This document is an Addendum No. 1 to a solicitation by the Florida Department of Environmental Protection (DEP) for Airborne Thermography Services, specifically a Northwest Florida Coastal Thermography Survey. The project involves conducting an airborne thermal data survey over Project Area A, which covers approximately 562 square miles along the coastline from Summercamp Road and Highway 98 in Franklin County to 2 miles east of the Econfina River in Taylor County. The survey is intended to identify and inventory artesian springs, with data collection to be performed between January 1 and February 28, 2026, prioritizing coastline flight paths. The contractor will use thermal sensors to collect high-resolution (1-meter or better) thermal imagery during the coldest days and lowest tides, with specific requirements for cloud-free conditions and temperature/tide parameters.

The solicitation includes detailed specifications for data collection, including temperature range expectations (0-100 degrees Fahrenheit), with artesian springs typically around 68-72 degrees Fahrenheit. The contractor is responsible for securing all necessary access permissions, providing daily flight logs, and delivering final data by May 1, 2026. Financial consequences are outlined for non-compliance, including potential invoice reductions for missed deadlines or incomplete documentation. The document also mentions a potential supplemental survey for Area B (approximately 103 square miles) pending funding availability, to be compensated at a fixed price. The Department of Environmental Protection will provide project management support, including issuing notices to proceed and deploying background field instrumentation prior to the contractor's data collection efforts.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP Solicitation No. 2026004 Addendum No. 1 Page 1 of 6

ADDENDUM No. 1

FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION

DEP Procurement Section

3800 Commonwealth Boulevard, MS#93 Tallahassee, Florida 32399-3000

October 20, 2025

Addendum To: DEP Solicitation No. 2026004, entitled “Airborne Thermography Services”

The Department hereby answers questions posed by prospective Vendors. This addendum does not need to be returned with the response.

Question Number

Solicitation Section

Solicitation Page

Number Question / Answer

1.

The RFP provides only limited information on the sensor class requirements. Galileo owns and operates a LWIR frame camera with a spectral range of 7.5µm to 14µm, delivering relative apparent temperature in degrees Celsius. We want to ensure this class of thermal sensor is appropriate for this RFP. Please provide specific sensor band-range specifications for this RFP.

Please see revised scope of work below.

2.

There is no specification listed for spatial resolution of the thermal imagery. This specification largely determines flight planning, cost, and complexity so it is essential for factoring in for planning purposes. What is the target spatial resolution of the thermal imagery? A typical operation scenario for Galileo Thermal system is 50cm per pixel GSD flying at 2600ft AGL.

See answer to question number 1.

3.

Can the thermal imagery be flown at any time of the day or night so long as the imagery is cloud free?

See answer to question number 1.

4.

The RFP does not list specific deliverables for the thermal imagery. A typical deliverable would be a geo-rectified mosaic of the entire study area in GeoTiff or similar format. Please provide specific imagery deliverable requirements.

See answer to question number 1.

Addendum No. 1 Page 2 of 6

Question Number

Solicitation Section

Solicitation Page

Number Question / Answer

5.

As a sensor class alternative , we also operate hyperspectral line scanners that operate in the VNIR (400 to 1000nm) and the SWIR (1000 to 2500nm). However, these systems rely on reflected sunlight rather than thermal (emissive) radiation. Assuming we meet spatial requirements per question two above, would either of these sensor classes be an acceptable alternative?

See answer to question number 1.

6.

As a further collection modality alternative, the RFP specifically lists “airborne” thermography services” but there are multiple satellite options that can provide thermal imagery. Are equivalent satellite-based approaches applicable?

See answer to question number 1.

– Remainder of Page Intentionally Left Blank –

Addendum No. 1 Page 3 of 6

In accordance with Section 2.6, Addenda/Amendments to the RFP, the Department hereby formally amends the Solicitation. The amendments are indicated in blue with strikethrough for deletions and underlines for additions.

4 Scope of Work

4.1 Scope of Work

The Contractor shall provide Airborne Thermal Data over Project Area A (approx. 562 square miles) see (See Exhibit J - Airborne Thermal Data Map)

The Contractor will select sensor(s)/instrument(s) appropriate for conducting the airborne thermographic survey which is intended to identify and inventory artesian springs within the project area (See section 1.2 of the RFP).

The Contractor will maximize sensor/instrument capabilities thus producing the best possible survey results based on temperatures and tides. Sensor/Instrument selection and flight scheduling should be based on the following criteria.

Data collection should be conducted 1) without cloud interference, 2) during forecasted temperature minimums on the coldest days and during the coldest times (using forecasted cold fronts during January-February and in the hours between 12:00 AM-7:00 AM), and 3) during negative or low tide(s) (preferably during a spring tide). Tides are especially important along the coast and in rivers that are tidally influenced.

The acquired data will have a one (1)-meter or better resolution and will have four (4)-meter or better accuracy. Data should be tiled and delivered using an alphanumeric scheme and include a gridded reference map. Data should include temperature field data reported in either Celsius or Fahrenheit for each pixel.

The Contractor is responsible for data processing and delivery. The Contractor will be responsible for reporting metadata associated with the data deliverable which will include aircraft, sensor/instrument specific documentation. The anticipated temperature range to be encountered is between 0-100 degrees Fahrenheit. For reference, artesian springs in Florida are consistently around 68-72 degrees Fahrenheit, average temperatures in the Gulf are around 61 degrees Fahrenheit in January and February, ground temperatures will vary based on sun, weather, and infrastructure.

The Contractor shall:

1. Meet any infrastructure needs to complete the services. This includes ensuring the availability of road/boat ramp/waterbody/air space access, access to electricity or water, appropriately sized and situated area for performing services, and any other infrastructure required (i.e. permits) by the Contractor.

2. Secure all necessary access permissions to conduct flights throughout the Project Study Area and will supply copies to the Department Project Manager, and is required to have all appropriate local, state, and federal licenses and/or training required to operate the aircraft. The Contractor is expected to comply with all local, state, and federal laws including but not limited to Chapters 329, 330 and Section 934.50(4)(l), Florida Statues, as applicable. Copies of executed permits and permissions or documentation of exemption will be presented to the Department Project Manager before work is conducted.

3. Notify the Department’s Project Manager of all scheduled flights and data collection so that the Department can deploy instruments for duplicate background data collection. The window of time will be determined based on air and water temperatures; coldest temperatures being the target days and during negative tides so that groundwater discharge points are most defined. If data collection cannot be completed in the first collection period, the contractor will propose an estimate for a subsequent collection window.

4. Complete data collection within the coldest months of the year (no sooner than January 1 or later than February 28) 2026. Coastline flight paths will be prioritized. The Contractor will supply daily field logs recorded during the

Addendum No. 1 Page 4 of 6 completion of data collection. Daily logs will include flight times, area, manifest, and weather conditions during data collection. The Contractor will deliver daily logs at the end of each week of data collection. The Contractor will deliver all data deliverables for Department review no later than May 1, 2026. (Service).

4.2 Definitions

In this Contract, the following terms shall be defined as set forth below:

Aircraft: Airplane or Drone.

Airborne Thermal Data: Thermal data representative of land and water surface temperatures at the time of data collection.

Access Agreements: Any permit required by local, state, and federal laws and regulations.

Daily Logs: A log of daily flight activities to include flight times, flight area, flight manifest, and weather conditions during data collection.

Data Collection: Collection of thermal data.

Department Contract Manager: The Department Contract Manager will be responsible for receiving invoices and submitting payment once approval is received by the Department Project Manager.

Department Project Manager: The Department Project Manager will be responsible for receiving final deliverables and supporting documentation for each task from the Contractor. The Department Project Manager will be responsible for interfacing with the Department Contract Manager regarding progress updates and scheduling payments.

Groundwater Discharge: Water flows from underground aquifers to the Earth's surface.

Instrument: A tool used for observation and measurement.

Low Tide: Water level is at its lowest point, representing the trough of the tidal wave.

Negative Tide: Water level at low tide drops below the average low tide level for a specific area.

Project Area: The project area is defined by the map provided in Exhibit J. The project area extends along the coastline from the intersection of Summercamp Road and Highway 98 (Franklin County) to approximately 2 miles east of the Econfina River (Taylor County). The coastline coverage extends from 0.5 miles offshore to approximately 2.5 miles onshore. The river areas include coverage of the Aucilla, Wacissa (and Bailey Mill Creek), St. Marks, and Wakulla (and McBride up through Munson). River area coverage encompasses the river and an additional 1.5 miles on both sides of the feature. A second area delineated within the project area includes portions of central Leon and Wakulla counties, extending South from Tallahassee Airport to Highway 98.

Sensor: A device that detects and responds to a physical stimulus from the environment.

Spring Tide: Tidal phenomenon that occurs when the Earth, Moon, and Sun align (new or full moon).

Thermal Data/Thermography: refers to a survey technique, utilizing infrared cameras to detect and visualize temperature variations on the surface of objects.

Addendum No. 1 Page 5 of 6

4.3 Contractor Responsibilities

a. Deliverable. The Contractor shall provide the following deliverable including all component tasks:

Deliverable Task(s) Performance Standards

Supporting Documentation

Financial Consequence(s)

Northwest Florida Coastal Thermography Survey

a. Access Agreements:

Acquire all necessary approval/permissions to conduct flights within the survey area.

a. Approvals and permissions must be secured by December 31, 2025.

a. Provide copies of supporting documentation to the Project Manager.

a. Reduction of final invoice $50.00/day if approvals and permissions are not secured by December 31, 2025.

b. Notify Department’s Project Manager of flight schedule.

b. Provide notification fourteen (14) days in advance of scheduled flights.

b. Provide schedule, manifest, and itinerary.

b. Reduction of final invoice $50.00/day if notification of scheduled flights are not provided fourteen (14) days in advance of scheduled flights

c. Complete data collection.

Daily Log of site activities, estimated percentage complete, weather conditions, and listing of personnel.

c. Flights and data collection will be conducted on coldest days and lowest tides as determined by the Department’s Contract Manager or Project Manager.

Delivered on time and accurate.

c. Daily log will be delivered every Friday by close- of-business during weeks when data collection occurs. Final data deliverable will be delivered by May 1, 2026.

Reduction of final invoice $100.00/day if daily log is not delivered by May 1, 2026.

d. Services and Deliverables.

d. Data is provided in the resolution (or better) agreed upon. All data is delivered in a timely fashion.

d. Completion report, daily logs, data delivery.

d. Reduction of final invoice $50.00/day if daily logs, data delivery is not completed by May 31, 2026.

Addendum No. 1 Page 6 of 6

4.4 Supplemental Services

Additional Survey: The Contractor may be required to conduct an additional survey for Area B (approx. 103 square miles) (See Exhibit J - Airborne Thermal Data Map) based on funding availability as requested by a duly authorized representative of the Department. Payment for this service shall be based on a fixed price.

4.5 Department’s Responsibilities

The Department will be responsible for the following.

1. The Department (DEP Project Manager) will confirm receipt of all access permissions and permits;

2. The Department (Project Manager) will issue a notice to proceed;

3. The Department (Project Manager) will issue a Notice to Proceed to the Contractor; After the Department’s

Project Manager notifies the Contractor, the Contractor will schedule flights and notify the Department’s Project Manager. The Department’s Project Manager will deploy background field instrumentation prior to the Contractor’s flights/data collection efforts.

4. The Contractor will deliver all data to the Department Project manager.

4.6 Enforcement

Noncompliance with the Terms and Conditions of the SOW will result in:

1. Delayed payment until a satisfactory record of the specified documentation of data collection and processing is complete and has been submitted along with the invoice according to this SOW.

2. Nonpayment for work that does not meet the Terms and Conditions in the Contract.

If the Department’s review confirms that data collection and processing is complete, the Contractor will submit an invoice to the Department’s Contract Manager within thirty (30) business days upon receipt of approval from the Department’s Project Manager. The Contractor shall also include a copy of all costs and charges incurred with the invoice.

ADDENDUM No. 1
Addendum To: DEP Solicitation No. 2026004, entitled
“Airborne Thermography Services”
4 Scope of Work
4.1 Scope of Work
4.2 Definitions
4.3 Contractor Responsibilities
4.4 Supplemental Services
4.5 Department’s Responsibilities
4.6 Enforcement