Addendum One.pdf

PDF 174 KB Posted

Attached to
RFB-158-24 DMA BGS 5B & 5E Loading Dock Repair
Solicitation number
RFB-785-2400000361-2
Issued by
Fayette County, Lexington-Fayette Urban County, Kentucky

About this file

This document is an Addendum to Invitation to Bid No. RFB-158-24 issued by the Commonwealth of Kentucky Department for Facilities and Support Services Division of Engineering and Contract Administration for the Loading Dock Repairs at Buildings 5B & 5E of the Bluegrass Station Department of Military Affairs in Lexington, Kentucky. The addendum includes changes to the specifications and drawings as distributed by Lynn Imaging, with a 90-day substantial completion timeline and 15-day final completion period. The project requires replacing the loading docks one at a time, with one dock to remain open at all times. The bid should include 57's stone in lieu of dense grade aggregate for the drywell, and there is an onsite location available for spoils dumping. The concrete must meet a minimum 4,000 psi requirement, and a construction porta-potty is required for the duration of the project.

The pre-bid meeting questions and responses are also included, which provide additional clarification on project details. No other pricing terms, set asides, incumbent information, funding requirements, or other salient details are provided in this addendum document.

View the file

Other files

File Type Posted
Final_RFB_785_2400000361_2_SO_FORM.PDF PDF
Final_RFB_785_2400000361_1_SO_FORM.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-158-24

FOR: Loading Dock Repairs Buildings 5B & 5E Bluegrass Station Department of Military Affairs Lexington, Kentucky

DATE: February 13, 2024

RFB-785-2400000361

ADDENDUM NO. One (1)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.

END OF ADDENDUM

Invitation to Bid No. RFB-158-24 For: Loading Dock Repairs Buildings 5B & 5E Bluegrass Station Department of Military Affairs Lexington, Kentucky

Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration

YEISER STRUCTURAL 403 MARQUIS AVE. | LEXINGTON, KY |40502

JORDAN@YEISERSTRUCTURAL.com 859-797-5566

February 12, 2024

Questions from pre-bid and site walk meeting are as follows. Response is below in bold.

• Is there a timeline for the project?

o Substantial completion at 90 days and final completion 15 days later per page 104 of the spec book.

• Can both docks be replaced at the same time?

o No, they should be replaced one at a time. One dock shall be open at all times.

• Should the dense grade aggregate shown in the drywell be 57’ stone instead?

o Yes, please include 57’s in the bid in lieu of dense grade aggregate.

• Is there a location on property that could be used to dump spoils?

o Yes, there is a location on site to dump the spoils.

Additional items to note are as follows:

• The concrete shall be a minimum of 4,000 psi

• There shall be a construction porta-potty for the duration of the project.

Best, Jordan Yeiser, PE

RFB-158-24

BGS 5B and 5E Loading Dock Repair

Addendum One
RFB-158-24 - BGS 5B and 5E Loading Dock Repair - Addendum to Pre Bid Meeting Questions

File details come from the government source that posted it. Updated .