About this file

This is Addendum No. 1 to an Invitation for Bid (IFB) issued by the California Department of Transportation for roof replacement and gutter repairs at Fort Ross Property in Sonoma County. The project encompasses roof removal and installation work at two residential houses and their detached garages, as well as gutter repairs and metal roof repainting at a Crew Office and Equipment Storage Building, Gas House, and shed. The bid proposal consists of eight line items with lump sum pricing for removal and disposal of existing roofing systems, furnishing and installing new shingle roofs, repairing gutters and downspouts, replacing deteriorated decking up to 500 square feet, and performing unforeseen labor on an hourly basis. The addendum revises the original bid proposal form and updates the scope of work and property photos. Bidders must hold a current and valid C-39 Roofing license issued by the Contractors State License Board, maintain approval from the roofing manufacturer, and possess valid Department of Industrial Relations registration at the time of bid submittal and throughout the contract period.

The approximate budget for this solicitation is $300,000.00. The revised bid proposal requires all line items to be completed; any blank unit price columns will render the bid non-responsive. Unforeseen labor is estimated at 100 hours for each house structure, with a maximum allowable expenditure cap of $10,000.00 for unforeseen parts, materials, and supplies to be reimbursed based on submitted original receipts. The addendum clarifies that contractor-supplied field-applied metal roof coatings must contain a minimum of 70 percent polyvinylidene fluoride, with Sherwin Williams Fluropon identified as an acceptable alternative. The scope of work excludes Title 24 compliance requirements and includes removal of rusty screws from the Equipment Building with confirmation by the Caltrans Contract Manager prior to new paint application.

View the file

Other files

File Type Posted
Solicitation_Package_04A7417.pdf PDF
Addendum_No._1_IFB_04A7426_(Q_A).pdf PDF
Addendum_Three_04A7417.pdf PDF
Addendum_Two_04A7417.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

1727 30th STREET, MS-65

SACRAMENTO, CA

95816

PHONE (916) 227-6000

TTY 711

https://dot.ca.gov/programs/procurement-and- contracts/

February 27, 2026

Addendum No. 1

Invitation for Bid (IFB) 04A7417 Roof Replacement and Gutter Repairs in Sonoma County

NOTICE TO ALL PROSPECTIVE BIDDERS:

Addendum No. 1 is being issued for the above-referenced IFB. Bids for this work shall be with the full understanding of this Addendum.

The following are questions received for this IFB and the department’s responses:

Question 1: What is the budget for this solicitation?

Answer 1: Approximately $300,000.00.

Question 2: We have an A and B license, but our subcontractor has a C-39 license. Can we participate?

Answer 2: Please refer to IFB, Attachment 3, Proposed Form of Agreement, Exhibit E, Item 3.A.

The prime contractor shall have a C-39 license.

Question 3: Does the roof need to meet Title 24 regulations?

Answer 3: No.

Question 4: Will the rusty screws on the Equipment Building need to be removed?

Answer 4: Yes, please see the changes below.

Question 5: Can we park an RV inside the property during construction?

Answer 5: No, but there are campgrounds nearby that may accommodate RVs.

Question 6: What is the time frame for the work?

Answer 6: Please refer to IFB, Attachment 3, Proposed Form of Agreement, Exhibit A, Scope of Work, Item 4.

Question 7: There are several coatings available that could be field applied to metal roofs. Will Caltrans accept other field applied coatings systems for metal roofs?

Answer 7: Contractor may substitute product as long as product contains 70% of polyvinylidene fluoride.

Sherwin Williams Fluropon is an acceptable alternative.

The following are changes to this IFB:

1. IFB, Attachment 1, Bid Proposal has been revised. The new REVISED Bid Proposal must be submitted, or the bid may be deemed nonresponsive.

2. IFB, Attachment 3, Proposed Form of Agreement, Exhibit A, Scope of Work, page 2, has been revised. Please refer to the pages below for the changes in red font.

DEPARTMENT OF TRANSPORTATION

ADMINISTRATION

DIVISION OF PROCUREMENT AND CONTRACTS

http://www.dot.ca.gov/dpac/ http://www.dot.ca.gov/dpac/ http://www.dot.ca.gov/dpac/

Page | 2

3. IFB, Attachment 3, Proposed Form of Agreement, Attachment 3, Photos of Fort Ross Property has been updated and attached below.

All other terms and conditions set forth in the IFB remain in full force and effect.

Sincerely, JoAnna Nevarez

Contract Analyst

STATE OF CALIFORNIA ∙ DEPARTMENT OF TRANSPORTATION Agreement Number 04A7417 BID PROPOSAL Page 1 of 2 ADM-1412 (REV. 9/2025) Attachment 1-REVISED

Contractor’s Name (Please Print):

Item Number

Estimated Quantity

Unit of Measure Item

Unit Price (Price Per

Unit of Measure)

Total (Estimated

Quantity X Unit Price)

1 1 Lump Sum

All labor, equipment, tools, travel, fees, permits, and incidentals necessary to remove and legally dispose of roofing system at House 1, House 1 Garage per STD 213, Exhibit A, Scope of Work.

2 1 Lump Sum

All labor, equipment, tools, travel, fees, permits, and incidentals necessary to remove and legally dispose of roofing system at House 2 and House 2 Garage per STD 213, Exhibit A, Scope of Work.

3 1 Lump Sum

All labor, parts, materials, supplies, equipment, tools, travel, fees, permits, and incidentals necessary to furnish and install roofing system, at House 1 and House 1 Garage per STD 213, Exhibit A, Scope of Work.

4 1 Lump Sum

All labor, parts, materials, supplies, equipment, tools, travel, fees, permits, and incidentals necessary to furnish and install roofing system, at House 2 and House 2 Garage per STD 213, Exhibit A, Scope of Work.

5 1 Lump Sum

All labor, parts, materials, supplies, equipment, tools, travel, fees, permits, and incidentals necessary to repair gutters, downspouts, flashing, and repaint the roof of Crew Office and Equipment Storage building, Gas House and shed per STD 213, Exhibit A, Scope of Work.

6 500 Square feet

All labor, parts, materials, supplies, equipment, tools, travel, fees, permits, and incidentals necessary to remove, furnish and replace up to 500 square feet of deteriorated sheeting or decking per STD 213, Exhibit A, Scope of Work.

7 100 Hour All labor, equipment, tools, travel, fees, permits, and incidentals necessary to perform unforeseen labor for House 1 and House 1 Garage per STD 213, Exhibit A, Scope of Work.

8 100 Hour All labor, equipment, tools, travel, fees, permits, and incidentals necessary to perform unforeseen labor for House 2 and House 2 Garage per STD 213, Exhibit A, Scope of Work.

Subtotal: $

9 Maximum allowable expenditure for unforeseen parts, materials, supplies per Exhibit A, Item 7, shall be $10,000.00 and shall not exceed $10,000.00. Actual cost will be reimbursed based on submitted original receipts. $10,000.00

STATE OF CALIFORNIA ∙ DEPARTMENT OF TRANSPORTATION Agreement Number 04A7417 BID PROPOSAL Page 2 of 2 ADM-1412 (REV. 9/2025) Attachment 1-REVISED

1) The above quantities are estimates only and are given as a basis for comparison of bids. No guarantee is made or implied as to the exact quantity that will be needed.

2) In case of discrepancy between the unit price and the total set forth for a unit basis item, the unit price shall prevail.

3) Do not alter, modify, or change this bid proposal sheet. Any alterations, modifications, or changes to this bid proposal sheet will be grounds to reject the bid.

4) Each line item must be bid. Do not leave any unit price column blank or this bid proposal sheet will be deemed non-responsive.

Total This Proposal (Subtotal + Line 9)

Contractor’s Name TBD Agreement Number 04A7417

Exhibit A

Public Works (State)

(i) For garage, remove and install new shingle above new canopy roof to ensure watertight between canopy and shingle roof.

b) Remove and install new 75 feet of gutter and downspouts in kind

c) Remove and install new related appurtenance (V-T-R and flues)

d) Contractor to carefully remove and reinstall antennae in same location

2) House 2 and House 2 garage – approximately 1,800 SF. Refer to Attachment 3, Photos of Fort Ross Property.

a) Remove and install new shingle roof

b) Remove and install new 100 feet of gutter and downspouts in kind

c) Remove and install new related appurtenance (V-T-R and flues)

d) Carefully remove and reinstall antennae in same location

3) Crew and Equipment Building, Gas House and Shed

a) Repair gutter and downspout damage in kind as shown on Attachment 4, Gutter

Photos.

b) Repair hip flashing and gutter damage in kind as shown on Attachment 4, Gutter

Photos.

c) Clean and prepare metal roof per manufacturer’s recommendation for new paint application using Kynar 500 FSF PVDF or equivalent, (color to match existing). Existing metal roof is approximately 7,500 SF. This area is approximate and shall be field verified by Contractor before the start of work. Refer to Attachment 3, Photos of Fort Ross Property.

d) Remove all rusty screws and replace in kind. Caltrans Contract Manager to confirm removal and replacement prior to applying new paint.

C. Contractor shall carefully remove all existing roofing materials from the roof decking, including flashings, metal edgings, drain leads, pipe boots, and pitch pockets and clean substrate surfaces of all asphalt and adhesive contaminants. Contractor shall bid assuming removal of two (2) layers of existing shingles.

D. Damage caused by Contractor during the roof removal shall be replaced with like material of equal or better quality at Contractor's expense, which shall include the same section depth, lip width, and gauge thickness of the member damaged.

E. Contractor shall confirm quality and condition of existing deck and secure all loose decking and shall remove and replace in kind all deteriorated decking. Contractor shall replace any damaged sheeting or decking, up to 500 SF, prior to new roof installation. Contractor shall only complete more than 500 SF with prior Caltrans Contract Manager approval and will be reimbursed per Item 9 on Attachment 1, Bid Proposal.

F. Contractor shall prepare substrate surface to industry standards.

G. Contactor shall install roof systems per manufacturer’s recommendations and installation guide.

H. Caltrans Contract Manager has sole authority and must approve all components before

House 1 residence and House 1 detached garage.

Attachment 3 Photos of Fort Ross Property

Contractor's Name TBD

House 2

Photos of Fort Ross Property

Contractor's Name TBD

House 2 detached garage (foreground).

Photos of Fort Ross Property

Contractor's Name TBD

Crew Office and Equipment Storage Building

Photos of Fort Ross Property

Contractor's Name TBD

Back of Gas House

Photos of Fort Ross Property

Contractor's Name TBD Agreement Number 04A7417

Gas House and Shed

1Addendum One 04A7417.pdf
04A7417 Addendum One.pdf
add 3 revised bid sheet
Pages from Public Works EXHIBITS 04A7417
Att 3 Photos of Fort Ross Property.pdf
Att 3 Photos of Fort Ross Property.pdf
Pages from 04A7417 - new att 3 Addedum 1 pictures.pdf

File details come from the government source that posted it. Updated .