This document is an Addendum No. 1 to the contract documents and specifications for the Pine Park Road, et al. Roadway Resurfacing Phase 3 project in Grady County, Georgia. The bid opening date and time have been changed to Tuesday, April 9, 2024, at 2:15 PM. Additionally, some of the bid form quantities have been revised, and bidders are instructed to disregard the original bid form on yellow paper and use the new, revised bid form on blue paper. The remaining specifications on yellow paper shall still be submitted as part of the bid package.
The Pine Park Road, et al. Roadway Resurfacing Phase 3 project involves furnishing labor, materials, and equipment to construct the proposed roadway resurfacing work, which includes widening and resurfacing 1.97 miles of Pine Park Road and 2.26 miles of Singletary Road. The project has a 90 consecutive calendar day construction schedule and will be awarded in one contract. Bid documents can be obtained from the engineer's office upon payment of a $300 non-refundable fee. Bids must be accompanied by a 10% bid bond, and the successful bidder will be required to furnish a 100% performance bond and payment bond.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00111 _ Pine Park Road Advertisement for Bids.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T: 229.388.8823 | 1606 Whiddon Mill Road, Tifton, GA 31793 | WWW.WATKINSENG.COM
ADDENDUM NO. 1
CONTRACT DOCUMENTS & SPECIFICATIONS
March 26, 2024
PROJECT: Pine Park Road, et al. Roadway Resurfacing Phase 3
W&A Project No.: W0744-049-01
OWNER: Grady County Board of Commissioners
BID DATE: Thursday, March 28, 2024, at 11:30 AM
Tuesday, April 9, 2024, at 2:15 PM
1. CONTRACT DOCUMENTS – Section 00111 – Advertisement for Bids:
The Bid Opening Date and Time has been changed to Tuesday, April 9, 2024, at 2:15 PM.
2. CONTRACT DOCUMENTS: Section 00410 – Bid Form:
Some of the Bid Form quantities have changed. Please disregard the Bid Form on Yellow paper and utilize the new, revised Bid Form printed on Blue paper. The remaining Specifications printed on Yellow paper shall still be submitted as part of the Bid Package.
END ADDENDUM NO. 1