This document is an Addendum (No. 4) to an Invitation to Bid (RFB-23-26) issued by the Commonwealth of Kentucky's Department for Facilities and Support Services, Division of Engineering and Contract Administration, for Sewer Upgrades Phase 3 at the Wastewater Treatment Plant located at Carter Caves State Resort Park in Olive Hill, Kentucky. The official bid date has been moved to September 17, 2025, at 1:30 P.M. Eastern Time, with additional specifications and clarifications provided for potential bidders. The addendum includes detailed responses to two key questions from prospective submitters regarding temporary chlorine line requirements and excavation expectations.

The addendum specifies that contractors cannot impact the Wastewater Treatment Plant (WWTP) in a way that would cause a KPDES permit violation and must provide alternative disinfection methods if normal operations are interrupted. Regarding excavation, the owner will not provide an allowance for rock removal or unsuitable soils, instead directing bidders to consult the Geotechnical Report in Appendix A for risk assessment. The project involves specific technical considerations for chlorine dosing lines, disinfection methods, and site-specific excavation challenges, with an emphasis on contractor flexibility and coordination with park staff.

View the file

Other files

File Type Posted
Addendum Three .pdf PDF
Final_RFB_785_2600000038_3_SO_FORM.PDF PDF
Final_RFB_785_2600000038_5_SO_FORM.PDF PDF
Addendum Two .pdf PDF
Final_RFB_785_2600000038_1_SO_FORM.PDF PDF
Final_RFB_785_2600000038_4_SO_FORM.PDF PDF
Final_RFB_785_2600000038_2_SO_FORM.PDF PDF
Addendum One .pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-23-26

FOR: Re-Ad of RFB-255-25 Sewer Upgrades Phase 3 Wastewater Treatment Plant Carter Caves State Resort Park Olive Hill, Kentucky

DATE: September 10, 2025

RFB-785-2600000038

ADDENDUM NO. Four (4)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.

Item 2: Official Bid Date has been moved to September 17, 2025, at 1:30 P.M. Eastern Time

END OF ADDENDUM

Invitation to Bid No. RFB-23-26 For: Re-Ad of RFB-255-25 Sewer Upgrades Phase 3 Wastewater Treatment Plant Carter Caves State Resort Park Olive Hill, Kentucky

Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration

DECA Account No. 670-CBAX-CC21-00 Page 1

GRW Project No. 4803-04

ADDENDUM NO. 4

INVITATION TO BID # RFB-23-26 FOR: RE-AD OF RFB-255-25

CONTRACT DOCUMENTS

PARKS – CARTER CAVES SRP (CC) – SEWER UPGRADES PHASE 3

WASTEWATER TREATMENT PLANT IMPROVEMENTS

DECA ACCOUNT NO. 670-CBAX-CC21-00

GRW PROJECT NO. 4803-04

September 9, 2025

TO ALL PROSPECTIVE SUBMITTERS:

Be advised that the following clarifications and modifications are to be included in the above referenced Project:

Questions Answers

1. What type of material and size is required for the temporary chlorine line? Does the temporary line need to be buried? If so, is there a detail on how to connect to the existing effluent structure?

The Contractor cannot impact the WWTP in such a way that causes a KPDES permit violation. A means for disinfecting and dechlorinating (if needed) needs to be provided if normal disinfection operations at the

WWTP are inhibited, stopped, or interrupted. This can be temporary UV disinfection, chlorine tablets with dechlorination, point of use liquid sodium hypochlorite with dechlorination, point of use peroxyacetic acid (PAA), underground or above ground temporary 2” PVC chlorine dosing line. If using 12.5% sodium hypochlorite the line does not need to be buried as the freezing point is approximately -15 degrees Fahrenheit. The contractor can choose to bury if desired. Contractor should coordinate with Park staff for application of liquid at existing tie in point at effluent structure.

2. The specification calls for unclassified excavation. A significant amount of rock is expected to be encountered according to the

Geotech Report along with potential unsuitable soil and groundwater. Would the owner/engineer entertain an allowance to cover any rock removal/structural remediation for unsuitable soils.

No allowance will be provided for rock removal or for unsuitable soils. There is a Geotechnical Report in Appendix A to aid with decision making and risk assessment.

Addendum Four