Addendum No. 2 for the South Fir Street Pedestrian Bridge Improvements project is issued by the Public Works Department of the Town of Telluride, Colorado. The addendum provides critical updates and clarifications for the project, which involves removing and replacing the existing pedestrian bridge decking, handrails, and lighting. Key modifications include specifying that no CDPHE Stormwater Construction Permit is required, revising the crusher fines composition to 25% aggregate base and 75% red crusher fines, and detailing payment terms for the structural steel and utility crossing infrastructure. The project has a final completion date of October 31, 2025, with work to be completed after a single mobilization to minimize impacts to trail and bridge users, and no construction will occur during the Telluride Bluegrass Festival (June 18-20, 2025).

The addendum clarifies several important project details, including bid submission procedures (email to Justin Blair instead of BidNet), utility considerations (811 locate ticket responses are included as Exhibit A), and site access requirements. The staging area will be within the public right-of-way parking area directly north of the bridge, and access to properties on the south side of the river must be maintained at all times. The Town is not aware of any lead paint on the existing bridge structure and notes that repair of concrete spalling on the central pier is not included in the current scope of work but may be considered later depending on budget and needs.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Public Works

1370 W Black Bear Road, PO Box 397

Telluride, CO 81435

Addendum No. 2

South Fir Street Pedestrian Bridge Improvements

Town of Telluride, Colorado

1. Addendum No 1. was not uploaded correctly and therefore does not exist or need to be acknowledged. This Addendum No. 2 shall take serve as the first substantive addendum.

2. Bid Submittal: Public Works will not hold a public bid opening. Do not enter Bid into BidNet and refer to Advertisement and Invitation with respect to emailing Justin Blair (jblair@telluride.gov) your bid.

3. 811 Utilities: For reference only, responses received for Engineering Locate Ticket A436500498 are included at the end of this document as Exhibit A.

4. Clarification for Erosion Control Note #78 (Sheet 4) : A CDPHE Stormwater Construction Permit will not be necessary for this project as the area of disturbance is <1 Acre. Contractor shall submit an erosion control plan for approval as part of the Public Works Excavation Permit (no cost).

5. Delete Utility Note #101 (Sheet 4): no hydronic snow melting systems are known to exist within the project limits.

6. Crusher fines typical section (Sheet 19) shall be modified such that top aggregate layer shall be 25% aggregate base (gravel) with 75% red crusher fines from Benson Brothers (Austin, CO), or other approved equal.

7. Bid Item No. 5- Clean Structural Steel & Utility Crossing Infrastructure shall include protecting existing facilities in place, removal and replacement of insulation for sanitary sewer main, and removal of any abandoned appurtenances (e.g. conduit, hangers, etc.) per direction of the Town. 50% of Lump Sum to be payable upon completion of demolition with the remainder payable after installation of FRP decking.

8. Lead paint: The Town is not aware of any lead paint or coatings on the existing bridge structure or surfaces.

9. Repair of concrete spalling on central pier is not included in the scope of work. The Town may consider this additional work depending on budget, schedule, and needs.

10. Project Schedule: The final completion date of October 31, 2025 is intended to provide flexibility during the spring through fall construction season. However, the intent is for the project to be

Telluride, CO 81435 completed after a single mobilization in order to minimize impacts to trail and bridge users. Work shall not occur during the Telluride Bluegrass Festival (June 18-20, 2025).

11. Staging Area is anticipated within the public right-of-way parking area directly north of the bridge in

S Fir Street and the Town and will be formalized as part of the Public Work Excavation Permit (no cost).

12. Access to properties on the south side of the river must be maintained at all times. When the bridge is closed for construction activities, alternative access is provided via the river trail eastbound towards S Pine St.

Exhibit A: 811 Information for Reference