This document is an Addendum No. 2 issued by Wakely Associates, Inc. for the Brandon School District, specifically for the Brandon Middle School Site Improvements project located in Ortonville, Michigan. The addendum, dated July 26, 2019, relates to site improvements to the baseball field and new dugouts, with the architect's project number 191832. The addendum modifies the original project specifications, focusing on Bid Category 0200 Sitework, which requires the provision of an additional 500 linear feet of new control wiring from the Boiler Room to existing zone control valves, including all necessary wiring, conduits, and connections to complete the system.
No specific pricing details, funding sources, or contract terms are outlined in this addendum. The document appears to be a technical modification to the original project specifications, providing additional technical requirements for the sitework portion of the baseball field improvement project. No drawings are being reissued with this addendum, and the modification is solely focused on the control wiring specification for the mechanical systems.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Info Page for Bid Baseball Fields.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WAKELY ASSOCIATES, INC. ADDENDUM NO. TWO
ARCHITECTS BRANDON SCHOOL DISTRICT
30500 Van Dyke Avenue Suite 209 BRANDON MIDDLE SCHOOL Warren, Michigan 48093 SITE IMPROVEMENTS TO BASEBALL FIELD
AND NEW DUGOUTS
Page 1 of 1 (write up only)
July 26, 2019
ADDENDUM NO. TWO to the plans and specifications for the BRANDON SCHOOL
DISTRICT, BRANDON MIDDLE SCHOOL - SITE IMPROVEMENTS TO BASEBALL
FIELD AND NEW DUGOUTS, Ortonville, MI, Architect’s Project No. 191832 dated June 10, 2019.
The above plans and specifications are modified, supplemented or augmented as follows, and this ADDENDUM NO. TWO, is hereby made a part of the contract documents.
No drawings to be issued with this Addendum.
DRAWING ITEMS:
ITEM NO. A1: Refer to Drawing No. AS1.10 (Not re-issued):
For Bid Category 0200 Sitework:
a. Provide additional 500 linear ft of new control wiring from Boiler Room to existing zone control valves. Provide the necessary wiring, conduits, connections, etc. for a complete system.
END OF ADDENDUM NO. 2
Cc: John Thompson, Brandon School District
| ARCHITECTS BRANDON SCHOOL DISTRICT |
| 30500 Van Dyke Avenue Suite 209 BRANDON MIDDLE SCHOOL |
| Warren, Michigan 48093 SITE IMPROVEMENTS TO BASEBALL FIELD |
| AND NEW DUGOUTS |
| July 26, 2019 |
File details come from the government source that posted it. Updated .