Addendum No. 1.pdf
PDF 66 KB Posted
- Solicitation number
- 27-0674
- Issued by
- Washakie County, Wyoming
About this file
This is Addendum No. 1 to a Request for Bids (RFB #27-0674) issued by the Wyoming State Construction Department for roof replacements at Wyoming Boys School. The addendum extends the bid submission due date from August 31, 2026, to September 14, 2026, at 1:00 p.m. Mountain Time, with bids submitted through Public Purchase. The project encompasses removal of all existing single-ply membrane roofing on four dormitory buildings and a portion of the maintenance building at Wyoming Boys School in Worland, Washakie County, with deck repairs as needed and furnishing and installation of all roofing materials, flashing, and trims. The approximate total roof area is 455 squares, and the estimated work commencement is October 1, 2026, with project completion targeted for September 30, 2027. The tentative contract award date is September 30, 2026. The bid due date extension was necessitated by recent core cut investigations that revealed all existing roofs contain two full roofing systems in place, requiring full removal to the decks before reroofing; modifications to plans and specifications addressing this finding will be provided in a subsequent addendum.
Bidders must submit a bid deposit equal to 10% of the total bid amount in the form of a bid bond, cashier's check, or certified check, and the successful bidder must furnish a Performance and Payment Bond equal to 100% of the accepted bid amount within 20 days of award notification, with costs included in the bid amount. Wyoming resident bidders receive a 5% preference if their bid is not more than 5% higher than the lowest non-resident bid, and successful resident bidders may not subcontract more than 30% of the work to non-resident contractors. Projects valued at $1 million or more qualify for a 1% reduction in bid evaluation if bidders commit to at least 10% apprentice labor hours. Wyoming Prevailing Wage Act requirements apply to this project. Bidders must acknowledge receipt of Addendum No. 1 on the Bid Form and accept responsibility for forwarding pertinent information to suppliers and subcontractors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Notice-Wyoming Boys School Roof Replacements - State Construction Department.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE of WYOMING, State Construction Department
ADDENDUM NO. 1
Project: WY Boys School Roof Replacements
RFB #27-0674
Date: August 18, 2026
Owner: State Construction Department
State Project Representative: Chris Pollock/Project Manager
(307) 777-8682
Except as described below, the original bid documents remain unchanged. The bid documents are modified, clarified and/or amended as follows:
1. This Addendum #1 is only extending the bid submission due date. No other terms of the original bid documents are being revised.
Bid submission due date is 1:00 p.m. on September 14, 2026, submitted on Public Purchase.
The bid due date is being extended due to the need to modify bid documents to reflect information revealed during recent core cut investigations of the existing roofs. It appears that all the roofs currently have two full roofing systems in place so full removal to the decks will be required before reroofing. Modifications to plans and specifications will be addressed in a subsequent addendum.
Note: This Addendum is considered part of the Contract Documents for this project, and where the provisions of the following differ from those of the original, this addendum shall take precedence. Bidders shall acknowledge receipt of this addendum on the Bid Form and therefore accept responsibility for forwarding pertinent information to suppliers and subcontractors.
End of Addendum No. 1
Addendum No. 1 to RFB #27-0674
File details come from the government source that posted it. Updated .