This document is an Addendum to an Invitation to Bid (ITB) issued by the Commonwealth of Kentucky Department for Facilities and Support Services Division of Engineering and Contract Administration for Plumbing Upgrades & Repairs at the Christian County Rest Area Westbound I-24 Mile Marker 92 in Christian County, Kentucky. The Addendum provides changes to the specifications and drawings, which will be distributed by Lynn Imaging. It also changes the official bid date to January 30, 2024 at 2:00 P.M. Eastern Time, while the bid reading information will remain the same.
The Demolition Plan included in the Addendum provides details on the project scope, including the removal of the existing slab, excavation of gravel and soil to access underground cast iron waste piping and fittings, and the protection of the HVAC system and building access areas during the construction work. The contractor is also required to provide temporary restrooms and resurface the men's restroom floor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final_RFB_785_2400000333_1_SO_FORM.PDF | ||
| Final_RFB_785_2400000333_2_SO_FORM.PDF |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-148-24
FOR: Plumbing Upgrades & Repairs
Christian County Rest Area Westbound I-24 Mile Marker 92 Kentucky Transportation Cabinet Christian County, Kentucky
DATE: January 24, 2024
RFB-785-2400000333
ADDENDUM NO. One (1)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.
Item 2: Official bid date changed to January 30, 2024 @ 2:00 P.M. Eastern Time; bid reading Information will remain the same.
END OF ADDENDUM
Invitation to Bid No. RFB-148-24 For: Plumbing Upgrades & Repairs
Christian County Rest Area Westbound I-24 Mile Marker 92 Kentucky Transportation Cabinet Christian County, Kentucky
Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration
TRG PSCArchitects - Engineers - Landscape Architects The Roberts Group
239 Southland Drive - Lexington, KY 40503 859-276-2006 - 859-276-2901 Facsimile
EX
PI
RA
TI
ON
/3
0/
ST
ATE OF KENTUCKY
P R
O
FESS I ONA L ENG
I N E
E R
L
I C E N S E
D
A100
1 DEMOLITION PLAN
1/4" = 1'-0"
DEMOLITION PLAN
SHEET KEYED NOTES DEMOLITION:
1. APPROXIMATE EXISTING SLAB INDICATED INSIDE HATCHED AREA TO BE REMOVED.
EXCAVATE GRAVEL, SOIL, ETC. AS REQUIRED TO ALLOW ACCESS TO UNDERGROUND
CAST IRON WASTE PIPING AND FITTINGS TO BE REMOVED. SEE PLUMBING PLANS FOR
MORE INFORMATION. ALL SPOILS ARE TO BE REMOVED FROM SITE.
2. NO WORK IN THIS AREA. AREA SHALL BE PROTECTED FROM DUST AND DEBRIS WITH
POLYETHYLENE PLASTIC BARRIERS FOR THE FULL DURATION OF SLAB REMOVAL AND
GRAVEL BACKFILL.
3. EXISTING PLUMBING FIXTURES TO REMAIN INTACT AND UNDISTURBED WHERE
POSSIBLE.
4. AIR HANDLING UNITS AND EXHAUST FANS SHALL BE SHUTDOWN AND DUCT OPENINGS
SEALED FOR THE DURATION OF SLAB REMOVAL, GRAVEL BACKFILL, OR ANY OTHER
TASK THAT WOULD INTRODUCE DUST AND DEBRIS INTO THE HVAC SYSTEM. FAILURE
TO DO SO WILL RESULT IN DUCTWORK, COILS, FANS, AND AIR HANDLING UNITS BEING
CLEANED AT THE CONTRACTORS EXPENSE.
5. ALL CONSTRUCTION ACCESS SHALL BE THRU THE EMPLOYEE BACKDOOR AVOIDING
THE MAIN LOBBY WHERE POSSIBLE. ROUTE BETWEEN BACKDOOR AND CHASE AREAS
SHALL BE PROTECTED FROM ANY DAMAGE, CONSTRUCTION DUST, AND DEBRIS. IF
DEEMED NECESSARY, ACCESS THRU MAIN LOBBY SHALL BE COORDINATED AND
AGREED TO BY OWNERS PROJECT MANAGER. SAME PROTECTION REQUIREMENTS
WILL APPLY FOR THIS AREA.
6. CONTRACTOR TO PROVIDE TEMPORARY RESTROOMS (2 REGULAR - 2 ADA
OCCUPANCY) FOR THE FULL DURATION OF THE PROJECT UNTIL COMPLETION AS
DETERMINED BY OWNER.
7. CONTRACTOR SHALL GRIND AND RESURFACE BOTH SIDES OF MEN'S RESTROOM
FLOOR ONLY. NEW SURFACE TO MATCH EXISTING COLOR AND DESIGN AS
AUTHORIZED BY DECA AND KYTC PRIOR TO INSTALL. APPROXIMATELY 396FT2 (198 FT2
EACH SIDE) DOOR THRESHOLD TO DOOR THRESHOLD.
GENERAL NOTES:
X
A. REFER TO SHEET P102 FOR SCHEDULES, DETAILS, AND GENERAL NOTES
A1
A1
A1
A1 ADDENDUM 1 - 01/24/2024 MEN'S FLOOR RESURFACING