and placing grout as depicted on the Drawings and as directed by the ENGINEER in accordance with “Grout Products” AML
Standard Technical Specification.
Special Considerations: None
Major Incidentals: Formwork, subgrade preparation and testing.
Measurement: Actual Quantities shall be measured as the next whole cubic yard installed and accepted by the ENGINEER.
Payment: Payment shall be the product of Actual Quantities and the Unit
Price for “GROUT” in accordance with the “General Provisions” AML
Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and incidentals.
COR & BID & BMP 6
8 60-KSI
REINFORCING
STEEL
This item consists of furnishing all materials, equipment, and labor necessary to properly installing 60 KSI reinforcing steel of various diameters and lengths as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Concrete” and “Steel” AML Standard Technical Specifications.
This bid item covers steel used for: reinforcement in concrete ditches (all types), footers, retaining walls, concrete piles & cap reinforcement, anchors, Special Considerations: See AML Technical Specification for overlap Steel
Item 2.2.6.
No splicing shall be permitted for length of steel less than 10 feet in length.
Splicing of lengths between 10 feet and 20 feet is allowed. No lengths less than
4 feet is allowed including the overlap.
For lengths greater than 20 feet splicing is allowed. Minimum length of steel shall be 10 foot including overlap.
Maximum of 10 % payment for overlap steel.
Major Incidentals: Coatings, excess steel, connections, cut-offs, testing, and waste materials
Measurement: Actual Quantities shall be measured as pounds of reinforcing steel placed and accepted by the ENGINEER. Actual Quantities may be obtained by using a CRSI chart that shows lbs/lf for each size bar and multiplying the length of each bar used.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “60-KSI REINFORCING STEEL” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment as specified shall constitute full compensation for all labor, materials, equipment, and incidentals.
9 CONCRETE-
FORMED &
FINISHED
This item consists of furnishing all materials, equipment, and labor necessary to construct concrete field cast items as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Concrete” AML Standard
Technical Specification. This bid item covers concrete used for: concrete ditches (all types), retaining walls (all types), footers, caps, and any other purpose that requires formwork and/or finishing. All formwork, no matter the size/scale or changes are incidental, including increases in heights of walls.
Special Considerations: None
Inspector Notes: Collect manufacturer certificates for each unit.
Major Incidentals: Formwork (including height/width increases), admixtures, finishing, materials testing.
Measurement: Actual Quantities shall be measured as the next whole cubic yard installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price for “CONCRETE- FORMED & FINISHED” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and incidentals.
COR & BID & BMP 7
10 FILTER FABRIC This item consist of furnishing all materials, equipment, and labor, necessary to install filter fabric utilized in ditch construction as depicted on the Drawings and as directed by the ENGINEER in accordance with “Filter Fabric” AML
Standard Technical Specification. This includes all types of filter fabric used on a jobsite. The standard details list the type and quantity of fabric for each purpose.
Special Considerations: None
Inspector Notes: Collect manufacturer certificates for each unit.
Major Incidentals: Staples
Measurement: Actual Quantities shall be measured as the next whole square yard installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “FILTER FABRIC” in accordance with the “General
11 NO. 2 STONE
BACKFILL
This item shall consists of furnishing all materials, equipment, and labor necessary to place No. 2 stone aggregate as depicted on the Drawings and as directed by the ENGINEER in accordance with “Crushed Aggregate and
Channel Lining” AML Standard Technical Specification.
Special Considerations: None
Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) installed and accepted by the
ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “NO. 2 STONE BACKFILL” in accordance with the
“General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and
12 CLASS II BACKFILL This item consists of furnishing all materials, equipment, and labor necessary to place Class II aggregate as depicted on the Drawings and as directed by the
ENGINEER in accordance with the “Crushed Aggregate and Channel Lining”
AML Standard Technical Specification.
Special Considerations: None
Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) of each type of aggregate installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “CLASS II BACKFILL" in accordance with the “General constitute full compensation for all labor, materials, equipment, and incidentals.
COR & BID & BMP 8
13 SILT BARRIER–
BALES & FENCE
This item consists of furnishing all materials, equipment, and labor necessary to maintain silt control as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Silt Control” AML
Standard Technical Specification. Hay/straw bales shall be placed with an overlap equal to 0.4 bales per linear foot of silt control fencing. Silt fence shall be trenched and removed at the end of the project. Failure to remove silt control fence (geotextile fabrics) shall result in forfeiture of demobilization.
Special Considerations: None
Major Incidentals: Maintenance, silt fence trenching and removal
Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “SILT BARRIER - BALES & FENCE" in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for materials, equipment, labor, and
14 HOE RAM This item consist of furnishing all materials, equipment, and labor necessary to accomplish the required excavation of rock utilizing a hoe ram as depicted on the Drawings and as directed by the ENGINEER in accordance with the
“Equipment” AML Standard Technical Specification.
Special Considerations: None
Major Incidentals: Equipment, operator, fuel, maintenance items
Measurement: Actual Quantities shall be measured as the next whole equipment hour when required to construct ditches and other features approved by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “HOE RAM” in accordance with the “General constitute full compensation for materials, equipment, labor and incidentals.
15 EARTHWORK
(LUMP SUM)
This item consist of furnishing all materials, equipment, and labor necessary for excavation of materials as required to construct walls and other features as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Earthwork” AML Standard Technical Specification.
Special Considerations: None
Major Incidentals: Excavation, transportation, placement, compaction of all excavated materials including rock ditches constructed without hoe ram.
Measurement: Not applicable.
Payment: Payment shall be made at the Lump Sum price bid for
“EARTHWORK” in accordance with the “General Provisions” AML Standard
Technical Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and other items necessary to complete the work—this includes all transportation and gradework efforts associated with designated waste areas.
COR & BID & BMP 9
16 CLASS II / III –
(DITCHES,
ANCHORS, DRAINS,
& BUTTRESSES)
This item consist of furnishing all materials, equipment, and labor necessary to install Class II and Class III rock as depicted on the Drawings, AML Standard
Details, and as directed by the ENGINEER in accordance with “Crushed
Aggregate and Channel Lining” and “Ditches” AML Standard Technical
Specifications. Subgrade preparation shall be incidental. For channels with acid mine drainage DAML will use the current Limestone Sample Results published by the KY Department of Agriculture to determine an effective weight when material is from a source with < 85% calcium carbonate.
Special Considerations: None
Inspector Notes: Collect supplier tickets.
Major Incidentals: Excavation, subgrade preparation
Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) installed and accepted by the
ENGINEER. Material for treating AMD and not meeting the 85% minimum is adjusted by multiplying the weight ticket tons by the ratio of the report %
CaCO3 (as Calcium %) to the 85% minimum, rounded to the nearest ton.
Material exceeding the 85% minimum is not adjusted.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “CLASS II/III” in accordance with the “General constitute full compensation for all labor, materials, equipment, and incidentals.
17 GABION
RECTANGULAR
DITCH
This item consist of furnishing all materials, equipment, and labor necessary to prepare a uniform foundation, furnish, place and fill rectangular gabion baskets with aggregate as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with “Crushed Aggregate and
Channel Lining”, “Ditches”, and “Gabions” AML Standard Technical
Specifications.
Special Considerations: None
Inspector Notes: Collect manufacturer certificates for each unit.
Major Incidentals: Excavation, subgrade preparation, gabions, gabion aggregate, backfill.
Measurement: Actual Quantities shall be measured as the next whole cubic yard installed and accepted by the ENGINEER.
Payment: Payment shall be the product of Actual Accepted Quantities and the
Unit Price for “GABION RECTANGULAR DITCH” in accordance with the
“General Provisions” AML Standard Technical Specification. Such payment
COR & BID & BMP 10
18 RETAINING WALL
SUBDRAIN
This item of work shall consist of furnishing all materials, equipment, and labor necessary to install subsurface drains as depicted on the Drawings, AML
Standard Details, and as directed by the ENGINEER in accordance with the
“Crushed Aggregate and Channel Lining”, “Filter Fabric”, and “Subsurface
Drains” AML Standard Technical Specifications.
Special Considerations: None
Major Incidentals: Pipe, filter fabric, aggregate backfill
Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “RETAINING WALL SUBDRAIN” in accordance with the “General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and incidentals.
HDPE PIPE-
STANDARD
This item consists of furnishing all materials, equipment, and labor, necessary to install standard, non-steel reinforced HDPE pipe as depicted on the
Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Crushed Aggregate and Channel Lining”, “Grout
Products”, and “Pipe” AML Standard Technical Specifications.
Special Considerations: None
Inspector Notes: Collect manufacturer certificates for each unit.
Major Incidentals: Excavation, bedding, aggregate backfill to 1’ over top of pipe, steel plates for access maintenance.
Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “HDPE PIPE-STANDARD” in accordance with the
“General Provisions” AML Standard Technical Specification. Such payment shall constitute full compensation for all labor, equipment, materials, and
COR & BID & BMP 11
20 CONCRETE
HEADWALL- PIPES
≤36” DIA.
This item consists of furnishing all materials, equipment, and labor, necessary to construct the headwalls as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Concrete
Headwalls” AML Standard Technical Specification. Units cast in the field require fiber, pre-cast units require manufacturer certification that concrete meets or exceeds required strength.
Special Considerations: None
Inspector Notes: For pre-cast units collect manufacturer certificate (includes strength of concrete used).
Major Incidentals: Concrete, steel reinforcement, fiber, grout, formwork, dissipaters, backfill
Measurement: Actual Quantities shall be measured as “EACH” unit installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities installed and the Unit Price for “CONCRETE HEADWALL- PIPES ≤36”
DIA.” in accordance with the “General Provisions” AML Standard Technical
Specification. Such payment shall constitute full compensation for all labor, materials, equipment, and incidentals.
21 GABION
RETAINING WALL
This item consists of furnishing all materials, equipment, and labor, necessary to prepare a uniform foundation, furnishing, placing and filling gabion baskets as depicted on the Drawings, AML Standard Details, and as directed by the
ENGINEER in accordance with the “Crushed Aggregate and Channel Lining”
“Geogrid”, “Filter Fabric”, and “Gabions” AML Standard Technical
Specifications.
Special Considerations: None
Inspector Notes: Collect manufacturer certificates for each unit.
Major Incidentals: Gabion baskets, gabion aggregate, & labor.
Measurement: Actual Quantities shall be measured as the next whole cubic yard installed and accepted by the ENGINEER.
Payment: Payment shall be the product of Actual Accepted Quantities and the
Unit Price bid for “GABION RETAINING WALL” in accordance with the
“General Provisions” AML Standard Technical Specification. Such payment
COR & BID & BMP 12
22 RESIDENTIAL
SEEDING
This item shall consist of furnishing all materials, equipment, and labor for the purpose of revegetation of the disturbed areas as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Revegetation” AML
Standard Technical Specification.
Special Considerations: None
Major Incidentals: Seedbed preparation, agriculture limestone, fertilizer, seed, and mulch
Measurement: Actual Quantities shall be measurement as the next tenth of an acre seeded as approved by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “RESIDENTIAL SEEDING” in accordance with the
“General Provisions” AML Standard Technical Specification. Such payment
23 ROADWAY STONE This item shall consist furnishing all materials, equipment, and labor necessary to place and compact as necessary the various gradations of stone as depicted on the Drawings and as directed by the ENGINEER in accordance with the
“Crushed Aggregate and Channel Lining” AML Standard Technical
Specification.
Special Considerations: None
Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) of each type of channel lining, and/or aggregate installed and accepted by the ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and the Unit Price bid for “ROADWAY STONE” in accordance with the “General
24 BITUMINOUS
REPAIR
This item shall consist of furnishing all materials, equipment, and labor necessary to repair bituminous surfaces damaged by construction activities as depicted on the Drawings and as directed by the ENGINEER in accordance with the “Bituminous Repair” AML Standard Technical Specification.
Removal and disposal of old materials are covered under the site preparation bid item.
Special Considerations: None
Major Incidentals: DGA, subgrade preparations, materials, placement
Measurement: Actual Quantities shall be measured based on weigh tickets supplied to the ENGINEER as ton(s) of bituminous placed and accepted by the
ENGINEER.
Payment: Payment shall be the product of the Actual Accepted Quantities and
Unit Price bid for “BITUMINOUS REPAIR” in accordance with the “General
COR & BID & BMP 13
25 DEBRIS BARRIER
WALL
This item of work shall consist of furnishing all materials, equipment, and labor necessary to install, maintain, and remove this item as depicted on the
Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the "Barrier- Bale and Plywood" AML Standard Technical
Specification.
Special Considerations: None
Major Incidentals: Materials (including plywood, bales, post, concrete, plastic), placement, maintenance, & complete removal.
Measurement: Actual Quantities shall be measured as the next whole linear foot installed and accepted by the ENGINEER.
Payment: Payment shall be the product of Actual Accepted Quantities and the
Unit Price for “DEBRIS BARRIER WALL” in accordance with the “General constitute full compensation for all labor, materials, equipment, and incidentals
26 CHAIN LINK FENCE This item shall consist of furnishing all materials, equipment, and labor necessary to construct a chain-link safety fence as depicted on the Drawings, AML Standard Details, and as directed by the ENGINEER in accordance with the “Fence” AML Standard Technical Specification.
Special Considerations: None
Measurement: Actual Quantities shall be measured to the next whole linear feet of fence installed and accepted by the ENGINEER.
Payment: Payment shall be the product of Actual Accepted Quantities and the
Unit Price bid for “CHAIN LINK FENCE” in accordance with the “General
COR & BID & BMP 14
Erosion and Sediment Control
Best Management Practices (BMP) Plan
January 2017
COR & BID & BMP 15
OVERVIEW
This Best Management Practices (BMP) plan is a guide for Kentucky Division of Abandoned
Mine Lands (DAML) projects. It contains information regarding preventing, reducing and controlling erosion, sediment, and pollutant runoff from Abandoned Mine Land (AML)
Reclamation and Acid Mine Drainage (AMD) Abatement project construction sites. The information in this BMP will aid DAML staff and contractors in selecting, installing, and maintaining erosion prevention and sediment control measures during the different stages of construction. This BMP plan, in accordance with DAML Technical Specifications and Standard
Drawings, is intended to protect Kentucky’s streams from potential water quality impacts resulting from DAML projects.
This general BMP document is to outline the various pollution prevention measures used on
AML Reclamation or AMD Abatement Projects. The primary sources of pollutants are solids mobilized during storm events and precipitants from mineralized mine drainage. Other sources of pollutants include oil/fuel/grease from servicing and operating construction equipment, concrete washout water, sanitary wastes, and trash/debris.
EROSION PREVENTION AND SEDIMENT CONTROL MEASURES
Plans for Reclamation and AMD abatement construction projects will include erosion control measures on the planview sheets when possible, and will depict Disturbed Drainage Areas
(DDAs) and related information. The construction notes and project description may describe other control measures. The Contractor and Engineer may select an additional BMP for the project as the project changes and construction progresses. Projects that do not have DDAs annotated in the plans will employ the same concepts selecting and implementing this general
BMP plan.
Address disturbed areas or sources of sediments by the most effective means in the specific work area. Direct non-storm water discharges to sediment basins/traps or to a filter fence enclosure in a flat vegetated infiltration area or filtered via another approved commercial product. All deep mine and surface impoundment water will be tested and treated, when as necessary, to meet the
DAML Water-Treatment and Disposal Technical Specification unless stricter limitations are listed in an existing Total Daily Maximum Load (TMDL) limit.
PERMITS
The DAML shall review each project during project development to determine whether any permits are required to implement the project work. When a permit is required, DAML will make every effort to obtain the permit prior to letting the project for bidding. Permit specific conditions shall trump any standard conditions and/or practices. All permits must be maintained onsite and produced when requested by regulatory authorizes inducing representative of the permitting authority.
Common permits types for DAML projects:
COR & BID & BMP 16
• 401 Water Quality Certification (WQC) o Issued by the KY Division of Water
• 402 KY Pollution Discharge Elimination System (KPDES) o DAML activities are covered under the AML KPDES General Permit
• 404 US Army Corps of Engineers (USACE) o Issued by the US Army Corps of Engineers- Nashville District, Louisville District, or Huntington District (Depending upon major drainage basin)
• KY Stream Construction (Floodplain) o Issued by the KY Division of Water
• Local Floodplain Permit o Issued by the County/Municipality
• Local Storm Water Construction o Issued by the County/Municipality
A) Field Review Walk-Thru:
The DAML will conduct a project review between the Project Engineer, Construction Branch
Personnel, Project Design Technician, and Field Office Staff, to review the construction plans and identify any changes needed prior to letting the project for bidding. The group will evaluate the locations and types of site specific BMP and any other erosion prevention and sediment control measures chosen for incorporation into the final design plans.
B) Pre-Bid Conference
DAML will present the project specific BMP and permit requirements/conditions to the potential contractors during the pre-bid conference meeting.
C) Pre-Construction Conference
Prior to the actual beginning of the project, DAML will hold a pre-construction conference between representatives of the DAML, the Contractor, including any Subcontractors, as well as other interested agencies and parties. Items discussed will include the time and sequence for construction, planned methods of operation, payment, and other relevant questions including any permit requirements and the erosion and sediment control plan.
D) Construction Access
This is the first land-disturbing activity. Construction entrances shall be a minimum of twenty
(20) feet wide by fifty (50) feet long, measured from the shoulder of the public road, and consist of No. 2 aggregate over a heavy weight non-woven filter fabric base. As soon as construction begins, stabilize bare areas with gravel and temporary mulch and/or vegetation.
E) Clearing and Grubbing
Use the following techniques for clearing and grubbing activities:
COR & BID & BMP 17
1) Leave areas undisturbed when possible.
2) Construct silt basins to provide silt volume for large areas.
3) Construct Silt Trap(s) Type A for small areas.
4) Construct Type B silt traps for areas with rapid runoff and sediment-laden runoff.
5) All silt traps should have a 3:1 flow length to width ratio. Add spreader bars, baffles, or turbidity curtains to maintain the flow path ratio when site conditions require traps sizes smaller than the standard detail dimensions.
6) Install geotextile bags and/or rock checks in front of existing drop inlets.
7) Construct diversion ditches to catch sheet runoff and carry it to basins or traps or to divert it around areas to be disturbed.
8) Maintain brush and/or other barriers to slow and/or divert runoff.
9) Construct silt fences/hay bales to catch sheet runoff on short slopes. For longer slopes, multiple rows of silt fence/hay bales may be considered.
10) Apply temporarily mulch to area not actively being disturbed or for any area left undisturbed for fourteen (14) days.
11) Employ non-standard or innovative methods.
F) Stream Crossings / Work Along Streams
1) Temporary low-water stream crossings follow the guidelines included in the DAML
Technical Specifications and those established by the KY Division of Water Floodplain
Management Section. Removal of a temporary crossing may be required to accommodate large storm events.
2) Do not completely block stream flow (even temporary). Instead, utilize some form of pass thru mechanism during all AML projects.
3) Work within a stream channel shall not cause flooding of properties upstream, downstream or within the project area or cause downstream water quality degradation. Minimize equipment contact time with the stream water by diverting water around equipment working in or along streams.
4) No flowing water will interact with any uncured concrete placed in the stream channel.
5) Divert all stream water around the work areas in accordance to methods listed in the DAML
Stream Protection & Relocation technical specification, AML Standard Details Section 60, and as by the appropriate permit guidelines.
6) Temporary out of channel stream diversion must use one of the three approved methods:
pipe diversion, sandbag/stone channel diversion, and/or fabric-based channel diversion.
Do not construct any temporarily diverted channel on bare, erodible soil. No temporary diversion shall be permanent without a 401, 404, and other appropriate permits.
COR & BID & BMP 18
G) Deep Mine and Surface Water Impoundments
The DAML Resident Inspector will test the mine water from deep mines and surface impoundments on the project area to determine the pH and total iron content. Treat the water until it meets the DAML Water-Treatment and Disposal Technical Specification or an existing TMDL, whichever is stricter, before release through a silt control structure(s).
Monitoring & Recording
The DAML Inspector will maintain a log of the pH and total iron content results prior to releasing and during each release day. Perform a minimum of two (2) tests downstream each day to ensure the maintenance of water quality during release and is not degrading the receiving stream.
Types of structures/facilities include:
1) Silt Traps Type A (20’L x 5’W x 2’D min dugout)
2) Silt Traps Type B (20’L x 5’W x 2’D min dugout with rock berm)
3) Silt Check - Rock checks with filter fabric core lining installed in channels and in front of pipes
4) Temporary silt control fence with Class II filter berm
5) Sediment collection bags
H) Cut and Fill and Placement of Drainage Structures
Areas at final grade will be seeded and mulched within five (5) days. Soil stock piles and areas that are not at final grade but where construction will cease for a period of fourteen (14) days or longer, shall receive temporary mulch no later than fourteen (14) days from the last construction activity in that area.
Types of structures/facilities include:
1) Silt Traps Type B (20’L x 5’W x 2’D min dugout with rock berm)
2) Silt Checks - Bags in front of pipes after they are placed
3) Channel lining
4) Erosion control blanket
5) Temporary mulch and/or seeding for areas where construction activities will be ceased for
14 days or more
6) Non-standard or innovative methods
I) Temporary Shutdown
Items to be completed prior to shutdown include:
1) Clean out behind, repair or replace silt fence and/or hay bales
2) Clean out all silt traps
COR & BID & BMP 19
3) Apply temporary mulch and track into the soil
4) Sow cover crop (weather permitting)
J) Finish Work
1) Establish permanent seeding and protection
2) Remove non-permanent silt checks from ditches and drains if protected with other BMPs sufficient to control erosion and vegetation is established.
3) Remove non-permanent silt traps and basins.
4) Remove geotextile silt fence.
5) Planting trees and/or shrubs where they are included in the project.
6) Clean out behind, repair, and/or replace bale silt barriers
7) Clean out all permanent silt traps and basins
K) Post-Construction
The Contractor shall assume responsibility for all workmanship and materials for a period of one year from the date of final payment, as directed by the Contract Documents. Any work found to be defective due to failure to comply with the provisions and intent of the Contract Documents shall be corrected at the Contractor's expense. Problems determined not to be created by the landowner or due to the Contractor will be addressed by the DAML for a period of up to three years, pending available funding.
OTHER CONTROL MEASURES
L) Solid Materials
No solid materials, including rock and building materials, shall be discharged into waters of the
U.S. except as authorized by the Clean Water Act (CWA) Section 401 and Section 404 permits.
M) Waste Materials
Collect and store waste materials that may leach pollutants (paint and paint containers, caulk tubes, oil/grease containers, liquids of any kind, soluble materials, etc.) in appropriate covered waste containers. Remove waste containers from the project site frequently as to not allow wastes to become a source of pollution. Instruct all personnel regarding the correct procedure for waste disposal and dispose of wastes in accordance with appropriate regulations.
N) Hazardous Waste
Manage and dispose of hazardous waste materials in the manner specified by local or state regulation. Notify the Resident Inspector if there are any hazardous wastes generated, and provide a plan for the management and disposal of such materials. Instruct site personnel with regard to proper storage and handling of hazardous wastes when required and use the practices to reduce the risks associated with all hazardous materials. Keep products in original containers
COR & BID & BMP 20
unless they are not re-sealable with the original labels and material safety data sheets (MSDS) will be reviewed and retained.
O) Spill Prevention
Use good housekeeping and material management practices to reduce the risk of spills or other exposure of materials and substances to the weather and/or runoff. Manufacturers' recommended methods for spill cleanup will be maintained on site and readily available upon request. Make personnel aware of procedures and the location of the information and cleanup supplies.
Equipment and materials will include as appropriate, brooms, dust pans, mops, rags, gloves, oil absorbents, sand, sawdust, and plastic and metal trash containers.
Clean up all spills immediately after discovery. Keep the spill area well ventilated. Personnel will wear appropriate protective clothing to prevent injury from contract with a hazardous substance. Report spills of toxic or hazardous material to the appropriate state/local agency as required by KRS 224 and applicable federal law. Wastes from spill cleanup will be disposed of in accordance with appropriate regulations. The spill prevention plan will be adjusted, as needed, to prevent spills from reoccurring and improve spill response and cleanup.
P) Petroleum Products
Monitor vehicles and equipment fueled and maintained on site for leaks, and receive regular preventative maintenance to reduce the chance of leakage. Protect petroleum products onsite will be stored in tightly sealed, clearly labeled containers from exposure to weather. The
CONTRACTOR shall not have a total of over 1,300 gallons of petroleum products on site at any given time.
Q) Fertilizers
Store fertilizers in a covered area away from water. Transfer the contents of any partially used bag of fertilizer to a sealable plastic bin to avoid spills. Once applied, work into the soil and apply mulch to limit exposure to storm water.
R) Concrete Truck Washout
Concrete truck mixers and chutes will not be washed on pavement, near storm drain inlets, or within seventy (75) feet of any ditch, stream, wetland, lake, or sinkhole. Where possible, discharge excess concrete and wash water to areas prepared for pouring new concrete, flat areas to be paved that are away from ditches or drainage system features, or other locations that will not drain off site. Where this approach is not possible, excavate a shallow earthen washbasin away from ditches to receive the wash water.
INSPECTIONS
Use inspection and maintenance practices to maintain erosion and sediment controls:
COR & BID & BMP 21
1) The Contractor and DAML Resident Inspector will inspect all erosion prevention and sediment control measures at least once each week and following any rain of 0.1 inch or more.
2) The DAML Resident Inspector will record the silt control inspections by in their daily report.
3) Silt fences/hay bales will be inspected for bypassing, overtopping, undercutting, depth of sediment, tears, and to ensure attachment to secure posts.
4) Inspect silt traps and basins for depth of sediment, and built-up sediment and clean out when it reaches 50% of the design capacity and at the end of the job.
5) Inspect diversion dikes and berms and promptly repaired any breaches. Repair areas that are eroding or scouring and re-seeded / mulched as needed.
6) Inspect temporary and permanent seeding and mulching for bare spots, washouts, and healthy growth. Repair bare or eroded areas as needed.
7) Inspect…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .