About this file
This document is Addendum No. 1 to a Request for Quotation (RFx) issued by the Virginia Department of Wildlife Resources (DWR). The addendum provides responses to questions raised during the mandatory pre-bid conference held on January 8, 2024, for the contract with RFx number QQ:55429. The scope of work includes site preparation, seeding, and road maintenance for several units ranging from 1 to 10 acres in size, located at varying distances from a nearby pond and road. The addendum extends the solicitation close date to January 15, 2024, at 4:00 PM Eastern. Bidders must acknowledge the addendum by submitting a signed copy with their bid.
The addendum specifies the use of paper-based mulch for hydroseeding and that DWR will provide the native warm-season grass and forb seed mix. It also clarifies that the contractor is responsible for providing all materials and labor to fix any damaged roads, and that a disk or culpacker cannot be used to firm the planting sites due to the presence of rocks on-site. Bidders are advised to consult the provided YouTube videos for instructions on submitting their bids through the eVA platform.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Cheney Creek Wildlife Habitat Project.pdf | ||
| Notice of Award | — | |
| Bid tab | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 1 TO ALL BIDDERS
1/10/2024
RFx: QQ:55429
The following ques�ons and answers are provided from the Mandatory Pre-Bid conference that was hosted on January 8, 2024:
1. How far is it from the pond to the road and the pond to the units?
(These values were obtained via GIS and are es�mates) Approximately 160 � to the road Approximately 1,837 � to unit H, 1,928 � to unit G, 5,326 � to unit R, 6,176 � to unit J, 6,841 � to unit N, 8,269 � to unit L and 7,002 � to unit K.
2. How many acres are there in each unit?
G = 1 acre, H=5 acres, R=1 acre, J=10 acres, K=3 acres, N=1 acre, M=1 acre/1,190 �, L= 7 acres.
3. What type of mulch should be used in the hydroseeder?
Paper based mulch
4. What seed mix is going to be used?
DWR will provide the contractor with a na�ve warm season grass and forb seed mix to plant.
5. How o�en does the road need to be fixed if it is damaged?
As soon as possible within reason. If the damage is major it needs to be fixed as soon as possible, if it is minimal, it may be fixed prior to finishing the contract. The contractor should consult with DWR on a case-by-case basis.
6. Is the use of gravel to fix the road considered in the solicita�on?
It is the responsibility of the contractor to provide all materials and labor to fix damaged roads.
7. Can I use a disk or cul�packer to firm the plan�ng sites instead of the dozer tracks?
No, a disk or cul�packer will be damaged by the rocks on site.
8. How do I submit my company’s bid in eVa?
Vendors can go to the following link for instruc�ons on how to submit their bid in eVA. If there are any other ques�ons bidders should contact eVA Customer Care at 866-289-7367.
htps://www.youtube.com/watch?v=KSxcAkOekW0 https://www.youtube.com/watch?v=KSxcAkOekW0
This quick quote Scope of Work is is hereby changed as follows:
Please add the following to the treatment specifica�ons:
12. Please change number 12 to say the following: The contractor can obtain water for hydroseeding from the exis�ng pond and/or stream onsite.
13. The contractor shall remove the overhanging vegeta�on along the main gas road to get equipment and vehicles in and out of the site safely.
The solicita�on close date is extended un�l Monday, January 15, 2024 at 4:00PM Eastern.
Thanks, Stephanie Adams
Stephanie Adams Procurement Manager Stephanie.adams@dwr.virginia.gov
Bidders are required to acknowledge this Addendum by submi�ng a signed copy with their bid submission.
Signature
Name
Title
Date mailto:Stephanie.adams@dwr.virginia.gov