This Addendum No. 1 document issued by the California Department of Transportation (Caltrans) pertains to Invitation for Price Quote (IFPQ) 07A6324 for mulch application services in Los Angeles County. The contractor shall provide all labor, equipment, tools, materials, supplies, permits, and incidentals necessary to apply mulch to Caltrans right-of-way areas. The agreement is estimated to commence on May 4, 2026, pending Caltrans approval, and will expire on May 3, 2027. Work shall be performed during normal business hours, Monday through Friday, 6:00 a.m. to 2:30 p.m., excluding State holidays. The contractor must provide three mulch blower trucks with a minimum of two personnel per truck, with each truck required to apply approximately 300 cubic yards of mulch per day as a minimum. Cubic yard quantities per service request will vary by location. Caltrans will provide all traffic control for work performed within the right-of-way, relieving the contractor of this responsibility.

At the time of bid submittal and continuously throughout the agreement term, the bidder must be certified as a small business, micro business (MB), small business for public works (SB-PW), or disabled veteran business enterprise (DVBE) registered with the California Department of General Services. Additionally, the bidder must maintain valid and current registration with the Department of Industrial Relations and possess a current and valid C-27 Landscaping license issued by the Contractors State License Board. The contractor will not receive payment for any work performed prior to Caltrans approval and receipt of notice to proceed from the Caltrans Contract Manager.

View the file

Other files

File Type Posted
Solicitation_Package_07A6324.pdf PDF
Solicitation_Package_07A6319.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

Addendum No. 1 Invitation for Price Quote (IFPQ) 07A6324

Mulch Application Services in Los Angeles County

NOTICE TO ALL PROSPECTIVE BIDDERS:

Addendum No. 1 is being issued for the above-referenced IFPQ. Bids for this work shall be with the full understanding of this Addendum.

The following are questions received and the Department’s responses:

Question 1: What is the typical cubic yard quantity per Service Request?

Answer 1: This can vary by location. Please see changes below.

Question 2: Can you confirm the contractor will not be responsible for providing traffic control for work within the right-of-way.

Answer 2: Yes, Caltrans will do all traffic control. Please refer to IFPQ, Attachment 3, Proposed Form of Agreement, Exhibit A, Item 10.C.

The following are changes to this IFPQ:

1) IFPQ, Attachment 3, Proposed Form of Agreement, Exhibit A, Item 5 has been revised as follows:

6. This Agreement will commence on May 4, 2026 (estimate), or upon approval by Caltrans, whichever is later, and no work shall begin before that time. This Agreement is of no effect unless approved by Caltrans. Contractor shall not receive payment for work performed prior to approval of the Agreement and before receipt of notice to proceed by Caltrans Contract Manager. This Agreement will expire on May 3, 2027 (estimate). The routine services shall be provided during normal business hours Monday through Friday 6:00 a.m. to 2:30 p.m., excluding State holidays.

The parties may amend this Agreement as permitted by law.

2) IFPQ, Attachment 3, Proposed Form of Agreement, Exhibit A, Item 10.D has been added as follows:

D. Contractor shall provide three (3) mulch blower trucks with at least two (2) personnel per truck.

Each truck shall apply approximately 300 cubic yards per day, per truck, at a minimum.

DEPARTMENT OF TRANSPORTATION

ADMINISTRATION

DIVISION OF PROCUREMENT AND CONTRACTS

1727 30th STREET, MS-65

SACRAMENTO, CA

95816

PHONE (916) 227-6000

TTY 711

https://dot.ca.gov/programs/procurement-and- contracts/

March 17, 2026 http://www.dot.ca.gov/dpac/ http://www.dot.ca.gov/dpac/ http://www.dot.ca.gov/dpac/

Page | 2

All other terms and conditions set forth in the IFPQ remain in full force and effect.

Sincerely, JoAnna Nevarez

Contract Analyst

6. This Agreement will commence on May 4, 2026 (estimate), or upon approval by Caltrans, whichever is later, and no work shall begin before that time. This Agreement is of no effect unless approved by Caltrans. Contractor shall not receive payment for...