Addendum No. 1.pdf

PDF 224 KB Posted

Attached to
751/17267. BDW-Lexington Harbor BAS-Parking Area Improvements
Solicitation number
RFQ-171-210000000141-2
Issued by
Sanilac County, Michigan

About this file

This is an Addendum No. 1 issued by the Michigan Department of Technology, Management and Budget's State Facilities Administration for the Lexington Harbor BAS Improvements project (File No. 751/17267.BDW). The project involves parking area and launch pavement reconstruction, including pavement removals, grading/excavation, storm drain placements, new concrete walk installation, and placement of a new pit toilet. Additional work includes replacing existing site lighting with new poles and LED fixtures, partial removal and replacement of a gabion wall section, and final restoration including landscape boulder resetting and greenbelt hydroseeding. The bid opening date is February 17, 2021, with work to begin in late Spring 2021 and be completed within 90 calendar days of Notice to Proceed.

The project includes a Provisional Allowance of $40,000 for scope additions or unforeseen circumstances. Bid Alternate 1 covers procurement and installation of a dock extension. The contractor is responsible for all construction layout, permit fees (including LARA for plumbing/electrical and DTMB SESC control), and site security measures. Davis Bacon wages do not apply to this project. The site will be closed during construction, with the contractor responsible for providing barricades to restrict traffic. The pre-bid meeting was held online on February 8, 2021, with attendance from multiple contractors and state agency representatives.

View the file

Other files

File Type Posted
Plans (Part 2).pdf PDF
Specifications.pdf PDF
Plans (Part 1).pdf PDF
DTMB-0415 (Advertisment).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 (Rev 12/17)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

CONSTRUCTION BID ADDENDUM NO. 1

This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

2/12/2021

PROJECT NAME

Lexington Harbor BAS Improvements

FILE NUMBER

751/17267.BDW

PROFESSIONAL

NFE Engineers

PROJECT DIRECTOR

Bruce Watkins, P.E.

BID OPENING DATE:

2/17/2021

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

The pre-bid attendance sheet from on-line meeting held February 8, 2021 is attached. In addition, the pre-bid discussion topics from NFE Engineers is also attached for reference.

Questions and answers posed by contractors during the bid phase:

Does Davis Bacon Wages apply to this project? If they do please send a copy of the Wage Rates. Davis Bacon wages do not apply.

When will this project begin? Intent is to begin as weather allows for site work in the late Spring of 2021.

Construction plan sheet C6 shows a light pole near the outhouse that is also on the existing plan sheets. The electrical site plan sheet E3 does not have this light pole. Please clarify. The civil plans incorrectly show a proposed light pole near the pit toilet. Proposed poles and fixtures are portrayed correctly on the Electrical sheets.

Will the temporary chain link fencing be required around the entire site or will Class III barriers on the roadway be sufficient to keep out the public? Fencing to surround the site is not required; Barriers at the roadway will be permitted, but the Contractor may have to employ additional measures as they deem necessary, to safely secure the site.

Please clarify which posts to use for signage. Site plan shows wood posts, square tube and u channel. Wood post detail is not needed.

All signposts shall be as shown on the ADA Parking Signage Detail (10’x1.75” square galvanized steel post) Will the site be completely shutdown to outside traffic or will we have to maintain access onto the site? The site will be closed during construction. Contractor will be responsible for providing barricades to restrict traffic.

How deep will the owner supplied tank and pit be? The standard DNR tank is 72”x96”x60” deep.

ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.

Steve Sutton

PROFESSIONAL: DATE: 2/11/2021

APPROVED BY:

PROJECT DIRECTOR: Bruce Watkins

DMB-441 (R 4/10)

PRE-BID MEETING ATTENDANCE RECORD

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

Facilities Administration

PROJECT DESCRIPTION/LOCATION

Lexington Harbor BAS Improvements

DATE

February 8, 2021

INDEX NUMBER

FILE NUMBER

751/17267.BDW

CONTRACT NUMBER

Y

TIME

3:00 PM

MEETING PLACE

ONLINE ONLY

PAGE _1___ OF __ ___

PLEASE PRINT YOUR NAME

FIRM YOU REPRESENT

TELEPHONE NUMBER

EMAIL ADDRESS

Bruce Watkins

DTMB- State of Michigan

517-242-7882 (M) watkinsb1@michigan.gov

Mark Sine

DNR-PRD - Lakeport SP

810-327-6224 sinem@michigan.gov

John Terpstra

DNR-PRD

313-396-6864 terpstraj@michigan.gov

Steve Sutton

Nowak & Fraus Engineers

248-635-6571 swsutton@nfe-engr.com

Dean Barr

DTMB-State of Michigan

517-403-9099 barrd@michigan.gov

Jordan Byelich

DNR-PRD

517-284-6087 byelichj@michigan.gov

Steve Reed

Genoa Contracting

586-224-7844 genoacontracting@gmail.com

Courtney Gary

MKC Group

989-439-1767 cgary@mkcmi.com

Jodi Wendorf

Astec Aspahlt

810-346-2092 info@astecasphalt.com

Brian Umphrey

LJ Construction

989-761-0131 ljconstructionmi@gmail.com

Jake Dam

Boddy Construction

810-364-9560 jaked@boddyconstruction.com

Tracie Szczepanek

STE Group

586-468-1135

Tracies1972@att.net

Mike Gaffke qdv Construction

989-414-0274 qdvconstruction@gmail.com

Scott Dickerson

TGPriehs

810-272-6224 scott@priehspaving.com

DMB-441 (R 4/10)

PRE-BID MEETING ATTENDANCE RECORD

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

Facilities Administration

PROJECT DESCRIPTION/LOCATION

Lexington Harbor BAS Improvements

DATE

February 8, 2021

INDEX NUMBER

FILE NUMBER

751/17267.BDW

CONTRACT NUMBER

Y

TIME

3:00 PM

MEETING PLACE

ONLINE ONLY

PAGE _1___ OF __ ___

PLEASE PRINT YOUR NAME

FIRM YOU REPRESENT

TELEPHONE NUMBER

EMAIL ADDRESS

Bruce Watkins

DTMB- State of Michigan

517-242-7882 (M) watkinsb1@michigan.gov

Ellen Englund

Fisher Contracting

989-488-8710 eenglund@thefisher.co

Lexington Harbor BAS Improvements

Pre- Bid Meeting Discussion Topics:

General Scope o Parking area and launch pavement reconstruction, including pavement removals, grading / excavation, storm drain placements to aid in stormwater management, installation of new concrete walk to aid in pedestrian movements and placement of a new pit toilet.

o Work also includes the removal of existing site lighting and replacement with new poles and LED fixtures.

o Work includes the partial removal and replacement of a gabion wall section to allow for parking and drive expansion.

o Final restoration includes resetting of existing landscape boulders, installation of a small section of chain link fence and greenbelt hydroseeding.

Permits / Alternates / Contingencies o Contractor will be responsible to finalize all paperwork and pay all fees associated with each of the permits and inspection fees. Anticipated permits include LARA for plumbing and electrical, and DTMB SESC control.

o Provisional Allowance of $40,000 included for any scope additions or unforeseen circumstances.

o Bid alternates 1 includes the procurement and installation of a dock extension. Drawings are in the construction plans that show the general requirements. Contractor would be responsible to coordinate with the supplier, submit a fabrication drawing for approval and obtain / install the extension.

Miscellaneous o The contractor is responsible for providing all project related construction layout. The owner will provide all project related material testing.

o All work to be completed within 90 Calendar Days of NTP. NTP to coincide with contract approval and mutually agreed to starting date once weather accommodates work this Spring.

o Addenda #1 will be published with attendance list, and any bidder questions.

o Bidder questions due in writing to swsutton@nfe-engr.com by February 11th at 12:00PM

(noon).