Addendum No 2.pdf

PDF 144 KB Posted

Attached to
RFB-81-26 DMA - WFRTC Cypress Creek Restoration Phase III
Solicitation number
RFB-785-2600000130-3
Issued by
Grant County, Kentucky

About this file

This document is an Addendum (No. Two) to an Invitation to Bid (RFB-81-26) issued by the Commonwealth of Kentucky's Department for Facilities and Support Services, Division of Engineering and Contract Administration for the Cypress Creek Restoration - Phase III project at the Wendell H Ford Regional Training Center in Greenville, Kentucky. The addendum provides clarifications and responses to contractor questions regarding electronic drawing files, material quantities, small woody debris installation locations, and aerial herbicide treatment areas.

Key clarifications include: electronic drawing files will be provided after project award with alignment files in DWG format, though surface grading files are not guaranteed; no specific material quantities will be provided; small woody debris installation is limited to areas between "step style" structures on drawings 11 and 24, specifically between downstream structure pools and the next grade control structure; and aerial herbicide treatment will cover all 8 project phases, regardless of alternate bid status. The addendum directs bidders to refer to Lynn Imaging for additional specification and drawing changes, and emphasizes that bid documents take precedence over any electronic files.

View the file

Other files

File Type Posted
Addendum No 1.pdf PDF
Final_RFB_785_2600000130_1_SO_FORM.PDF PDF
Final_RFB_785_2600000130_3_SO_FORM.PDF PDF
Final_RFB_785_2600000130_2_SO_FORM.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-81-26

FOR: Cypress Creek Restoration - Phase III DMA - Wendell H Ford Regional Training Center Greenville, Kentucky

DATE: September 23, 2025

RFB-785-2600000130

ADDENDUM NO. Two (2)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.

END OF ADDENDUM

Invitation to Bid No. RFB-81-26 For: Cypress Creek Restoration - Phase III DMA - Wendell H Ford Regional Training Center Greenville, Kentucky

Kristi Sharp, Statewide Procurement Manager Division of Engineering and Contract Administration

Cypress Creek Phase III – Addendum 2

• Questions:

• Are CAD files available for the grading plan?

o Electronic Drawing Files

Electronic Drawing Files shall be provided at the request of Contractor after award of project. Alignment files will be provided in DWG format. Surface Grading files are not guaranteed to be available. If surface files are provided, they will be for reference only and to be used at the sole discretion of the Contractor. Surface files are not guaranteed to be a specific format, but expected format is DWG. Bid Documents shall take precedence over any electronic files.

• Can you provide the planned quantities for materials?

o Quantities are not provided.

• A Small Woody Debris installation is indicated on drawings 11 and 24. The callout text on drawing 24 states Between Structures. Does this installation start at 600+12.21 and continue to 600+68.47? Also, are there any other locations that require small woody debris installation?

o Small woody debris are between “step style” structures. This includes log steps, but not riffles. Refer to Detail 11/DO-3. The small woody debris complex begin at the downstream of the structure pool and continues until the next grade control structure. Drawings 11 and 24 are the only locations of the small woody debris complex.

• Should the Aerial Herbicide location that covers the Add Alt for Tributary 2-11 be included in the Add Alt pricing or the base lump sum pricing?

o Please refer to Drawing 04, LI-01. The Aerial Herbicide locations include all 8 phases. All 8 phases will be treated as part of this contract, regardless of Add Alt.

Addendum No 2.pdf
Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.
END OF ADDENDUM

Cypress Creek Phase III-Addendum 2.pdf